HomeMy WebLinkAboutPR 12241 PA BUSINESS PARKPort Arthur Economic Development Corporation
P. O. Box 1089 . Port Arthur, Texas 77641-1089
409/983-8195 · 409/98::;-8222 fax
Email: portarthuredc(~eonet.net · http://www.portarthur, com/edc
Memo
To: Mayor, City Council and City. Manager
From: Ike Mills, Executive Directoff~
Date: June 19, 2003
Re: P.R. No. 12241; Council Meeting June 24, 2003
Attached is P.R. No. 12241 approving a change order in the amount of
$63,000 for the Business Park as approved by the Section 4A Port Arthur
Economic Development Corporation and the Board of Directors during the June
17, 2003 meeting.
Cc: Mark Sokolow, City Attorney
Jim Wimberly, EDC Attorney
P. R. No. 12241
06/19/03 twa
RESOLUTION NO.
A RESOLUTIONAPPROVING CHANGE ORDER NO. i FOR
CONTRACT V IN THE A~K)UNT OF $63,000, AS IT
PERTAINS TO THE PORT ARTHUR BUSINESS PARK AS
APPROVED BY THE SECTION 4A PORT ARTHUR
ECONOMIC DEVELOPMENT CORPORATION
WHEREAS, the Section 4A Economic Development Corporation
entered into a contract with Excavators & Constructors for
$887,500.00 as it pertains to Contract V; and
WHEREAS, Excavators & Constructors has submitted a Change
Order request in the amount of $63,000 for the increased lime
stabilization; and
WHEREAS, this Change Order has been approved by the
Directors of the Port Arthur Section 4A Economic
Corporation on June 17, 2003 by a four to one vote.
Board of
Development
order from
WHEREAS, a status report recommending the change
Diamond Consulting is attached as Exhibit "A".
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR:
Section 1. That the facts and opinions in the preamble are
true and correct.
Section 2. That the Change Order No. 1 in the amount of
$63,000 is herein approved as denoted in Exhibit "B".
Section 3. That a copy of the caption of this Resolution
be spread upon the Minutes of the City Council.
READ, ADOPTED AND APPROVED on this __ day of ,
A.D., 2003, at a Regular Meeting of the City Council
of Port Arthur, Texas, by the following vote: AYES:
Mayor , City Council
of the City
NOES:
ATTEST:
EVANGELINE GREEN,
OSCAR 0RTIZ, MAYOR
CITY SECRETARY
APPROVED AS TO FORM:
MARK T. SOKOLOW, CITY ATTORNEY
APPROVED FOR ADMINISTRATION:
STEVE FITZGIBBONS, CITY MANAGER
APPROVED AS TO AVAILABILITY OF FUNDS:
REBECCA UNDERHILL, DIRECTOR OF FINANCE
EXHIBIT "A"
Diamond Consulting
11 Gambrel Oak Place
The Woodlands, Texas 77380
Economic Development
Architecture
Planning
Memorandum
To: Port Arthur Economic Development Corporation Board
From: Bill Diamond
Date: May 16, 2003
Re: May Progress Report on Business Park Project
The following report and attachments summarizes the status of the project as of the date of this report.
SUMMARY OF PROGRESS
The award of the balance of the construction work for the Business Park has been approved. This includes separate
agreements for a modular office originally contained in work bid as Contract I (General Requirements), and
Contract VII (Landscape and Final Grading). It also includes approval of utility agreements for gas and power and
Change Orders for Contracts III and IV necessary to allow work to continue. In addition the outstanding section of
right of way required to route the sanitary sewer force main to the sewage treatment plan was condemned (see
previous month's reports). The majority of the work of Contracts II -IV (Rough G-fading and Site Preparation,
Underground Utilities and Drainage Improvements) is moving toward completion. Work is beginning on Contracts
V and VI (Road Improvements and Lift Station and Force Main).
Construction Progress
The following reflects progress as of the end of April (see payment requests).
Contract I General Requirements - award of contract for the on-site modular office was approved
by City Council. Contracts for a construction sign and a temporary site identification sign were
disapproved. The project will have no identification until permanent signs are installed at the end
of construction.
Contract II Rough Grading and Site Preparation - with continued generally dry weather the site is
drying out. Additional clearing and grubbing and installation of fill material in areas previously
inaccessible due to wet site conditions and pipeline construction has been accomplishe. This
contract is now 87 % complete. Thirteen additional rain days (mostly for continued muddy
conditions that have impeded construction) were approved for March.
Contract m Underground Utilities -the majority of the off site water distribution is nearing
completion. Most of the work remaining for the water system involves tie ins to the city system.
The EDC board and City Council has approved Change Order 2 (revisions to tie in to city water
main on FM356). Installation of underground conduit for power and telephone (lines to be
installed by these utility companies) also neared completion last month. This contract is
approximately 89% complete. Eleven additional rain days (mostly for continued muddy
condition~ that have impeded construction) were approved for April.
