Loading...
HomeMy WebLinkAboutPR 15442: MASON CONSTRUCTION COMPLETION OF PUBLIC WATER SYSTEM IMPROVEMENTS AT TOTALMEMORANDUM CITY OF PORT ARTHUR UTILITY OPERATIONS DEPARTMENT TO: Stephen Fitzgibbons, City Manager FROM: Kelly Eldridge, Director of Utility Operations DATE: Augus[ 17, 2009 SUBJECT: Proposed Resolution No. 15442 COMMENTS RECOMMENDATION I recommend that the City Council approve Proposed Resolution No. 15442, which accepts the Engineer's Certificate of Completion, Contractor's Certificate of Guarantee, and Contractor's Certificate and Release from Mason Construction Ltd., for the completion of public water system improvements to serve TOTAL -Port Arthur Refinery. BACKGROUND TOTAL developed a tract of land located at 39'~ Street and Locust Ave. TOTAL granted the City an easement for the water system in an accompanying Proposed Resolution. Their contractor, Mason Construction, Ltd., subsequently performed this work in accordance with City Standards and the improvements are ready for acceptance by the City. BUDGET/FISCAL EFFECT None. STAFF/EMPLOYEE EFFECT City staff attended the Final hLSpection of these utilities to verify conformance with City Standards. SUMMARY Approval of Proposed Resolution No. 15442 is recommended. P.R No. 15442 08/17/09 aw RESOLUTION NO. A RESOLUTION AUTHORIZING ACCEPTANCE OF AN ENGINEER'S CERTIFICATE OF COMPLETION FROM JOEL K NEELY, P.E. OF RICHARD DESIGN SERVICES, INC. AND CONTRACTOR'S CERTIFICATE AND RELEASE AND CONTRACTOR'S CERTIFICATE OF GUARANTEE FROM MASON CONSTRUCTION, LTD. FOR THE COMPLETION OF PUBLIC I1~IPROVEMENTS (PUBLIC WATER SYSTEM) TO SERVE TOTAL, AND AUTHORIZING THE CITY MANAGER TO SIGN THE CERTIFICATE OF ACCEPTANCE ON BEHALF OF THE CITY OF PORT ARTHUR, TEXAS. WHEREAS, TOTAL planned and developed a tract of land for the purpose ofproviding fire protection and domestic water use; and, WHEREAS, TOTAL granted utility easements for these public improvements; and, WHEREAS, TOTAL contracted with Mason Construction, Ltd. for construction of the public water system throughout this development; and, WHEREAS, the City has received an Engineer's Certificate of Completion dated August 14, 2009 from Joel K Neely, P. E. of Richard Design Services, Inc., certifying that the water system in the project has been completed according to City Standards, copy attached hereto and made a part hereof as Exhibit A, together with a Contractor's Certificate and Release (Exhibit B) and a Contractor's Certificate of Guarantee (Exhibit C) executed by Charles Mason, President of Mason Construction, Ltd.; NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: Section 1. That the City Manager of the City of Port Arthur is hereby authorized to P.R No. 15442 08/17/09 aw Page 2 execute on behalf of the City of Port Arthur a Certificate of Acceptance (Exhibit D) for the completion of the public water and sewer infrastructure. Section 2. That a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED THIS day of 2009 at a Regular Meeting of the City Council of the City of Port Arthut, Texas, by the following vote: AYES: Mayor Councilmembers: NOES: Deloris Prince Mayor ATTEST: Terri Hanks City Secretary APPROVED AS TO FORM: Mark Sokolow City Attorney APPROVED: Stephen Fitzgibbons City Manager Kelly Eldridge ~ Director of Utitity Operations EXHIBIT A ;- w w w K/I ~ ,.wv RICNRRO DESIGN SERVICES, INC. Richard