HomeMy WebLinkAboutPR 12236: CONTRACT ALLCO INC. MEMORANDUM
CITY OF PORT ARTHUR
UTILITY OPERATIONS DEPARTMENT
TO:
FROM:
DATE:
SUBJECT:
Steve Fitzgibbons, City Manager
Daniel Shepherd, Director of Utility Operations
June 17, 2003
Proposed Resolution No. 12236
COMMENTS
RECOMMENDATION:
I recommend that the City Council approve Proposed Resolution No. 12236 executing Change Order
No. One to the contract between the City and Allco, Inc., related to the water line rehabilitation
project. This change order increases the contract amount to $31,731.00.
BACKGROUND:
In September 2002, the City authorized Allco, Inc. for the ;vater line rehabilitation project. This
project is part of the city-wide water system improvement plan. It includes the replacement of
approximately 93,500 feet of the City's water lines with the greatest break frequency. This change
order adjusts the quantities of some items not included in the original contract and changes the
alignment of two line segments due to conflict with existing structures.
BUDGET/FISCAL EFFECT:
This change order increases the contract amount by $31,731.00 to $4,190,14I .90.
STAFF/EMPLOYEE EFFECT:
No anticipated effect on staffing. City staff will continue to monitor the progress of this project.
SUMMARY:
I recommend that the City Council approve Proposed Resolution No. 12236 authorizing execution of
Change Order No. One to the contract with Allco, Inc.
/aw
P.R. No. 12236
06/17/03/aw
RESOLUTION NO.
A RESOLUTION APPROVING CHANGE ORDER NO. ONE TO THE CONTRACT
BETWEEN THE CITY OF PORT ARTHUR AND ALLCO, INC, RELATED TO THE
WATER LINE REHABILITATION. (INCREASE THE CONTRACT AMOUNT BY
$31,731.00) ACCOUNT NO. 427-1626-532.85-00, PROJECT NO. 427005.
WHEREAS, the City Council of the City of Port Arthur has awarded the contract for
water line rehabilitation to ALLCO, Inc., in Resolution No.02-293; and,
WHEREAS, Arceneaux and Gates Consulting Engineers, Inc., as owner's
representative, has reviewed and recommends approval as denoted in Exhibit "A" of Change
Order No. One, copy attached hereto and made a part hereof as Exhibit "B", for additional
work not included in original project bid; increased contract amount of $31,731.00;
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR:
THAT, the City Manager be authorized to execute Change Order No. One (Exhibit
B) to the referenced contract, for additional work not included in original project bid; and,
THAT the total contract amount to be adjusted will be from Four Million One
Hundred Fifty-Eight Thousand Four Hundred Ten Dollars and 90/100 dollars
($4,158,410.90) to Four Million One Hundred Ninety Thousand One Hundred Forty-One
Dollars and 90/100 dollars ($4,190,141.90); and,
ThAT the contract time will be increased by 130 calendar days; and,
THAT no other conditions or covenants of the contract are changed or waived by this
Change Order; and,
THAT a copy of the caption of this Resolution be spread upon the Minutes of the
City Council.
P.R. No. 12236
06/17/03/aw
Page 2 of 3
READ, ADOPTED AND APPROVED THIS day of ,2003
at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following
vote:
AYES: Mayor
Councilmembers
NOES: ,,
Oscar G. Ortiz
Mayor
ATTEST:
Carolyn Dixon, City Secretary
APPROVED AS TO FORM:
Mark Sokolow, City Attorney
APPROVED:
Steve Fitzgibbons, City Managerj ./~
iel Shepl'r~r~7-, D~ of Utility Operations
P.R. No. 12236
06/17/03/aw
Page 3 of 3
APPROVED AS TO AVAILABILITY OF FUNDS:
Rebecca Underhill, Director of Finance
Account No. 427-1626-532.85-00
Project No. 427007
EXHIBIT A
Memo
CITY OF PT. ARTHUR
UTILITY OPERATIONS-ADH.
To: Mr. Dan Shepherd
Front: Joe M. Wilson, Jr., E.I.T.
CC~ Project File
Date: June 16, 2003
Entail:
Fa~ 983-8254
Re:. Explanation of Items, Change Order No. 1
Job.' 01-CPA-231
Mr. Shepherd,
The following is a bdef explanation of the Items included in Change Order No. 1. Please review and if
you have any questions or require further information please contact me at my office.
ITEM NO: 1. Additional cost to provide tie of 8' PVC to ~xistJng 12" water line (project
line No. 2g). This item is to provide an additional tie in of the new 8" water line
(project line No. 29) to the existing 12" water line at 5th Ave. This is an additional
tie in that was not included in the edginal project bid. Installation of this tie in will
help provide better flow distribution for the new lines being installed.
