HomeMy WebLinkAboutPR 23128: SANITARY SEWER SYSTEM REHAB City of
tifiort rt
Texas
INTEROFFICE MEMORANDUM
WATER UTILITIES DEPARTMENT-ADMINISTRATION
Date: April 27, 2023
To: The Honorable Mayor and City Council
Through: Ronald Burton, City Manager
From: Calvin Matthews, P.E., Water Utilities Director
RE: PR No. 23128 — Sanitary Sewer System Rehabilitation Contract No. 1
Introduction:
The intent of this Agenda Item is to seek Council's approval for the City Manager to execute a
contract with King Solutions, Inc. of Houston, Texas for the pipebursting of sanitary sewer
mains in Port Arthur. King Solutions submitted the lowest bid with a total projected budgetary
impact of$1,419,884.00.
Backjround:
The wastewater collection system in Port Arthur is in need of rehabilitation and the Water
Utilities Department wishes to enter into a contract with King Solutions, Inc. of Houston,
Texas for the pipebursting of sanitary sewer mains.
Budget Considerations:
This project will be funded through Water Utilities Capital Improvement Fund and charged to
Account No. 405-40-000-8516-00-00-000, Project No. WS-0016-CON.
Recommendation:
I recommend that City Council approve Proposed Resolution No. 23128 authorizing the
execution of a contract with King Solutions, Inc. of Houston, Texas as described/outlined
above.
PR No. 23128
4/27/23 bw
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE A CONTRACT WITH KING SOLUTIONS
OF HOUSTON, TEXAS, FOR THE PIPEBURSTING OF
SANITARY SEWER MAINS IN PORT ARTHUR, TEXAS
WITH A TOTAL PROJECTED BUDGETARY AMOUNT OF
$1,419,884.00; FUNDING AVAILABLE IN ACCOUNT NO.
405-40-000-8516-00-00-000,PROJECT NO. WS0016-CON.
WHEREAS, the City's sanitary sewer system needs rehabilitation and staff has
recommended that the work be perform by contractors through competitive sealed bids; and,
WHEREAS, pursuant to the Texas Local Government Code Chapter 252.043, (d-1), a
contract for construction of a project described by Subsection (d) that requires an expenditure of
$1.5 million or less may be awarded using the competitive sealed proposal procedure prescribed
by Subchapter D, Chapter 2269, Government Code; and,
WHEREAS, on March 11, 2023 and March 18, 2023, the Purchasing Division of the
Finance Department advertised for bids for the sanitary sewer system rehabilitation and a total of
three bids were received on April 14, 2023 (Exhibit"A"); and,
WHEREAS, the Water Utilities Dept. reviewed the bids, and recommends awarding the
contract to King Solutions of Houston, Texas who submitted the lowest responsive bid.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT,the facts and opinions in the preamble are true and correct; and,
THAT,the City Manager of the City of Port Arthur is hereby authorized and directed to
execute a contract with King Solutions, Inc. of Houston, Texas in substantially the same form
attached hereto as Exhibit "B", for the sanitary sewer mains in Port Arthur, Texas with a total
projected budgetary amount of$1,419,884.00; and,
PR No. 23128
4/27/23 bw
Page 2 of 2
THAT, said funding for this contract is being provided through Water Utilities Capital
Improvement Fund 405-40-000-8516-00-00-000, Project No. WS0016-CON; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ,ADOPTED AND APPROVED THIS day of , 2023 at a
Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor ;
Councilmembers ;
NOES:
Thurman Bill Bartie
Mayor
ATTEST: APPROVED AS TO FORM:
Sherri Bellard Valecia Tizeno
City Secretary City Attorney
APPROVED FOR ADMINISTRATION: APPROVED FOR FUNDING:
*CA.J\_ 00kA"----4
Ronald Burton Kandy Dan' 1
City Manage Finance Director
' `Ct CCQCA.1 - l
Calvin Matthews, P.E. Clio on Williams, CPPB
Water Utilities Director Purchasing Manager
EXHIBIT "A"
BID TABULATION WITH DESCRIPTIONS OF ITEMS)
BID TABULATION
SANITARY SEWER SYSTEM REHABILITATION CONTRACT NO.1
BID OPENING DATE:Thursday April 14,2023 @ 3:15 PM
The Bid Proposals submitted have been reviewed and to the best of my knowledge
this is an accurate tabu tion of the bids received.
