HomeMy WebLinkAboutPR 23005: RATIFICATION OF SEWER MAIN EMERGENCY REPAIR ON ORANGE AVE. AT GULFWAY DR. nrt rthuur INTEROFFICE MEMORANDUM Date: May 9, 2023 To: The Honorable Mayor and City Council Through: Ronald Burton, City Manager From: Calvin Matthews, P.E., Water Utilities Director RE: PR 23005 —Ratification of Sewer Main Emergency Repair on Orange Avenue at Gulfway Drive Introduction: The intent of this Agenda Item is for the City Council to ratify the emergency repair of the 12" sewer main on Orange Avenue at Gulfway Drive (State Highway 87). The condition of the sewer pipe created a situation that would cause damage to the highway and present a danger to the citizens if not taken care of. Background: The 12" sewer main on Orange Avenue which crosses Gulfway Drive (State Highway 87) was in need of urgent repair, to prevent the situation from worsening, causing sanitary sewer backup in residences and damage to the highway. On February 23, 2023, the City Manager signed an emergency memo, authorizing the repair. The original estimate for the repairs was $50,000.00, but due to the complications found after excavating, additional work was required. Global Drilling, Inc. of Winnie, Texas was called to make the repairs. Budget Impact: The total budgetary impact is $186,700.00 and funding is available in Account No. 405-40- 000-8516-00-00-000, Project No. WS0016-CON. Recommendation: It is recommended that City Council approve Proposed Resolution No. 23005, ratifying the emergency repair of the 12" sewer main as described/outlined above. "Remember, we are here to serve the Citizens of Port Arthur" PR No. 23005 5/9/23 bw Page 1 of 3 RESOLUTION NO. A RESOLUTION RATIFYING THE CITY MANAGER'S DECISION TO AUTHORIZE THE EMERGENCY REPAIR TO THE SEWER MAIN ON ORANGE AVENUE AT GULFWAY DRIVE (STATE HIGHWAY 87), FOR THE TOTAL NOT TO EXCEED AMOUNT OF $186,700.00 FROM WATER UTILITIES ACCOUNT NO. 405-40-000- 8516-00-00-000, PROJECT NO. WS0016-CON. WHEREAS,the sewer main on Orange Avenue at Gulfway Drive(State Highway 87)was in need of urgent repair, to prevent the situation from worsening, causing sanitary sewer backup in residences and damage to the highway; and, WHEREAS,on February 23,2023,the City Manager signed an emergency memo(Exhibit "A"), authorizing the repair by Global Drilling, Inc. of Winnie, Texas; and, WHEREAS, the original estimate for the repairs was $50,000.00, but due to the complications found after excavating, additional work was required; and, WHEREAS,pursuant to Section 252.022(a)(1),this procurement is necessary to preserve or protect the public health or safety of the municipality's residents; and, WHEREAS, it is authorized pursuant to Section 252.022(a)(3) of the local government code because of the unforeseen damage to public machinery, equipment, or other property. NOW THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the facts and opinions in the preamble are true and correct; and, THAT, City Council hereby ratifies the City Manager's decision to authorize the emergency repairs for the total not to exceed amount of$186,700.00 (Invoice