Design Services, Inc. 1308 Boston Ave., Suite 200 Nederland, Texas 77627 Office: 409-727-3881 Fax: 409-727-3427 Aug. 14ei, 2009 City of Port Arthur P.O. Box 1089 Port Arthur, Texas 77641-1089 Attn: Mr. Kelly Eldridge. Re: Fire Water Loop, and Domestic Line for Total Petrochemical's Phase 1 Modular Mobile Office Trailer Complex, ENGINEERS CERTIFICATE Gentlemen: I, Joel K.Neely, P.E., hereby certify that the Fire Water Loop, and Domestic Line for Total Petrochemicals Phase 1 Modulaz Mobile Office Trailer Complex, was constructed in general conformance with the approved plans and specifications. The pressure test and bacteria testing was done and or witnessed by your Mr. Warren Guidry. All tests passed. We request that the infrastructure be accepted by the City of Port Arthur. Should you have any questions, please call. Respectfully submitted, q ~ ~ ~~ Joel K. Neely, P.E. Design Engineer ~ ineely(uu~richarddesienservices com y c. Mr. Ross Blacldcetter, P.E. JQEL K. NEELY 67452 ~- ~~lt~'1 ~'I~ESS~7RE TEST Connpan~ Ptia~ne: TOTAL Address: 39TH ST & LOCUST AVI;/ Date: 0712$109 Pipe Size: 8" C-900 PVC Pressure Reading: PSI u5~ Meter Reading: 3737.051 Time: 13:00 P.M. Two Hours Pressure Readiug: PSI ~ G ~, Meter Reading: 3737.082 Time: 16:00 P.M. Flush Line Sample Good: Bad: Date• 43 ' ~ ~'Z.U L~ ~{ Signature: ~~ ~~ ~lL~ C-rY of rO-r-' n-rrnul( CHAIN-OF-CU5"IOUY WATER P[1RTF7CATTnN Pi,ANT Company: Tf1TA7. PF.TR(1C'HF.M T(`AT. Address: 7600 32nd STREET I'.O. l{O\ 11189 furl iArlhur, "f)i 77641-11189 11111 ILU. dills lilctl 1'orl :~rlhur, I'X 7764(1 SI(e: 79"iA i.ll('rIRT 2 T.AriRET, Diu Tlh~cr ___S AMJJ$T, __ Sample Nn. Sample Lucniion ILiic (~allci~rt~d liinc ~ u0atcd ti;nnplr r, pc ~ ~~~~~.i Cpo~cil Uiw Gish ll~nq~ l~~mi,iiun tiiic l'I? Kcsidir,il :\n;ih si. KcyucsicJ 3938 r.ocust 7/29/0 11:03 X X Total Coliforttl 1 393A Locust 7/30/0 11:13 x X 3,p __ Total (oliform Relinyuislied by: Trtc/Tin Rccci~t•d hc: bile/Tim Relinquished by: Ualei'I ime______,________ Itecri~ccl hc: Uuld lime Received Cor Laboratory by: Samuel _Ualc/I imc 7/_310.9..-.---------.._~\nalvsl tiignaunc_~~ ~k ~~iti+..esU Test Resuhs'Cotal Coliform:_ Not Found - SamolP Good EXHIBIT B TOTAL Port Arthur Refinery August 11, 2009 Mr. Kelly Eldridge Water Utilities Department City of Port Arthur P. O. Box 1089 Port Arthur, Texas 77641 Subject: Fire Water and Domestic Line for TOTAL office setting at 39th street and Locust Dear Mr. Eldridge: Please find enclosed an Engineers Certificate, which includes a Contractor's Certificate and Release document, and a Contractor's Certificate of Guarantee regarding the construction of a public water line that we would like the City of Port Arthur to accept. Should you have any questions, please contact me at 409-963-6050 or by email to Tom.Henrvna.total.com . Sincerely, Tom Henry Manager, Finance & Business Systems THE/bw: jln Attach: (3) cc: File (1) TOTAL P. O. Box 849, Part Arthur, TX 77641-0849 Hvry 366 & 32n° Street, Port Arthur, TX 77642 Tel_ 409.963 fi800 -Fax: 409.962.8870 TOTAL MASON CONSTRUCTION, LTD . INDUSTRIAL AND CIVIL CONTRACTORS 6285 WALDEN ROAD, BEAUMONT, TX 7 7 70 7-5 599 P.O. Box 20057, BEAUMONT, Tx 7 7 7 20-005 7 PHONE (409)842-4455 FAX (409)842-4586 MAIL@MASONCONSTRUCTION.NET August 10, 2009 City of Port Arthur 444 4`h Street Port Arthur, Texas Reference: Release of Lien and One