By: � -
Dr.Hani Tohme,Golden Triangle Consulting Engineers Date:4/27/23
Horseshoe Construction,Inc. King Solutions Global Drilling
ITEM NO. QTY DESCRIPTION La Porte,Texas Houston,Texas Winnie,Texas
James Holt Mario Jaimes Baker Mohammad
UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL
Mobilization costs,including payment bond,
performance bond,insurance,moving equipment
ITEM NO.1 1 to project,and project sign,all in strict accordance $ 60,000.00 $ 60,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00
with the plans and specifications;NOT TO
EXCEED 4%of total project cost,for
Rehabilitate 8"Diameter Sanitary Sewer Pipe by
Pipe Bursting Using 8"SDR-17 HDPE Pipe,
complete in place,all depths,including liner pipe,
ITEM NO.2 5,884 connection to manholes,bypass pumping, $ 65.00 $ 382,460.00 $ 40.00 $ 235,360.00 $ 72.00 $ 423,648.00
cleaning,well points,surface restoration,testing
and necessary appurtenances,all in strict
accordance with plans and specifications for
Rehabilitate 10"Diameter Sanitary Sewer Pipe by
Pipe Bursting Using 10"SDR-17 HDPE Pipe,
complete in place,all depths,including liner pipe,
ITEM NO.3 4,580 connection to manholes,bypass pumping, $ 75.00 $ 343,500.00 $ 46.00 $ 210,680.00 $ 88.00 $ 403,040.00
cleaning,well points,surface restoration,testing
and necessary appurtenances,all in strict
accordance with plans and specifications for
Rehabilitate 12"Diameter Sanitary Sewer Pipe by
Pipe Bursting Using 12"SDR-17 HDPE Pipe,
complete in place,all depths,including liner pipe,
ITEM NO.4 1,474 connection to manholes,bypass pumping, $ 100.00 $ 147,400.00 $ 60.00 $ 88,440.00 $ 112.00 $ 165,088.00
cleaning,well points,surface restoration,testing
and necessary appurtenances,all in strict
accordance with plans and specifications for
Rehabilitate 27"Diameter Sanitary Sewer Pipe by
Pipe Bursting Using 30"SDR-17 HDPE Pipe,
complete in place,all depths,including liner pipe,
ITEM NO.5 915 connection to manholes,bypass pumping, $ 400.00 $ 366,000.00 $ 305.00 $ 279,075.00 $ 254.00 $ 232,410.00
cleaning,well points,surface restoration,testing
and necessary appurtenances,all in strict
accordance with plans and specifications for
Furnish and Install 4"Sanitary Sewer Service Line
(Short Side),to include tap on proposed sanitary
sewer pipe,concrete cleanout box,cleanout,
ITEM NO.6 341 connection to existing sanitary sewer service line, $ 1,000.00 $ 341,000.00 $ 720.00 $ 245,520.00 $ 1,700.00 $ 579,700.00
complete in place including tapping saddle,
embedment,excavation,backfill,surface
restoration and testing all in strict accordance with
the plans and specifications for
Fumish and Install 4"Sanitary Sewer Service Line
(Long Side)to include tap on proposed sanitary
sewer pipe,concrete cleanout box,cleanout,
ITEM NO.7 15 connection to existing sanitary sewer service line, $ 1,500.00 $ 22,500.00 $ 1,050.00 $ 15,750.00 $ 1,800.00 $ 27,000.00
complete in place including tapping saddle,
embedment,excavation,backfill,surface
restoration and testing all in strict accordance with
the plans and specifications for
Post-Installation TV Inspection including all labor,
ITEM NO.8 12,853 materials and equipment,all in strict accordance $ 2.00 $ 25,706.00 $ 3.00 $ 38,559.00 $ 7.00 $ 89,971.00
with the plans and specifications for
Remove the Exiting Sanitary Manholes and
Replace with reinforced Concrete Sanitary Sewer
Manhole as Per Plans,complete in place,
including excavation,cement stabilized sand
ITEM NO.9 30 backfill,compaction,surface restoration, $ 8,000.00 $ 240,000.00 $ 8,900.00 $ 267,000.00 $ 7,200.00 $ 216,000.00
SuperCoverTM manhole ring and cover(or
approved equal),water-tight connection of existing
and proposed sanitary sewer lines,and testing,all
in strict accordance with the plans and
specifications for
Furnish and Install end of Line Cleanout,complete
in place,including excavation,cement stabilized
ITEM NO.10 4 sand backfill,compaction,surface restoration, $ 2,200.00 $ 8,800.00 $ 1,500.00 $ 6,000.00 $ 2,800.00 $ 11,200.00
water-tight connection of proposed sanitary sewer
lines,all in strict accordance with the plans and
specifications for
Provide a Trench Safety Plan and a Trench Safety
ITEM NO.11 1 System,all in strict accordance with the plans and $ 10,000.00 $ 10,000.00 $ 8,500.00 $ 8,500.00 $ 5,200.00 $ 5,200.00
specifications for
TOTAL $1,947,366.00 $1,419,884.00 $2,178,257.00
EXHIBIT "B"
WILL BE PRESENTED AT OR BEFORE THE COUNCIL MEETING