attached as Exhibit "B") from Account No. 405-40-000-8516-00-00-000,Project No. WS0016-CON; and, PR No. 23005 5/9/23 bw Page 2 of 3 THAT, a copy of the caption of this Resolution shall be spread upon the Minutes of the Meeting of the City Council. READ, ADOPTED, AND APPROVED this day of , 2023 at a Regular Meeting of the City Council of the City of Port Arthur, Texas by the following vote: AYES: Mayor Councilmembers: NOES: Thurman Bill Bartie Mayor ATTEST: Sherri Bellard City Secretary APPROVED AS TO FORM: Valecia Tizeno City Attorney II I PR No. 23005 5/9/23 bw Page 3 of 3 APPROVED FOR ADMINISTRATION: Ronald Burton Calvin Matthews, P.E. City Manager Water Utilities Director APPROVED AS TO THE AVAILABILITY OF FUNDS: 4CAlN.4),,. loei(lre Kandy Daniel C fton Williams, CPPB " Finance Director Purchasing Manager Exhibit "A" Girt of 1i on rtltu — Tt't�lc INTEROFFICE MEMORANDUM Date: February 23, 2023 To: Ronald Burton, City Manager From: Calvin Matthews, P.E., Water Utilities Director RE: Approval for Emergency Repair to Sewer Main under Gulfway at Orange Ave. A sewer main under Gulfway near Orange Avenue is in need of immediate repair to prevent damage to the highway and sanitary sewer backup in residential homes. Emergency approval is requested of the City Manager to hire a contractor to assist in repairs of 12" sanitary sewer line and approve the purchase of materials for this repair. A labor cost of$36,000 is estimated for the installation of City-supplied materials. The City- supplied materials that need to be purchased total approximately $14,000.00. A proposed resolution will be presented to City Council for ratification. I, Ronald Burton, hereby approve the emergency repair of the sewer main under Gulfway at Orange Ave. t1iPtli Ronal• :urton City Manager , "Remember, we are here to serve the Citizens of Port Arthur" Exhibit "B" ■ ,yr�^� GLOBAL DRILLING,INC. GL■ t0,B A L 44994 Interstate 10 Winnie,Texas 77665,USA i`./J T:+1 800 956 8720;E:info@globaldrillingequipment.com, ORR LING, INC. w:www.alobaldrillinaequipment.com INVOICE Date: Attn: ACCOUNTING May 8,2023 Port Arthur. TX 77641 Ref.No. : Project Location:Orange Avenue Intersecting Gulfway Drive, Port Arthur Texas PA2022-006 COMPLETED WORK ITEM TOTAL NO. DESCRIPTION UNIT _ _ _ __.... _ UNIT PRICE TOTAL PRICE REMARKS Or( TOTAL TO % PREVIOUS DATE I REHABILITATION OF 12"SEWER PIPES 1 LS 100.0096 1 186,700.00 186,700.00 1 -Mobilization of manpower,equipment,project signs ■ 2 -Conducted Horizontal Directional Drilling works 2.1 Cleaning the blocked existing line from Manhole# _______________________________________________________________________________________ 2 to#3 -Cleaning the existing line from manhole to#2 ■■'■-- Replacement/Installation of 12"Sewer pipes -Furnish and Install 4-units of Concrete Sewer Manholes including excavation,concrete liners, dewatering,shoring,backfilling,compaction,surface restoration,Manhole Rings and Covers111 4 - Connection of existing/completed sewer lines to new . ■Manholes --- 5 -Installation of 2-units of 6"Gate Valves _--- 6 - All other necessary works associated