Year Warranty To whom it may concern: Please find the Release of Lien and One Year Warranty for the New Water Line installed for Total in the Fairlea Addition, Port Arthur, Texas. Regards, o~Voan Mason Construction, Ltd. BUILDING ON A FOUNDATION OF INTEGRITY - SINCE IJ39 CONTRACTOR'S CERTIFICATE AND RELEASE FROM: Mason Construction Ltd. (Name of Contractor) TO: City of Port Arthur ( Local Public Agent) REFERENCE CONTRACT NO. NIA ENTERED INTO THE DAY OF BETWEEN THE CITY OF PORT ARTHUR OF JEFFERSON COUNTY, TEXAS AND Mason Construction Ltd. (Name of Company) OF Beaumont Texas (CITY) (STATE) FOR THE New Water Line installed for TOTAL in the Fairlea Addition (Name of Operations) LOCATED IN THE CITY OF PORT ARTHUR, TEXAS: KNOW ALL MEN BY THESE PRESENTS: The undersigned hereby certifies that there is due from and payable by the Local Public Agency to the Contractor under the contract and duly approved Change Orders and modifications the balance of $0.00 2. The undersigned further certifies that in addition to the amount set forth in paragraph 1, there are outstanding and unsettled the following items which he claims are just and due and owing by the City to the Contractor; (b) (c) Page 1 of 3 (d) IVlH (Itemize claims and amounts due) (if none, so state) 3. The undersigned further certifies that all work required underthis contract including work required under change orders numbered 0 has been performed in accordance with the terms thereof, and that there are no unpaid claims for materials, supplies or equipment and no claims of laborers or mechanics for unpaid wages arising out of the performance of this contract, and that the wage rates paid by the Contractor and all Subcontractors were in conformity with the contract provisions relating to said wage rates. 4. Except for the amounts stated under paragraphs 1 and 2 hereof, the undersigned has received from the City of Port Arthur all sums of money payable to the undersigned under or pursuant to the above mentioned contract or any modification or change thereof. 5. That in consideration of the payment of the amount stated in paragraph 1 hereof the undersigned does hereby release the City of Port Arthur from any and all claims arising under or by virtue of this contract, except the amount listed in paragraph 2 hereof; provided, however, that if for any reason the City of Port Arthur does not pay in full the amount stated in paragraph 1 hereof, said deduction shall not affect the validity of this release, but the amount so deducted shall be automatically included under paragraph 2 as an amount which the Contractor has not released but will release upon payment thereof. The Contractor further certifies that upon the payment of the amount listed in paragraph 2 hereof, and of any amount which may be deducted from paragraph 1 hereof, he will release the City of Port Arthur from any and all claims of any nature whatsoever arising out of said contract or modification thereof, and will execute such further releases or assurances as the City of Port Arthur may request. IN WITNESS WHEREOF, the undersigned has signed and sealed this instrument this I"l~ day of _~tt US-E , 2~~ y_~ /'~f}~ ~„isf.~.~c rio/ Grh . (SEAL) (Contractor) ~i""~~~~ Pirv3~T (Signature and Title of Officer) ('yL~y(,~S t(Yll~~-Jr. -being first duly sworn on oath, deposes and says, Page 2 of 3 (Affiant) first that he is the ~.