HomeMy WebLinkAboutPR 22978: EDC, INSTALLATION OF A NATURAL GAS GENERATOR 0
c
PORT*ARTHUR
DEVELOPMENT CORPORATION
MEMORANDUM
Date: January 19, 2023
To: City of Port Arthur Council Members
Through: Ronald Burton, City Manager
From: Terry Stokes, PAEDC Chief Executive Officer
RE: PR-22978 I A resolution authorizing the City of Port Arthur Section 4A Economic
Development Corporation approving a quote from Panama Equipment of
Cleveland, Texas and engaging their services to purchase and install a 200kw 3
phase natural gas generator at the PAEDC office building located at 501 Procter
Street; in an amount not to exceed$192,142.86. Funds available in EDC account
No. 120-80-625-8522-00-00-000
Introduction:
The intent of this resolution is to authorize the City of Port Arthur Section 4A Economic
Development Corporation approving a quote from Panama Equipment of Cleveland, Texas and
engaging their services to purchase and install a 200kw 3 phase natural gas generator at the PAEDC
office building located at 501 Procter Street.
Background:
For the safety and comfort of the tenants of the office building at 501 Procter Street, the PAEDC
intends to purchase and install a backup generator for the building. Quotes were requested of the
following vendors: A&A Electric, Jefferson Electric, Panama Equipment, and Newtron Electric.
Quotes were submitted by the following vendors: Panama Equipment and Jefferson Electric.
At their Regular Board Meeting of January 10, 2023, the PAEDC Board of Directors approved
acceptance of the quote submitted by Panama Equipment as it was the lowest price.
Recommendation:
It is recommended that the City Council of the City of Port Arthur authorize the City of Port Arthur
Section 4A Economic Development Corporation approving a quote from Panama Equipment of
Cleveland, Texas and engaging their services to purchase and install a 200kw 3 phase natural gas
generator at the PAEDC office building located at 501 Procter Street.
Budget Impact:
The budgetary impact is $192,142.86.
P.R. No. 22978
01/12/2023 KM/jc
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY OF PORT
ARTHUR SECTION 4A ECONOMIC DEVELOPMENT
CORPORATION APPROVING A QUOTE FROM PANAMA
EQUIPMENT OF CLEVELAND, TEXAS AND ENGAGING
THEIR SERVICES TO PURCHASE AND INSTALL A
200KW 3 PHASE NATURAL GAS GENERATOR AT THE
EDC OFFICE BUILDING LOCATED AT 501 PROCTER
STREET; IN AN AMOUNT NOT TO EXCEED $192,142.86.
FUNDS AVAILABLE IN EDC ACCOUNT NO. 120-80-625-
8522-00-00-000
WHEREAS, the City of Port Arthur Section 4A Economic Development Corporation
(PAEDC) owns the property located at 501 Procter Street, Port Arthur. Texas and has the
commitment to maintain the safety and integrity of said premises; and
WHEREAS, a whole-building generator provides emergency power to keep an
organization active during a power outage; and
WHEREAS,for the safety and comfort of the tenants, a generator is necessary; and
WHEREAS,the PAEDC obtained two quotes for the purchase and installation of a whole-
building generator for the office building at 501 Procter Street; and
WHEREAS, Panama Equipment has provided the lowest quote that includes the purchase
of the generator, electrical labor, gas line labor, concrete labor, engineered drawings, galvanized
platform and complete generator start-up, as described in Exhibit"A"; and
WHEREAS, at their January 10, 2023 Regular Board Meeting, the PAEDC Board of
Directors approved the quote submitted by Panama Equipment for their services for a generator to
be installed at 501 Procter Street in the amount of$192,142.86.
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR:
Section 1. That the facts and opinions in the preamble are true and correct.
Section 2. That the City Council authorizes PAEDC to approve the Panama Equipment
quote and engage their services to purchase and install a generator at 501 Procter Street in the
amount of$192,142.86.
Section 3. That a copy of the caption of this Resolution be spread upon the Minutes of the
City Council.