to complete the ■ ■works ---- ............. TOTAL DUE: 186,700.00 Terms and Conditions: AS PER SUBCONTRACT NO.22-300 Amount in Words(US Dollars):One Hundred Eighty Six Thousand Seven Hundred Only For: GLOBAL DRILLING,INC. Mr.BAKER MOHAMMAD Page I of I Daily Site Report Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: March 22,2023(Wednesday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Cloudy/Fair Location: Sabine Pass.Port Arthur Texas 77655 Description of Work Completed: Start Finish Comment [Time] [Time] •• Mobilized in new location in Port Arthur 3:00AM 10:00AM 2 Fusion machine and Bobcat Excavtor were delivered on site 10:00AM 10:30AM 3 Fuse the 12"HDPE pipes-240' 10:30AM 7:00PM DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) -Orange Avenue intersecting Gulfway Drive MATERIALS PERSONNEL. CONSUMABLES Name From: Tc Total No of Hours FUEL(L) Daniel Cuellar 3:00AM OIL(L) Vicente Zecca 8:00AM 7:00PM PIPE(Type)-(Ft) 240'-12"HDPE Others EQUIPMENT: TYPE Hire Date Hours Used COMMENTS: Fusion Machine 22-Mar 7.5 Bobcat E26 Excavator 22-Mar SITE SUPERVISOR DANIEL CUELLAR Comments: NOTED BY: 03-22-Daily Site Report-Port Arthur Daily Site Report GLOBAL DRILLING.INC- Project: Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: March 23,2023(Thursday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Cloudy/Fair Location. Sabine Pass,Port Arthur Texas 77655 Description of Work Completed: Start Finish Comment [Time] [Time] 1 Fuse 200'of 12"HDPE Pipe 8:00AM 5:00PM Short of 1-Pipe.Will deliver tomorrow.March 24 2 • Locate Existing Lines:water fiber optic and gas lines 10:00AM 10:30AM 3 CAT 315 Rubber Crawler Excavator and Traffic Control Sign Boards were delivered on site 12:00PM 1:00PM 4 DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) -Orange Avenue intersecting Gultway Once MATERIALS• PERSONNEL• CONSUMABLES Name: From. To: Total No of Hours FUEL(L) Daniel Cuellar 7:30AM 5:30PM OIL(L) Vicente Zecca 7:30AM 5:30PM PIPE(Type)-(Ft) 200'-12"HDPE Jesse Martinez 7:30AM 5:30PM Others EQUIPMENT TYPE Hire Date Hours Used COMMENTS: Fusion Machine 22-Mar 15.5 Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar SITE SUPERVISOR: DANIEL CUELLAR Comments: NOTED BY 03-23-Daily Site Report-Port Arthur .' ' .''.. ,''''..., . ..i. ',-7, '....,......„.... a rry x • y�ss N. tn� / � l . f ..a 41111 --z'.e ii. 03-23-Daily Site Report-Port Arthur Daily Site Report CLBAL GRILLING.INC Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: March 24,2023(Friday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Sunny/Fair Location: Sabine Pass.Port Arthur Texas 77655 Description of Work Completed: Start Finish Comment [Time] [Time] 1 2 Loads of Caliche Sand were delivered on site 8:OOAM 10:00AM 2 Fuse additional 20'of 12'HDPE Pipe(Port Arthur delivered last night) 7:30AM 10:00AM 3 Excavation for Dnving and Receiving Pits 10:00PM 5:30PM 4 5 DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) -Orange Avenue intersecting Gulfway Drive MATERIALS PERSONNEL CONSUMABLES Name: From. To: Total No of Hours FUEL(L) Daniel Cuellar 7:30AM 5:30PM OIL(L) Jesse Martinez 7:30AM 5:30PM PIPE(Type)-(Ft) 20'-12"HDPE Gabriel 7.30AM 5:30PM Others EQUIPMENT TYPE Hire Date Hours Used COMMENTS: Fusion Machine 22-Mar Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar Vermeer D24x40 HDD Machine 24-Mar SITE SUPERVISOR DAME_CiELL-+v Comments: NOTED BY 03-24-Daily Site Report-Port Arthur Daily Site Report GL ,BAL DRILLING.INC. Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: March 25,2023(Saturday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Sunny/Fair Location: Sabine Pass,Port Arthur Texas 77655 Description of Work Completed: [StartTime] Fi[Tnish Comment Excavation for Driving and Receiving Pits 8:00AM 1:00AM While Excavating in Orange Street,the Operator hit the Gas Line that was not Marked Texas Gas came on site and fix the gas line 1:30PM 3:00PM 3 Fruc Truck came to pump the sewer line 11:00AM 3:00PM Surveyor came on-site 11:00AM 2:00PM Finished 380'by Horizontal Directional Drilling 1:00PM 5:00PM Installation of Reamer in Hirectional Drilling Machine 5:00PM 6:30PM DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) -Orange Avenue intersecting Guifwav Drive MATERIALS: PERSONNEL: CONSUMABLES Name From: To Total No of Hours FUEL(L) Daniel Cuellar 6:30AM 6:30PM OIL(L) Jesse Martinez 6:30AM 6:30PM PIPE(Type)-(Ft) Gabriel 6:30AM 6:30PM Others HDD Machine Operator 6:30AM 6:30PM Plus 5 Labours/Helpers 6:30AM 6:30PM EQUIPMENT TYPE Hire Date Hours Used COMMENTS: Fusion Machine 22-Mar Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar Vermeer D24x40 HDD Machine 24-Mar Fruc Truck 25-Mar Trailer 25-Mar SITE SUPERVISOR: DANIEL CUELLAR Comments: NOTED BY 03-25-Daily Site Report-Port Arthur S kt Illk of ## a•; n _ .s z a , s� a _ , . P:' . , .. . r r ...� +... y+ .r.. .,' s=rrt b 03-25-Daily Site Report-Port Arthur Daily Site Report GL Q BAL fRI[LING_INC Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: March 26,2023(Sunday) Pipe Bursting Using 8"SDR•17 HDPE Pipe Weather: Cloudy i Fair Location. Sabine Pass.Port Arthur Texas 77655 Description of Work Completed: Start Finish Comment [Time] [Time] Completed installing the 380'of 12"HDPE Pipe 7:00AM 1:00AM Backfilling of ramps made for Directional Drilling Machine 3:00PM 6:30PM 3 Excavation for new manholes 1 00AM 6:30PM DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) -Orange Avenue intersecting Gulfway 380 Drive MATERIALS: PERSONNEL CONSUMABLES Name From: To: Total No of Hours FUEL(L) Daniel Cuellar 7:00AM 6:30PM OIL(L) Jesse Martinez 7:00AM 6:30PM PIPE(Type)-(Ft) 380'HDPE HDD Machine Operator 7:00AM 6:30PM Others Plus 5 Labours Helpers 7:00AM 6:30PM EQUIPMENT: TYPE Hire Date Hours Used COMMENTS: Fusion Machine 22-Mar Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar Vermeer D24x40 HDD Machine 24-Mar Fruc Truck 25-Mar Water Truck 25-Mar Trailer 25-Mar SITE SUPERVISOR: DANIEL CUELLAR Comments: NOTED BY: 03-26-Daily Site Report-Port Arthur -Ati .:-',------...--'-•:, •.---;-..L------- ' -*1ST:, --e*.i.--1- ,. .:,..,. .,, •.'..e4r14\ctI"' '''' • •'.',-._.•.-.,,..,'„, ,. r7='; ---: . -- •.„:-. -:.-'s---.. ... - -- -• • • .-, .,Ir.,7-.,-;..-:...... .:- - .' . .