~Lr~ I~reS>dt~~-" of the (Title) MQSOri C,6Y1S'f1"t.LC~lbl'l~ )~ (Name of Company) second, that he has read the foregoing certificate by him subscribed as (Name Affiant further states that the matters and things stated herein are true. (Affiant) Subscribed and sworn to before me this ~~~ day of ~~~ ~~4 . My commission expires I l - I b - OG (Date) (Notary) ~z~''f ~ HALLIE SHORT NOTARY PUBLIC ` ~ ` STATE OF TEXAS m. ~ MY COMM. EXP. 1717 fil09 ~~OF Page 3 of 3 (~`f rL~G~6Y5 (,Q' .r~~'icuf2 ~ Vl~ ~e ~tCtSe of the Taal -\ EXHIBIT C CONTRACTOR'S CERTIFICATE OF GUARANTEE FROM: Mason Construction, Ltd. (Name of Contractor) TO: City of Port Arthur (focal Public Agent) REFERENCE CONTRACT NO. N/A ENTERED INTO THE DAY OF ,BETWEEN THE CITY OF PORT ARTHUR OF JEFFERSON COUNTY, TEXAS AND Mason Construction, Ltd. OF Beaumont Texas (CITY) (STATE) FOR THE New Water Line installed for TOTAL in the Fairlea Addition, (Name of Operations) LOCATED IN THE CITY OF PORT ARTHUR, TEXAS: KNOW ALL MEN BY THESE PRESENTS: Mason Construction, Ltd. does hereby guarantee all of the work done under the above referenced contract to be free from faulty materials in every particular, and free from improper workmanship, and against injury from proper and usual wear; and agrees to replace or re-execute without cost to the Owner such work as maybe found to be improper or imperfect, and to make good all damage caused to other work or materials, due to such required replacement or re-execution. 2. This guarantee shall cover a period of one (1) year from the date of acceptance of all work under this Contract, as evidenced by the ACCEPTANCE OF THE IMPROVEMENTS BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR. 3. This Certificate is given in connection of the final payment under the contract between the City of Port Arthur and NIA and with the knowledge that it will be relied upon in making such payment and that such payment would not be made except upon the truth of the matter contained in this affidavit. Page 1 of 2 IN WITNESS WHEREOF, the undersigned has signed and sealed this instrument this l~~'' day of ~1,~ , 200`i /'l~.vs~.wdF;.~, ~ Lr~ - (SEAL) (~~~~~.e ~fin~vr ~~6611 (Signature and Title of Officer) (~,r (1t5 1'1'1.Q.5~'L Tr . ,being first duly sworn on oath, deposes and says, (Affiant) first, that he is the ~~e 5~1t~~-'t-f of the (Title) of Company) second, that he has read the foregoing certificate by him subscribed as C6Y~'h'UG-l-bl~ S CU-~t~iCC~-F-crv~ ~ l,caf u-+'1-f~ C of the (Title) _ _ _ of Company) Affiant further states that the matters and things stated herein are true. (Affiant) Subscribed and sworn to before me this ~ day of ~~1uS+' 2004 My commission expires ll-l(o-O`t (Date) .~aa..~~~~-nom (Notary) .~~'"""~ w~LUesHORr NOTARY PUBLIC ~ * STATE OF TEXAS a?q~~ MY COMM. D(P.11/16109 Page 2 of 2 EXHIBIT D CERTIFICATE OFACCEPTANCE FOR Construction of the Public Water System to Serve TOTAL IN THE CITY OF PORT ARTHUR TO: Mason Inc. & TOTAL Inc. Gentlemen: This is to certify that the City of Port Arthur, Texas, accepts the completion of the public water system for the above development on the basis of the Engineer's Certificate of Completion, the Contractor's Certificate of Guarantee, and the Contractor's Certificate and Release, executed by Stephen Fitzgibbons City Manager ATTEST: Terri Hanks City Secretary