HomeMy WebLinkAbout4. 20230411 Pipebursting updatePipebursting Update
April 11, 2023
Presented by Dr. Hani Tohme
Topics
Completed Projects by City Forces
Completed Projects by Contractors
Projects in the Bidding Phase
Advantages of In-House Pipebursting Crew
Questions
Introduction
In 2019,industry contributed a combined amount of $1.1 million for the City to
purchase equipment and start an in-house pipebursting crew.
Pipebursting includes replacement of sanitary sewer pipe,manholes and service
lines up to the property line.
Pipebursting Projects completed by
In-House Crew
Work by In-House Crew
Lexington/42nd Street Area
9th Avenue and Procter Street Area
Dodge Place
Avant Lane
Kramer Place
9th Avenue
Dixie Drive
3rd Street
4th Street
Procter Street
5th Street
6th Street
Dequeen/Gulfway Area
12th Street
13th Street
14th Street
9th Avenue/Gulfway Area
Stanley Boulevard
12th Street
13th Street
W of Savannah between Gulfway &Thomas Blvd
Thomas Boulevard
12th Street
13th Street
14th Street
15th Street
Houston Avenue/Gulfway Area
W 12th Street
W 13th Street
W 14th Street
W 15th Street
W 16th Street
W 17th Street
W 18th Street
W Reverend Doctor Ransom Howard Area
Roosevelt Avenue
Harding Avenue
Dunbar Avenue
Washington Avenue
Port Acres Area
65th Street
Anne Street
Sabine Pass Area
S. Gulfway
Greenwich Street
S. 11th Avenue
Mechanic Street
Progress
Year 2019 2020 2021 2022 2023
Total Footage 5,380 4,250 9,520 8,971 January-March 3,100
Projected 12,400
Cost per Foot $198 $250 $112 $118 $85
Completed Pipebursting
Projects by Contractors
Sabine Pass Pipebursting Project 1
Horseshoe Construction, La Porte, Texas
Pearl Street
S. 11th Avenue
Tremont Street
Sabine Pass Pipebursting Project 2
Global Drilling, Winnie, Texas
S. 14th Street
Buford Street
S. 11th Avenue
Tremont Street
S. 15th Street
S. Gulfway Drive
Sabine Pass Pipebursting Project 2 (cont’d)
Global Drilling, Winnie, Texas
S. 3rd Avenue
Mechanic Street
Lakeside (Stadium Road to Williams Avenue)
Horseshoe Construction, La Porte, Texas
Lakeshore Drive
Lakeside Drive
Sanitary Sewer System
Rehabilitation Plans –Bidding Phase
City-Wide Pipebursting Project
Projected cost $1M
22nd Street
8th Avenue
Procter Street
5th Street
6th Street
7th Street
8th Street
9th Street
10th Street
Sabine Pass Pipebursting 3 Project
Projected cost $500K
Pearl Street
Advantages of In-House Pipebursting Crew
Advantages of
In-House Pipebursting Crew
Ability to respond immediately to sanitary sewer cavities and blockages
Ability to replace pipe instead of patching failed spots
Ability to continue the pipebursting program when capital program funding is
not available
Pipebursting at a cost cheaper than contractors
Average per foot by City Forces -$119
Cost per foot by Contractor as per last bid contract -$226
Questions?