-..-.'-.•'''''-. -. ..... , .„..,..._ „ „IS* --'•:7'.--,=,..-'4.14..,,..;?....,....,,,!--e,'. , -,,, .1,- ' - --ri - •-•-'- ,........• , - ,-.-.::-.;' -.. --.., ----,-,-',_;._.•-, „.-• :- - -. .i,..-_. ' --• --------------• • - , ........,-,....... . „.. . . ,.....„ , -- - ,. •, , i .4, • ' -.,,,- .„: A---,- . -' - , .,••. . . . • - --k, 4' - ti - !' - - . - .4., - - . • ., ., , . ... . . - -• ' , . _ .. ,..... ,.. . .. ,...,-... , .., . . , .,_...„,. ....... .,.... _ . . „. ' ',•_.--,--•-7-4-',,,- - ._ . _ . ., _ •, .-- •- ...- -s.. ,.s„, :.,,••-•,-,--, ,t•-•-is.-- -•-- ••'-i- ' .-..-±7,_:-.,-.1,.....,..„. , i . • - - -s---•-•4' . .,,.., . , . .. ' -:•,...4-...444_•. •,-" ;„:.'el* ."-'17--•,- * -I-- ,',..a,:.-",i1-‘,4; - . •'-'- - 1 '''6-6,-•-------:=,i4.'''?„-.--.1,7;_4 ,..*' • •°*--- ,-!• .,•-•,. . . ' ."-Ir-'-' 44=-.1•--;!-;f--.5-',';•-•4; ----', -`""'. L .. ..„ ,; ,.. ;._._ ,4-..',.•-•-ii•-*:4-,..--,.---";--,... S--; *' - - - • . , ., . , . - ° - - •=.4., -- :;'•-' 44 , : .- ' *-- - •=- • kia :- ---4;- .-•-../#47,4 : - -,•-'4:''''..1,- : - 'f* ... ...'.;•t.:-.'44.,„-- ." . - .;!..".. •=4,- ,..... .... .......„ . , .. .„/ • . - . - - .. i,.•: .. - . • - ....; '-'.P;'-:*• -'!•- -. --' t -4-' '.-- '.k ''''' '%' * .-'.52-4:: •-•-4, - • '• :44 -' - -‘...- • . ' . . -..- . - - „.•'-.,„.--- -4 . -,. - .‘ '. 4 :-,„...4...ff...7, ,,--.-- •\,,,,.. s s . -..,,... ,_. .. ......... . --..---,-.--.-: . :-.-..•''.' `••• e* -.4,-,, ' .,:,--••• -f,' • -_,,;.v, • I. 2:',„--- ..-- ,--, .. . . • , . . * . • '.k "- . . . '* *-- ,! ,-,'-'1,....! ...:-.. . , .--. ..„. - - . ..1- . .*,-r--'-;',:vre...$,--i'..•-„,,o,Pe-..-;-76--e.--...-..z:;,..R...-1-.1„0,--.,--,,-i., -........__ .- - . , .. , - , .- - .......,... , .,- , . . . 03-26-Daily Site Report-Port Arthur Daily Site Report CL 8AL DRILLING.INC, Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: March 27,2023(Monday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Cloudy i Fair Location: Sabine Pass,Port Arthur Texas 77655 Description of Work Completed. Start Finish Comment [Time] [Time] Receive the Steel Plate 1-00PM 1:00PM Clean the mud on the road 1:00PM 4:30PM 3 DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) -Orange Avenue intersecting Gulfway Drive MATERIALS: PERSONNEL: CONSUMABLES Name: From To Total No of Hours FUEL(L) Daniel Cuellar __ _ _°(I OIL(L) PIPE(Type)-(Ft) Others EQUIPMENT: TYPE Hire Date Hours Used COMMENTS: Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar SITE SUPERVISOR DANIEL CUELLAR Comments: NOTED BY 03-27-Daily Site Report-Port Arthur Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: March 29,2023(Wednesday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Cloudy then Raining Location:Orange Avenue Intersecting Gulfway Drive Start Finish Description of Work Completed: Comment [Time] [Time] 1 Vacummed Manhole#1 8:00AM 12:00PM 2 -Then started raining all day 3 4 5 DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) -Orange Avenue intersecting Gulfway Drive MATERIALS: PERSONNEL: CONSUMABLES Name: From: To: Total No of Hours FUEL(L) Daniel Cuellar 8:00AM 