Additional cost to install 200 L.F. lO" PVC (project line No.46). This item is to
install an additional 200 L.F. of 10" C-900 PVC that is to be supplied by the City.
This change is necessary due to unexpected field conditions that require moving
the tie in point of the new 10" water line approximately 200'. This additional water
line footage will relocate the tie in point to a segment of the existing 10" water line,
which has not been bypassed and provide a better installation.
Additional cost to install ii" water line to alternate alignment (project line
No, 33). This item is for the changing of the alignment of the proposed 8" C-900
PVC water line. q~is change is required in order to avoid placing the new water
line under an existing structure, The change in alignment will relocate the water
line approximately 10' and require the demolition of a existing garage as well as
removal of several large bees. This change of alignment will provide an easier to
maintain water line and allow the installation to proceed without placing the water
line under any structures.
Additional cost to install 8" water line to alternate alignment (project line
No. 34). This item is to change the alignment and materials for installation of the
new 8" water line. This change is required due to the necessity of having to install
the new 8" waterline under an existing garage structure by boring. This will also
change the materials and methods used for the construction of the portion of the
water line under the structure. The C-900 PVC pipe called for in the original bid
will be replaced with 8" High Density Poly Ethylene (HDPE). This type of pipe will
provide an installation with no joints or seems thus eliminating the chance of
leaking from a joint in the pipe. The line will be installed by boring and the annular
space around the HDPE pipe will be grouted to minimize the chances of
settlement if any. Using this method there will be no need to demolish the
existing structure to install the new water line but it will require the replacing of a
concrete driveway that will need to be removed for the construction.
· Page 2
EXHIBIT B
ARCENEAUX
&
GATES
DATE: June 16, 2003 JOB NO.
AGREEMENT DATE: October 1, 2002
01-CPA-230 [231], Contract No. 1
NAME OF PROJECT:
WATER LINE REHABILITATION
OWNER: CITY OF PORT ARTHUR
CONTRACTOR: ALLCO, INC.
The following changes are hereby made to the CONTRACT DOCUMENTS:
Additional Cost To Provide Tie In Of 8" PVC Waterline to
Existing 12" Water Line (Project Line No. 29).
(a.) Additional 12" x 8" TS & V Increase Bid Item No. 12
From 19 Each to 20 Each [Original Bid $2750.00]
(b.) Additional Labor, Materials Mobilization & Demobilization
(c.) 5 Days Additional Construction Time
2. Additional Cost To Install 200 L.F.I 0" PVC (Supplied By The City)
(a.) Furnish Additional Materials, Labor, Mobilization
& Demobilization (Project Line No. 46)
(b.) 12 Days Additional Construction Time
Additional Cost to Instell 8" Waterline to Alternate Alignment
(ProJect Line No. 33)
(a.) Demo And Haul Off Garage
(b.) Demo Garage Slab
(c.) Demo Existing Concrete Approach
(d.) Replace DrivesWith Limestone
(e.) Remove FencesAs Required
(f.) RemoveAnd HauI Off Shrubs
(g.) Remove And Haul Off Trees.
(h.) 20 Days Additional Construction Time
Additional Cost to Install 8" Waterline to Alternate
Alignment (Project Line No. 34)
(a.) Bore HDPE DR11 Waterline Under Building & Grout Annular Space
(b.) Remove and Replace Concrete Driveway
(c.) 15 Days Additional Construction Time
[-1 $~
7.343.00
8.555.o0
[.1 $ tt.s5a.oo
TOTAL [+] $ 31 3:!1 .oO
I ARCENEAUX
&
GATES
CHANGE ORDER NO. t
June 16, 2003
Job No. 0I-CPA-230 [2311, Contract No. 1
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $4,158,410.90
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER:
The CONTRACT PRICE due to this CHANGE ORDER will be [increased]
by: $:tl ,731.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be
$4,158,410.90
$4,190,141.90
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 365 Calendar Oavs
CLTRRENT CONTRACT TIME adjusted by previous CHANGE ORDER: $65 Calendar Days
CURRENT DATE OF COMPLETION: October 31,2003
CONTRACT TIME due to this CHANGE ORDER will be increased by * -130- Calendar Days
· Note: 78 Days for Weather Delays Experienced Between 10/31/02 - 5/31/03, 52 Additional Days
Construction Time Due to Change Order.
The New DATE OF COMPLETION: March 9, 2004
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCEN X &~
ACCEPTED BY:
CITY OF PORT ARTHUR
2/2 C:~PROJECTS~CPA231 \CO# 1 _6-54)3.doc