PR 22943: SABINE PASS PIPEBURSTING PROJECT NO. 2, CHANGE ORDER NO. 1
City of ort rthur INTEROFFICE MEMORANDUM Date: December 22, 2022 To: The Honorable Mayor and City Council Through: Ronald Burton,City Manager From: Calvin Matthews, P.E., Water Utilities Director RE: PR 22943 —Sabine Pass Pipebursting Project No. 2, Change Order No. 1 Introduction: The intent of this Agenda Item is to seek City Council's approval of Change Order No. 1 for the City of Port Arthur Sabine Pass Pipebursting Project No. 2 with Global Drilling, Inc. as the contractor. Resolution No. 22-300, which awarded the construction contract with a contract amount of$498,623.90. Change Order No. 1 has a contract time extension of 85 days and an increase of $107,070.00 with a new contract amount of $605,693.90. This change order is accepted by the Water Utilities Department because of weather days, manhole delays, and an increase in scope. The increased scope includes the rehabilitation of 3 manholes, 1,020 feet of 8" sewer line, and 400 feet of 6" slipped line. Background: On July 5, 2022, the Council passed Resolution No. 22-300, which awarded Global Drilling, Inc. with the construction phase of the Sabine Pass Pipebursting Project No. 2 contract, in the original contract amount of $498,623.90 (project designed by Golden Triangle Consulting Engineers and managed by City Staff). Bucket Impact: Change Order No. 1, if passed by Council, will extend the project time by 85 days and an increase of $107,070.00 with a new contract amount of $605,693.90. Funds are available in Account No. 405-40-000-8516-00-00-000, Project No. WS-0006-CON. Recommendation: It is recommended that City Council adopt Proposed Resolution No. 22943, thereby extending the contract end date and increasing the contract amount, as described/outlined above. "Remember,we are here to serve the Citizens of Port Arthur" PR No. 22943 12/22/2022 bw Page 1 of 3 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND GLOBAL DRILLING, INC. OF WINNIE, TEXAS FOR THE SABINE PASS PIPEBURSTING PROJECT NO. 2, INCREASING THE CONTRACT TIME BY 85 DAYS,WITH A NEW CONTRACT END DATE OF MARCH 8, 2023 AND INCREASING THE CONTRACT AMOUNT BY $107,070.00 WITH A NEW CONTRACT AMOUNT OF $605,693.90; FUNDING IS AVAILABLE IN ACCOUNT NO. 405-40-000- 8516-00-00-000, PROJECT,NO.WS-0006-CON. WHEREAS, pursuant to Resolution No. 22-300, City Council awarded a contract to Global Drilling, Inc. of Winnie, Texas for the construction phase of the Sabine Pass Pipebursting Project No. 2 for the amount of$498,623.90; and, WHEREAS, Change Order No. 1 includes a contract time extension of 85 days and contract price of$107,070.00; and, WHEREAS, Change Order No. 1, if accepted, would bring the new contract end date to March 8, 2023, and increase the contract amount to $605,693.90; and, WHEREAS, the increased scope includes the rehabilitation of 3 manholes, 1,020 feet of 8" sewer line, and 400 feet of 6" slipped line; and, WHEREAS, Change Order No. 1 (attached hereto as Exhibit "A") is submitted for the construction of the Sabine Pass Pipebursting Project No. 2. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT,the facts and opinions in the preamble are true and correct; and, THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to PR No. 22943 12/22/2022 bw Page 2 of 3 execute Change Order No. 1 to the contract with Global Drilling, Inc. of Winnie, Texas, extending the contract time by 85 days, bringing the new contract end date to March 8, 2023 and increasing the contract amount by $107,070.00 to a new contract amount of$605,693.90. THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ,ADOPTED,AND APPROVED THIS day of , 2023 at a Regular Meeting of the City Council of the City of Port Arthur, Texas,by the following vote: AYES: Mayor ; Councilmembers • NOES: Thurman"Bill" Bartie Mayor ATTEST: APPROVED AS TO FORM: Sherri Bellard Valecia Tizeno City Secretary City Attorney APPROVED FOR ADMINISTRATION: Ronald Burton City Manager PR No. 22943 12/22/2022 bw Page 3 of 3 Calvin Matthews, P.E. Water Utilities Director APPROVED AS TO AVAILABILITY OF FUNDING1: 1)<Cil./ (1)c-_,L Kandy Daniel y Clifton Williams, CPPB Finance Director Purchasing Manager EXHIBIT A (Change Order No. 1) CHANGE ORDER NO. 1 ORIGINAL AGREEMENT DATE: July 5, 2022 PROJECT DESCRIPTION: Sabine Pass Pipebursting Phase 2 REASON: Rain days,manhole delays, and the rehabilitation of 3 manholes, 1,020 feet of 8" sewer line, and 400 feet of 6" slipped line added to original scope CHANGE TO CONTRACT AMOUNT: ORIGINAL CONTRACT PRICE: $498,623.90 CURRENT CONTRACT PRICE (adjusted by previous CHANGE ORDER): $498,623.90 The Contract Amount due to this CHANGE ORDER will increase by: $107,070.00 The new CONTRACT AMOUNT including the CHANGE ORDER will be: $605,693.90 ORIGINAL CONTRACT DAYS: 120 NEW CONTRACT DAYS: 85, ending March 8, 2023 SIGNED AND AGREED TO on the_day of , 2023. GLOBAL DRILLING Print Name: Title: SIGNED AND AGREED TO on the_day of , 2023. CITY OF PORT ARTHUR BY: RONALD BURTON, CITY MANAGER GLOBAL DRILLING,INC. C LGLe,B AL 44994 Interstate 10 Winnie,Texas 77665,USA T:+1 800 956 8720;E:info©globaldrillingequipment.com, itjr !Nf W:www.olobaldrillinaequi0ment.com Project: Rehabilitate 8" Diameter Sanitary Sewer Pipe by Pipe Bursting Using 8"SDR-17 HDPE Pipe Location: Sabine Pass,Port Arthur Texas 77655 INo.of Days Date Weather Condition 1 August 24,2022 Raining 2 August 26,2022 Heavy Rain 3 August 29,2022 Heavy Rain 4 August 30,2022 Heavy Rain 5 September 3,2022 Heavy Rain 6 September 4,2022 Heavy Rain 7 September 16,2022 Raining 8 September 29,2022 High Tide 9 September 30,2022 High Tide 10 October 28,2022 Raining 11 November 1,2022 Raining 12 November 14,2022 Raining 13 November 19,2022 Raining 14 November 21,2022 Raining 15 November 22,2022 Raining 16 November 24,2022 Raining 17 November 25,2022 Raining 18 November 26,2022 Raining 19 November 27,2022 Raining 20 November 28,2022 Raining 21 December 11,2022 Raining 22 December 14,2022 Raining OTHER REMARKS PRODUCTION AND DELIVERY OF MANHOLE 12 Delayed for 12-Days due to Production Schedule (Approved Submittal:September 1,2022) (Delivery Date:September 12,2022)