6:00PM OIL(L) Troy Cuellar 8:00AM 6:00PM PIPE(Type)-(Ft) Jesse Martinez 8:00AM 6:00PM Others EQUIPMENT: TYPE Hire Date Hours Used COMMENTS: Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar 4pcs-ROAD PLATE,8X10',1" 27-Mar 8pcs-1.5'52"-88"HYDRAULIC 27-Mar SHORE 8pcs-VERTICAL SHORE 24" 27-Mar CYLINDER E 5 GAL.PLASTIC HAND PUMP 27-Mar 48"RELEASE TOOL 27-Mar SITE SUPERVISOR: DANIEL CUELLAR Comments: NOTED BY: 03-29-Daily Site Report-Port Arthur GLeBAL IR]LwillG INC Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: March 30,2023(Thursday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Cloudy/Clear Location:Orange Avenue Intersecting Gulfway Drive Description of Work Completed: Start Finish Comment [Time] [Time] 1 Undugged Manhole#1 to Manhole#2 7:30AM 7:00PM 2 3 4 5 DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) -Orange Avenue intersecting Gulfway Drive MATERIALS: PERSONNEL: CONSUMABLES Name: From: To: Total No of Hours FUEL(L) Daniel Cuellar 7:30AM 7:00PM OIL(L) Tor Cuellar 7:30AM 7:00PM PIPE(Type)-(Ft) Jesse Martinez 7:30AM 7:00PM Others EQUIPMENT: TYPE Hire Date Hours Used COMMENTS: Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar 4pcs-ROAD PLATE,8X10',1" 27-Mar 8pcs-1.5'52"-88"HYDRAULIC 27-Mar SHORE 8pcs-VERTICAL SHORE 24" 27-Mar CYLINDER E 5 GAL.PLASTIC HAND PUMP 27-Mar 48"RELEASE TOOL 27-Mar SITE SUPERVISOR: DANIEL CUELLAR Comments: NOTED BY: 03-30-Daily Site Report-Port Arthur Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: April 4,2023(Tuesday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Cloudy/Clear Location:Orange Avenue Intersecting Gulfway Drive Description of Work Completed: Start Finish Comment [Time] [Time] 1 Installed Manhole#2,its fiberglass manual cut into elevation 7:00AM 7:OOPM 2 Backfilling for Manhole#2 3 4 5 DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) Orange Avenue intersecting Gulfway Drive MATERIALS: PERSONNEL: CONSUMABLES Name: From: To: Total No of Hours FUEL(L) Daniel Cuellar 7:00AM 7:00PM OIL(L) Troy Cuellar 7:00AM 7:00PM PIPE(Type)-(Ft) Jesse Martinez 7:00AM 7:00PM Others EQUIPMENT: TYPE Hire Date Hours Used COMMENTS: Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar 4pcs-ROAD PLATE,8X10',1" 27-Mar 8pcs-1.5'52"-88"HYDRAULIC 27-Mar SHORE 8pcs-VERTICAL SHORE 24" 27-Mar CYLINDER E 5 GAL.PLASTIC HAND PUMP 27-Mar 48"RELEASE TOOL 27-Mar 4"VAC ASSIST(75 HP) 31-Mar Test Ball Plug,Rope and Gauge 31-Mar SITE SUPERVISOR: DANIEL CUELLAR Comments: NOTED BY: 04-03-Daily Site Report-Port Arthur GL AL DIG$1 Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: April 4,2023(Tuesday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Cloudy/Clear Location:Orange Avenue Intersecting Gulfway Drive Description of Work Completed: Start Finish Comment [Time] [Time] 1 Installed Manhole#2,its fiberglass manual cut into elevation 7:00AM 7:00PM 2 Backfilling for Manhole#2 3 4 5 DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) -Orange Avenue intersecting Gulfway Drive MATERIALS: PERSONNEL: CONSUMABLES Name: From: To: Total No of Hours FUEL(L) Daniel Cuellar 7:00AM 7:00PM OIL(L) Troy Cuellar 