HomeMy WebLinkAboutPR 23121: CHANGE ORDER TO WITH GULF COAST FOR THE VARIOUS STREETS ROADWAY IMPROVEMENT PROJECT 410 City of ..', ort t-thur www.PortArthurTx.gov INTEROFFICE MEMORANDUM Date: April 27,2023 To: The Honorable Mayor and City Council Through: Ron Burton, City Manager // From: John Cannatella,PE,City Engineer RE: PR23121:Various Streets Roadway Improvement Project;District 2&3—Gulf Coast a CRH Company of Beaumont,Texas-Change Order#2 increasing the original contract amount by $499,205.60 for the removal of 7th Street entirely,adding Evergreen Drive (Bernhardt Drive to Dead End),the addition of cement stabilized backfill, and quantity adjustments on the remaining streets. Introduction: The intent of this agenda item is to authorize the City Manager to execute Change Order No.2 for the Various Streets Roadway Improvement Project; District 2 & 3 that increases the original contract amount by $499,205.60 for the removal of 7th Street entirely, adding Evergreen Drive (Bernhardt Drive to Dead End), the addition of cement stabilized backfill,and quantity adjustments on the remaining streets. Background: Pursuant to Resolution 22-399 the City of Port Arthur awarded a contract for Various Streets Roadway Improvement Project; District 2 & 3 to Gulf Coast a CRH Company of Beaumont, Texas. The contract was advertised and bid under P22-074 for the rehabilitation of twenty-three (23) streets for an amount of $10,208,437.93. Pursuant to Resolution 22-451, approved by Council, four(4) streets were removed from the twenty-three (23) streets, changing the new number of streets to a total of nineteen (19) streets. The original contract amount of $10,208,437.93 was reduced by$2,473,929.00 to the new contract amount of$7,734,508.93. Change Order No. 1 also reduced the original number of contract completion days from 700 calendar days by110 days to new contract number of completion days to 590 calendar days. The new contract completion date is October 2,2024. Change Order No.2 is being presented by Gulf Coast a CRH Company of Beaumont,Texas,for the entire removal of 7th Street from Stadium Road to Williams Avenue; the addition of Evergreen Drive from Bernhardt Drive to Dead End,the addition of cement stabilized backfill,and quantity adjustments on the remaining streets for the amount of$499,205.60. Change Order No. 2 will increase the original contract amount of$7,734,508.93 by $499,205.60 to the new contract amount of$8,233,714.53. "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 S:\Engineering\PUBLIC WORKS\PW-ENGINEERING\UP.PROJECTS\Year 2022\VARIOUS STREETS Phase 2 Dist 2-3\Change Orders\Change Order 2\Agenda Memo Dist 2-3 Change Order K2.docx Budget Impact: Funds are available in the Street Program,Capital Improvement Project Account No.307-21-053-8517-00-10- 000. Recommendation: It is recommended that the City of Port Arthur City Council approve PR 23121 with Gulf Coast a CRH Company of Beaumont,Texas,authorizing the City Manager to execute Change Order No.2 to the Various Streets Roadway Improvement Project-District 2 & 3; removing 7'1' Street from Stadium Road to Williams Avenue, adding Evergreen Drive (Bernhardt Drive to Dead End), adding cement stabilized backfill, and adjusting quantities to the remaining streets for the amount of $499,205.60, increasing the original contract amount from $7,734,508.93 to the new contract amount of$8,233,714.53. "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 PRNo. 23121 4/27/2023 mje Page 1 of 4 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 2 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND GULF COAST A CRH COMPANY OF BEAUMONT, TEXAS, FOR THE VARIOUS STREETS ROADWAY IMPROVEMENT PROJECT-DISTRICT 2 & 3, REMOVING 7TH STREET (STADIUM ROAD TO WILLIAMS AVENUE), ADDING EVERGREEN DRIVE (BERNHARDT DRIVE TO DEAD END), ADDING CEMENT STABILIZING BACKFILL, AND ADJUSTING QUANTITIES ON THE REMAINING STREETS FOR THE AMOUNT OF $499,205.60; INCREASING THE PREVIOUS CONTRACT AMOUNT OF $7,734,508.93 TO THE NEW TOTAL CONTRACT AMOUNT OF $8,233,714.53. FUNDING IS AVAILABLE IN THE CAPITAL IMPROVEMENT PROJECT ACCOUNT 307-21-053-8517-00-10-000. WHEREAS, pursuant to Resolution No. 22-399, the City Council awarded a contract for the Various Streets Roadway Improvement Project-District 2 &3 to Gulf Coast a CRH Company of Beaumont, Texas, with a projected budgetary impact of $10,208,437.93; and, WHEREAS, pursuant to Resolution 22-451, approved by Council, four (4) streets were removed from the twenty-three (23) streets, changing the new number of streets in the improvement program to nineteen (19) streets; and, WHEREAS, Change Order No. 1 reduced the original contract amount of $10,208,437.93 by $2,473,929.00 resulting in the new contract amount of $7,734,508.93; and, WHEREAS, additionally, Change Order No. 1 reduced the original number of contract completion days from 700 calendar days by 110 days to 590 calendar days resulting in the new contract completion date of October 2, 2024; and, E:\a.Desktop\Agenda Items\PR 23121 Dist 2-3 CO No.2.docx PR No. 23121 4/27/2023 mje Page 2 of 4 WHEREAS, proposed Change Order No. 2 is being presented by Gulf Coast a CRH Company of Beaumont, Texas, for the removal of 7th Street (Stadium Road to Williams Avenue), the addition of Evergreen Drive (Bernhardt Drive to Dead End), the addition of cement stabilized backfill, and adjustments to quantity for the remaining streets, see Exhibit A; and, WHEREAS, proposed Change Order No. 2 will add $499,205.60 to the contract, increasing the contract amount of $7,734,508.93 to a new total contract amount of $8,233,714.53; and, WHEREAS, approval of Change Order No. 2 is herein deemed an appropriate action; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the facts and opinions in the preamble are true and correct; and, THAT, Change Order No. 2 is herein approved and the City Manager is hereby authorized to execute said Change Order No. 2 to the contract between the City of Port Arthur and Gulf Coast a CRH Company of Beaumont, Texas; and, THAT, Change Order No. 2 presented by Gulf Coast a CRH Company of Beaumont, Texas, for the