READ,ADOPTED AND APPROVED on this day of A.D., 2023,
at a Meeting of the City Council of the City of Port Arthur,Texas,by the following vote:
AYES:
Mayor
Councilmembers
NOES:
Thurman Bartie,Mayor
ATTEST:
Sherri Bellard, City Secretary
APPROVED:
QQ r 1 - rkIS
Te Stokes,PAE � SCEO
APPROVED AS TO FORM:
j � �-
eharles E. Zech, PAEDC Attorney
APPROVED A TO FORM:
Votif ii
Val Tizeno,City Att ey
APPROVEDP AS TO AVAILABILIT F FUNDS:
9k Cti.�
Kandy Daniel, Finance Director
EXHIBIT "A"
PAN
EQUI ME QUOTE
P E N T
Customer:City of Port Arthur EDC DATE: December 34,2022
State:Texas
SCOPE OF WORK:
• Engineered Drawings
• Have all utilities marked around building before cunstruction start
• Purchase 200kw 3 Phase 480/277V Natural Gas Generator and 400 amp 3 Phase 480/277V ATS
• Cut out existing concrete where smoking area is currently,Cut concrete out in driveway to trench for electrical line from
ATS to generator and gas line from meter to genertor.
• Install ATS and cut over after hours on a weekend
• Install electrical conduit in trench and stub up at where concrete generator pad will be Installed
• Install gas line and stub up where concrete generator pad will be installed
• Back fill trench and compact in 6 inch lifts
• Pour concrete over trench in existing alley drive way,pour generator pad.and new smoking area pad.
• Install 3'tall generator platform
• Set generator on platform
• Wire in generator to ATS to complete electrical
• Finish gas line plumbing from stub ups to generator
• Complete Generator Start-up
PANAMA EQUIPMENT
CONTACT INFO. CUSTOMER CONTACT INFORMATION
Name: Name: Phone Email:
Rene Trevino Krystle Villarreal-Muller (409)963-0579 kvillarreal-Muller PAEDC.ORG
Phone: Location Equipment ID Number Site Name v
281-68- 0 501 Procter St,Port
75 45 Arthur,TX7764o Emergency Generator PORT ARTHUR EDC BUILDING
QUANTITY DESCRIPTION UNIT PRICE LINE TOTAL
200kw 3 Phase
1.0o 480/277v Natural Gas Generator g 128,571.43 $ 228,571.43
400A 3 Phase 480/277v ATS
1.00 Electrical labor and Materials $ 20,000 00 $ 20,000.00
•
1.00 Gas Line Labor and Materials $ 17,857.14 $ 27,857.14
1.00 Concrete Labor and Materials ; $ 6,428.57 j $ 6,428.57
1.00 Engineered Drawings $ 10,714.29 I $ 20,714.29
2.00 3'tall galvanized Generator Platform $ 8,571.43 $ 8,572 43
Thank you for your business! TOTAL'; 8 192,142.86
General—Ouahficationsi0.M,rtrons
This document contains confidential and proprietary information.Its contents shall not be copied or distributed to third parties without the express written permission of Panama Equipment LLC
a.Proposal does not include any state sales tax(except for contractor consumable materials),gross receipt,or other taxes for this project.The customer is responsible to issue the contractor and the respective
subcontractors a`direct pay Femur and to accrue and pay any state saks or other taxes for this project.Buyer shall be responsible for any tax,interest,and penalty if such exemption certificate or direct payment
permf certificate Is disallowed by the proper taxing authority.
3 This proposal is based on the information provided by the customerandior owner or owners of legal record(If different)md includes installation of all materials and equipment as shown in the documents
provided as of the date of the proposal
a Work will be performed according to the drawings and information provided by the company being quoted.
5 Panama Equipment LLC will not accept any responsibilityo,charge for modifications,renal,servicing,and adjustment odor any other hems without the ath ,y In the forty of a purchase order in advance of
doing the work.
6.Panama Equipment LLC shall not under any circumstance be responsible for any additional cost,any loss or perceived lossby the customer.Pother,the customer shall wave any rights to charge back or deduct
from any payments due Parma Equipment LLC,any fees or costs the customer may have Incurred whereby Panama Equipment LLC didnot directly approve such fees or costs and was not in direct and complete
control for incurring such costs
].Removal of any unidentified obstructions and any associated delays or downtime due to same,wdl be considered as extras m this proposal
6.Any changes to these drawings or w drawings that are issued to Panama Equipment LLC at any time after the submittal ofour proposal will be considered an extra and priced accordingly on Change Ordet
Requests and submitted to at panes involved for rev w,approval,and budget increase before any work asociated wnh these changes takes place
g.Our standard labor and equipment races shall apply for any extra work.
so.My delays and/or work stoppages not caused by the deed result of Panama Equipment LLC or its direct subcontractors shall be considered extra and billed at the current contract rates
ss Upon completion of this project,Panama Equipment LLC willprovide all required documentation and inspection reports.
17.This quote is valid for 3o days.