7:00AM 7:00PM PIPE(Type)-(Ft) Jesse Martinez 7:00AM 7:00PM Others EQUIPMENT: TYPE Hire Date Hours Used COMMENTS: Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar 4pcs-ROAD PLATE,8X10',1" 27-Mar 8pcs-1.5'52"-88"HYDRAULIC 27-Mar SHORE 8pcs-VERTICAL SHORE 24" CYLINDER E 27-Mar 5 GAL.PLASTIC HAND PUMP 27-Mar 48"RELEASE TOOL 27-Mar 4"VAC ASSIST(75 HP) 31-Mar Test Ball Plug,Rope and Gauge 31-Mar SITE SUPERVISOR: DANIEL CUELLAR Comments: NOTED BY: 04-04-Daily Site Report-Port Arthur Daily Site Report GLOBAL HIRING.INC. Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: Aprils,2023(Wednesday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Cloudy/Scattered Rain Location: Sabine Pass.Port Arthur Texas 77655 Description of Work Completed: Start Finish Comment [Time] [Time] 1 Made the Flow from Manhole 2.pour concrete(2-Yards) 2 3 4 DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) -Orange Avenue intersecting Gulfwav Drive • MATERIALS: PERSONNEL CONSUMABLES Name: From. To: Total No of Hours FUEL(L) Daniel Cuellar 8.00AM 7:00PM OIL(L) Troy Cuellar 8:00AM 7:00PM PIPE(Type)-(Ft) Others Jesse Martinez 8:00AM 7:00PM 2-Labours 8:00AM 7:00PM EQUIPMENT• TYPE Hire Date Hours Used COMMENTS: Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar 4pcs-ROAD PLATE.8X10',1" 27-Mar 8pcs-1.5'52"-88"HYDRAULIC 27-Mar SHORE 8pcs-VERTICAL SHORE 24" CYLINDER E 27-Mar 5 GAL.PLASTIC HAND PUMP 27-Mar 48"RELEASE TOOL 27-Mar 4"VAC ASSIST(75 HP) 31-Mar SITE SUPERVISOR: DANIEL CUELLAR Comments: NOTED BY 04-05-Daily Site Report-Port Arthur Daily Site Report GLOBAL DRILLING.INC. Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: April 6,2023(Thursday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Scattered Rain Location: Sabine Pass.Port Arthur Texas 77655 Description of Work Completed. Start Finish Comment [Time] [Time] Set 1 Manhole Pumping the water Slow down because of the rain 3 Cleaning and preparing Open new line,the HDPE.to let sewerage flow from Manhole 1 to Manhole 2 Delivered the risers for all the manholes DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) -Orange Avenue intersecting Gutfway Drive MATERIALS PERSONNEL. CONSUMABLES Name From: To. Total No of Hours FUEL(L) Daniel Cuellar 6:30AM 5:00PM OIL(L) Jesse Martinez 6:30AM 5:00PM PIPE(Type)-(Ft( Others Troy Cuellar 6:30AM 5:00PM 2-Labours 6:30AM 5:00PM EQUIPMENT: TYPE Hire Date Hours Used COMMENTS: Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar 4pcs-ROAD PLATE,8X10'.1" 27-Mar 8pcs-1.5'52"-88"HYDRAULIC 27-Mar SHORE 8pcs-VERTICAL SHORE 24" 27-Mar CYLINDER E 5 GAL.PLASTIC HAND PUMP 27-Mar 48"RELEASE TOOL 27-Mar 4"VAC ASSIST(75 HP) 31-Mar SITE SUPERVISOR: DANIEL CUELLAR Comments: NOTED BY 04-06-Daily Site Report-Port Arthur Daily Site Report CL BAL Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: April 7,2023(Friday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Raining Location: Sabine Pass.Port Arthur Texas 77655 Description of Work Completed: Start Finish Comment [Time] [Time] 1 "-Manholes are FULL OF WATER 2 3 4 5 • DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) Orange