Contract iV Drainage Systems Improvements - Continued progress on this contract has occurred
during April. The excavation of the retention pond has progressed to 50% complete and portions
of the outfall structure into Drainage District 7's ponds have been installed. The City Council has
approved Change Order 2 (revision of outfall valves) required to allow this work to be completed.
This contract is approximately 89% complete. Nine additional rain days (mostly for continued
muddy conditions that have impeded construction) have been approved for April.
ph 281 3677821 fax281 367 7223 email biil@diarnondconsultingonline.com
Contract V Road Improvements - Work for this contract has begun. Culverts along West Port
Arthur Road have been placed. However the issues regarding about soil moisture and the paving
cross section (see monthly reports of March and April) have lead to additional investigations by
soil consultants. The results of these tests are a proposed modification to the lime stabilization of
the paving sub-grade called for by the current contract. This will entail a Change Order to this
contract (see attached summary.) The contact remains approximately 1.6% complete. No rain
days have been approved for this contract.
Contract VI Lit~ Station with Force Main - with the route for the sanitary sewer force main
secured, work is now beginning on this contract
Contract VII Landscaping and Final Grading - award of contract has been approved by City
Council.
On Thursday May 1, your project manager was called to testify in the condemnation proceedings conducted in 1
Circuit Court of Jefferson Coonty. The result ofthis hearing was the acquisition of a section right of way for the
sanitary sewer force main for the project.
A meeting was held with the engineering team including ESPA Corp (Schaumburg & Polk's engineering consultant
for street design) and the City Public Works Director on May 12th to review the problems associated with increased
soil moisture and the proposed Change Order to Contract V (Road Improvements). Please see further discussion
below.
Outstanding Issues
The regular monthly construction meeting was held on May 12, 2003. In addition to reviewing construction
progress the following were discussed.
At this time (with the exception to Change Order 1 to Contract V - Road Improvements) there are no known issues
that might cause delay in construction or give rise to additional change orders.
Change Order 1 for Contact V (please see attached summary)
The project engineer has requested a change order proposal from the contractor to increase the lime stabilization
percentage fi.om 6% to 8% and the depth of stabilization fi.om 6" to 8". The development of this change in paving
design began with observations of the engineer and contractor in regard to the retention of moisture by site soils
encountered during initial phases of construction. Consultation with the soil consultant that performed the initial
soil borings led to the decision to take additional borings. The results indicated that the soil moisture content
discovered in the initial borings had changed from a mean of approximately 20% to a mean of approximately 35%.
This represents a significant reduction in soil bearing capacity.
The soil consultant's original recommendation based upon the initial tests were for a paving section of 6' depth over
a sub grade formed by the removal one foot of existing soil and replacement with select fill. The engineer's design
as currently included in Contract V (with the concurrence of the soil consultant) called for 7" of concrete paving
over 6" of/'% lime stabilized subsoil. The difference between the soil consultant's original recommendations and
the engineers original design was estimated to save the project approximately $120,000.
Based upon his most recent findings the soil consultant issued a revised recommendation for paving design. He
recommended an increase of depth from 6" to 8" of 6% lime. Desiring to be conservative and cautious in the face of
changing recommendations, a second opinion was sought from a previously uninvolved soil consultant. These
additional tests and evaluations generally confirmed the revised recommendation of the initial soil consultant but
specified 8" of 8% lime stabilization. After reviewing these recommendations the engineers now propose to
increase the lime content to 8% and the depth to 8".
The increase in soil moisture content is clearly the result of over 100 inches of rainfall at a time that site construction
was getting underway. But the capacity of the soil at our site to absorb and hold moisture demonstrated by these
2 of 3
conditions requires increased stabilization if the we are to take proper measures to avoid paving failures in the
future. ~-
The quality of paving is one of the most important a~actions ufa business park to businesses seeking a place to
locate. This change order will increase the cost of the project by $63,000. But it is a cost that would have been
included in the original design if the information now available had been available. In addition the cost of
development remains well below the budget established for the project.
CONSTRUCTION pHASE cOSTS
The attached Budget and Cost Summary indicates that Change Order 1 of Contract V (see above) has been reduced
by $4,879 from its earlier estimate. The appr°val °f this change °rder will leave the pr°ject $898'$21 °r 85'3%
percent under the approved budget
CONSTRUCTION PHASE ISSUES AND ACTIONS
Approval of Change Order 1 to Contract ¥ is required to prevent delay of the progress of the work and pro. iect
completion.
ITEMS REQUIRING ACTION IN MAY
Contract ¥ - Change orderl - Additional Lime Stabilization - $63,000 (see above)
NT REQUESTS
PAYME ..... -_ .~.~ ,~,~.a Contract and Payment Summary. We recommend the
Invoices have been submitted ana taouia~eu m m~ o~,~ .....
following payments:
Diamond Consulting
Schaumburg & Polk
Excavators and Constructors
Contract II
Contract m
Contract IV
Contract V
$4,267.00
$6,548.80
$40,761.36
$147,474.12
$64,067.46
$33,107.46
The sum of payment requests to date for the Construction Phase equals 47.0% of the contracted
(this does not reflect the progress represented by the 5% retention for construction contracts).