removal of 7th Street (Stadium Road to Williams Avenue), the addition of Evergreen Drive (Bernhardt Drive to Dead End), the addition of cement stabilized backfill, and adjustments to quantity for the remaining streets; and, PR No.23121 4/27/2023 mje Page 3 of 4 THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED this the day of , A.D. 2023 at a meeting of the City of Port Arthur, Texas by the following vote: Ayes: Mayor: Council members: Noes: Thurman Bill Bartie Mayor ATTEST: Sherri Bellard City Secretary APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION: Valecia Tiz no, Esquire Ron Burton City Attorney City Manager S:\Engineering\PUBLIC WORKS\PW-ENGINEERING\C.I.P.PROJECTS\Year 2022\VARIOUS STREETS Phase 2_Dist 2-3\Change Orders\Change Order 2\PR 23121 Dist 2-3 CO No.2.docx PR No.23121 4/27/2023 mje Page 4 of 4 APPROVED AS FOR AVAILABILITY OF FUNDS: KC �- ,r, cA_A,\.__ID Kandy K. Dani Director of Finance Flozelle C. Roberts, EIT, MEng, MBA Director of Public Works dada/06'4 611 41(4 t Cli on Williams, CPPB Purchasing Manager EXHIBIT A Page 1 of 2 CITY OF PORT ARTHUR Public Works Engineering DATE: APRIL 13,2023 PROJECT: VARIOUS STREET REHABILITATION-DIST 2&3 OWNER: CITY OF PORT ARTHUR CONTRACTOR: GULF COAST A CRH COMPANY OF BEAUMONT,TX CHANGE ORDER NO.: 2 THE FOLLOWING CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE HEREBY MADE: Adjust the Estimated Quantities to reflect the Actual Quantities used in the completion of the project: Item Item Description Unit Original Unit Price Original New Quantity Added New Amount No. Code Quantity Amount DISTRICT 2 Duff Dr(Procter St to Lakeshore Dr)-(ST3035) 1 400.005 CEM STABIL BKFL TON 0 $ 96.50 $ - 160 $ 15,440.00 Pecos Ave(Lewis Dr to 7th St)-(ST3038) 1 400.005 CEM STABIL BKFL TON 0 $ 96.50 $ - 433 $ 41,784.50 Williams Ave(Lewis Dr to 6th Ave)-(ST3039) 1 400.005 CEM STABIL BKFL TON 0 $ 96.50 $ - 514 $ 49,601.00 $ Lakefront Dr(T.B.Ellison Pkwy to N.Levee)-(ST4002) $ - 1 247.002 FLEX BASE(TY A)(GR 1-2)(4")(COMPL IN PL) SY 7,251 $ 17.50 $ 126,892.50 3527 $ 61,722.50 2 251.001 REWORKING BASE COURSE(6")(ORD COMP) SY 3,175 $ 12.75 $ 40,481.25 6518 $ 83,104.50 3 310.001 PRIME COAT(AE-P) GAL 1,473 $ 9.80 $ 14,435.40 627 $ 6,144.60 4 340.001 D-GR HMA TY-D PG64-22(2")(SURFACE COURSE) TON 838 $ 200.00 $ 167,600.00 398 $ 79,600.00 $ - 7th St(Stadium Rd to Williams Ave)-(ST3047) $ - 1 REMOVAL OF STREET ENTIRELY FROM PROJECT $ 439,760.50 $ (439,760.50) DISTRICT 3 Evergreen Dr(Ferndale Dr to Griffing Dr)-(ST3054) 1 400.005 CEM STABIL BKFL TON 0 $ 96.50 $ - 351 $ 33,871.50 Tyrrell Pkwy(32nd St to Woodlawn St)-(ST4006) 1 400.005 CEM STABIL BKFL TON 0 $ 96.50 $ - 294 $ 28,371.00 Woodrow Dr(32nd St to Rosedale Dr)-(ST4003) 1 400.005 CEM STABIL BKFL TON 0 $ 96.50 $ - 302 $ 29,143.00 West Park Dr(32nd St to South Park Dr)-(ST4005) 1 400.005 CEM STABIL BKFL TON 0 $ 96.50 $ - 205 $ 19,782.50 Sunken Court(Rosedale Dr to South Park Dr)-(ST4007) 1 132.001 EMBANKMENT(VEHICLE)(ORD COMP)(TY C) CY 0 $ 60.90 $ - 586 $ 35,687.40 2 247.002 FLEX BASE(TY A)(GR 1-2)(2")(COMPL IN PL) SY 3,789 $ 8.50 $ 32,206.50 2283 $ 19,405.50 3 251.001 REWORKING BASE COURSE(6")(ORD COMP) SY 3,789 S 5.50 $ 20,839.50 2283 $ 12,556.50 4 275.001 CEMENT TREAT(MIX EXST MTL&NW BS)(8")(DC) SY 3,789 $ 6.55 $ 24,817.95 2283 $ 14,953.65 5 275.002 CEMENT SUPER SLURRY(4%)(DRY WT)(DEL)(COMPL IN PL) TON 61 $ 367.00 $ 22,387.00 37 $ 13,579.00 6 310.001 PRIME COAT(AE-P) GAL 758 $ 9.75 $ 7,390.50 457 $ 4,455.75 7 340.001 D-GR HMA TY-D PG64-22(2")(SURFACE COURSE) TON 438 $ 187.10 $ 81,949.80 264 $ 49,394.40 8 340.002 D-GR HMA TY-D PG64-22(1.5")(TRANSITIONS) TON 95 $ 269.50 $ 25,602.50 94 $ 25,333.00 9 400.005 CEM STABIL BKFL TON $ 96.50 $ - 326 $ 31,459.00 10 479.002 ADJUSTING MH(LIDS&COVERS) EA 1 $ 877.00 $ 877.00 1 $ 877.00 11 529.001 CONCRETE CURB&GUTTER COMBINED(COMPL IN PL)(TY I) LF 0 $ 36.40 $ - 2489 $ 90,599.60 Evergreen Dr(Bernhardt Dr to Dead End)-(ST0000) 1 104.001 REMOVING CONCRETE(CURB&GUTTER COMBINED)(INCL SAW CUT) LF 0 $ 3.95 $ - 1155 $ 4,562.25 2 251.001 REWORKING BASE COURSE(6")(ORD COMP) SY 0 $ 7.25 $ - 1467 $ 10,635.75 3 275.001 CEMENT TREAT(MIX EXST MTL&NW BS)(8")(DC) SY 0 $ 8.75 $ - 1467 $ 12,836.25 4 275.002 CEMENT SUPER SLURRY(4%)(DRY WT)(DEL)(COMPL IN PL) TON 0 $ 367.00 $ - 18 $ 6,606.00 5 310.001 PRIME COAT(AE-P) GAL 0 $ 11.15 $ - 293 $ 3,266.95 6 340.001 D-GR HMA TY-D PG64-22(2")(SURFACE COURSE) TON 0 $ 220.00 $ - 170 $ 37,400.00 7 340.002 D-GR HMA TY-D PG64-22(1.5")(TRANSITIONS) TON 0 $ 415.00 $ - 47 $ 19,505.00 8 340.003 D-GR HMA TY-D PG64-22(1.5"-3")(DRWYS) TON 0 $ 2,400.00 $ - 3 $ 7,200.00 9 400.005 CEM STABIL BKFL TON 0 $ 96.50 $ - 144 $ 13,896.00 S:\Engineering\PUBLIC WORKS\PW-ENGINEERING\C.I.P.PROJECTS\Year 2022\VARIOUS STREETS Phase 2_Dist 2-3\Change Orders\Change Order 2\Gulf Coast CO#2 10 479.001 ADJUSTING INLETS(LOWER INLET TOPS)(6"-12") ' EA 0 5 5,825.00 f$ 1: i 52� 9.0 CONCRETE CURB&GUTTER COMBINED(COMPL IN PLHTY 1 S :1,650.00 �i ) LF 0 5 36.4C $ :155 5 42,042.00 1 Miscellaneous DISTRICT 2&3 ROADWAY EXCAVATION&BACKFILL(6"-S'((LIMESTONE BASE) DRIVEWAYS(REMOVE&REPLACE) TON 0 $ 175.00 I$ - IXS :7,500.00 SF 0 I S 5C-CC 'I S ( 100 $ 5,000.00 TOTAL CHANGE ORDER $ 499,205.60 I ORIGINAL CONTRACT AMOUNT $ 7,734,508.93 NEW CONTRACT AMOUNT ORIGINAL CONTRACT AMOUNT:I 5 10,208,437.93 TOTAL AMOUNT OF CHANGE ORDER NO.1: (2,473,929.001 TOTAL: $ 7,734,508.93 TOTAL AMOUNT OF CHANGE ORDER NO.2: $ 499,205.60 PERCENT OF CHANGE ORDER NO.1: -24.23% PERCENT OF CHANGE ORDER NO.2: 4.89% TOTAL PERCENT OF CHANGE ORDER NOs.1&2: -19.34% NEW CONTRACT AMOUNT: S 8.233.714.53 ORIGINAL CONTRACT COMPLETION DATE: October 2,2024 NO CALEN R AYS HAVE BEEN ADDED TO CHANGE ORDER NO.2 PREPARED BY: REVIEWED BY: ,/,6tt Jennif r dwards,BAAS,MBA; CIP Manager Martin Flood,Project Manager I� APPROVED BY: APPROVED BY: 7 Zach Legetect Manager;Gulf Coast a CRH Company John Cannatella,PE,City Engineer APPROVED BY; APPROVED BY: Flozeile C.Roberts,EIT,MEng,MBA, Director of Public Works Clifton Williams,CPPB,Purchasing Manager APPROVED BY: Ron Burton,City Manager C:\Users\zacn.leggett\AppData\Local\Microsoft\W;ndows\WetCache\Content.0utlook\L7EBE26G\Gulf Coast CO#2