Avenue intersecting Gulfwav Drive MATERIALS: PERSONNEL: CONSUMABLES Name: From. To. Total No of Hours FUEL(L) Daniel Cuellar OIL(L) Jesse Martinez PIPE(Type)-(Ft) Others Troy Cuellar 2-Labours EQUIPMENT: TYPE Hire Date Hours Used COMMENTS: Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar 4pcs-ROAD PLATE.8X10',1" 27-Mar 8pcs-1.5'52"-88"HYDRAULIC SHORE 27-Mar 8pcs-VERTICAL SHORE 24" CYLINDER E 27-Mar 5 GAL.PLASTIC HAND PUMP 27-Mar 48"RELEASE TOOL 27-Mar 4"VAC ASSIST(75 HP) 31-Mar SITE SUPERVISOR: DANIEL CUELLAR Comments: NOTED BY 04-07-Daily Site Report-Port Arthur .,--' -1111116-74111,v ,...:tl:—.•:'"'t:•471::7-77---:-: .41.::177til:4::11IL':41.;-:'1::1'-:''..::----'.' • .._*,:'. _ '1.14, . `..•-'kc; T4 3. e 33'..‘-'.-,' '3..3"' . . . •'',. , y . • ''' 1 ::1,, - .., ,i:.;;'.'t;..::'''`', ''','•-'' • y y . .''''''''''' ' '''''.:.':';',' .•1 '''I 1• -'' :•.':,;. ' 1- f- 1-.,*,,,, - . 110111.-.;' .f,r -.74.-. ..f.P .. ..•-t1....3-:---31 3. ' *,..-.-s-- ---4•'--.-,k':'-. , ,, , -- -,'-.: .:*-.:--;. - - ,• 1. ' .------"- .-%--'- ',-;:-.7-7:' ...,--'r''-;-*;77*-:::'''?4 ;:-,,,-,'-'-':- -.:f7' . ' ‘... -t -,--- .-•-zIr,47,-----'. - . .;,.....,:i.t.: z ::--- - ...-......=..,----..- -- .,,.,,,,,t: '-'::...' .i'--i.-:".•.,.;,;--.' -• .', -;-_-_-_,,,,,-;4,''A.-,-.,* -,144,'. i ''' -1-4'''':N...' `• *':Ir:'... ,...... ....,....::::.. -,,,,,.: ,,....:....„....„*'‘.-.,_,;.-, .-,.:,„_ '-----.. .,. -_ :: - --- . • ,...,, -,-----,--:----..*„..,-,7t---, , .,-.3.f-,----i'' i:''- .. ..-...„, '`3.-- . .. . ;--444:(- .- .• * ''.',. , -";11....-, .:,;'1!...• ;:.4...,,,•,'„,.,,„tt-i..- -7,e'r:r/11/4„...".'..,; . '';.. , ''..., ,„, -_,_,.., _. , ,s.,,,,,,,I,,__- 1- -.7-•--,,'-;;:4--*5.P.Ak-0. 4' ' '''',*. -- . ;..v... . ...... -A • . ,,f.-- e '"',- ' 04-07-Daily Site Report-Port Arthur Daily Site Report GLOBAL DRILLING.INC. Project: Rehabilitate 8"Diameter Sanitary Sewer Pipe by Date: April 8,2023(Saturday) Pipe Bursting Using 8"SDR-17 HDPE Pipe Weather: Cloudy/Scattered rain Location. Sabine Pass.Port Arthur Texas 77655 Description of Work Completed: Start Finish Comment [Time] [Time] '`Manholes are FULL OF WATER Installed Gate valve and Water Line 3 DRILLING DETAILS: Crossing Reference No.: TODAY(Feet) PREVIOUS(Feet) TOTAL(Feet) Orange Avenue intersecting Guffwav Drive MATERIALS: PERSONNEL: CONSUMABLES Name: From: To Total No of Hours FUEL(L) Daniel Cuellar OIL(L) Jesse Martinez PIPE(Type)-(Ft) Others Troy Cuellar 2-Labours EQUIPMENT TYPE Hire Date Hours Used COMMENTS: Bobcat E26 Excavator 22-Mar CAT 315 Crawler Excavator 23-Mar 4pcs-ROAD PLATE.8X10'.1" 27-Mar 8pcs-1.5'52"-88"HYDRAULIC 27-Mar SHORE 8pcs-VERTICAL SHORE 24" CYLINDER E 27-Mar 5 GAL.PLASTIC HAND PUMP 27-Mar 48"RELEASE TOOL 27-Mar 4"VAC ASSIST(75 HP) 31-Mar SITE SUPERVISOR: DANIEL CUELLAR Comments: NOTED BY 04-08-Daily Site Report-Port Arthur X41040., ,% wa x � �. � !. fiF �.. 5 ..i f i - - • xt4 " ,.--,R. .:4:.. , - ,-.,„,:::::-.,1-!',.- V f ' x+i 04-08-Daily Site Report-Port Arthur o s" '. f aw t `" "§ ' a •, vw ,� a by l� s . r2r z � u� _ 5... ' ;`„#`. 'ram :' f. d'_ 04-08-Daily Site Report-Port Arthur