REQUESTED ACTION BY EDC BOARD AND CITY COUNCIL
Approval of Change Order 1 for Contract V (see above)
cost for this phase
Respectfully Submitted,
William E. Diamond 1I
Attachments
Budget and Cost Summary
Contract and Payment Summary
SPI Letter Recommending Award of Change Order No. 1 for Contract V
Project Manager's Summary of Change Order No. 1 for Contract V
3 of 3
~au lG 03 0~:52p D~amond Consu]t~nc 28~~367-7223
Diamond ConsulUng
11 Gambrel Oak Place
The Woodlands, Texas 77380
Economic Development
Architec~um
Pianning
March 12. 2003
Port Arthur Economic Development Coq)oration
P.O. Box 1089
Port Arthur, Texas 77640-1089
INVOICE FOR SERVICES
Invoice # 0403A
PEROID ENDING MARCH 31, 2003
Services
Project Management Services for Construction Phase of Port Arthur Business Park Project
Port Arthur Economic Develol~ment Corporation
Basic
Services
Amount
% Complete
Amount Famed
2.1 Coordinate Construction Phase $6,480 75.0% $4,860.00
2.2 Monthly Review and Report $24,540 65.0% $15,951.00
2.3 Issue Resolution $15,200 95.0% $14,440.00
2.4 Project Closeout $10,300 0.0% $0.00
Total Services $56,520 62.4% $35,251 .iX}
Services Previously Invoiced $30,984.00
Services this Period $4,267.00
AMOUNT DUE THIS INVOICE
$4,267.0O
voice 281 367 7821 fax 281 367 7223 email bill,diamond consulfingonline,com
EXHIBIT "B"
JUN-20-2003 FRI 01;17 PM SOHSUMBURG & POLK
06/1~/2003 05:30 40~7216037
FAX NO, 14098660337
EXCAVATOR5 & GI:H~TRU
P. 02/03
pAP~[
P. O!
AI~ROVA~ OF CONTRACT CHANGE
C~IA~O~ ORDBRNO.
DATE: Surm 18, 2003
PRO3'ECT: Port Aflhur Bu~ Park
Con.act V - Road lmprov~n~ts
OWNER:
CONTRACTOR:
Pofl AC&ut I~nomi~ Dcvdopm~nt Corporation
P,O. 8ox 1089
Po~t A~hm, Texa~ 77641-1089
t~e~v~tm~ & CoCkatoo, fao.
8869 S. Hvcy. 69
Port Arthm, Tex. T7640
TO
Appro~d of thc following r.,ontra~ change ts ~,
To ~ adju~cn~ ~ ~ for fl~ ~ ~, ~ to
$B89,S00.00
(+) 6{,o00,00
AMOUNT OF THIS CHAI~IOR ORDER;
(+)$63,000,00
TOTAL, RBVISF. D CONTIt, AC'r AWiOUN-i' INCI JUDINO TFflS
CHANGE ORDF~
$05~,$00.00
Polk,
COrbeL'rING ENGIN~m.,9
JUN-20-2003 FR] OI:17 PM $OH~UMBURO & POLK
F~X NO, 14098660337
P, 03/03
PAGE 0~/02
Port A~th~ Bugnoss P~rk
Conira~t V - Road Improv~aon~
Chanllc Order No. 1
P~ 2 of 2
ORIGINAL COiN'TRACT TI~E~
REVISED CONTRACT TIME DUE TO
PRevIOUS CliAl,~OE ORDI~RS:
TItlS CHANOB ORDER;
INCLUDING Tlti~ CIIANO~ ORDIiR;
120 Consoautivc C~lon~ ~
0 Cons~cutlvo C_~l~dar Days
120 CoIla~'utlve C~lel~l~r L~yf
'Conim~o~ ac~,nowledlto~ and ~ a~, il~ ~ljustm~ts ia co~ ~ ~ ~a~ ~
sz~l~ in ~s C~ Or~r mp~ ~1 co~on for ~1 ~ m~d ~ in
~stlt~ an a~t ~ ~ s~ Cont~r th~ ihs Ch~e ~ ~ts m ~1
i~lusiv% mu~lly ~ u~ ~t ~ ~ Co~ ~d ~ ~r will ~ aU
SUBMITI'ED BY: RIRVIEWED BY: APPROVED BY;
Cobb. stem,'tots, ln~. Dewlopmem Coqx~ra~on
Contramx~ Owne~
Pot~ Anlme Economlo Dovelopm~t Corporation
Excavators & Construotot~, I~.
$chaumburg & Polk, Inc.