HomeMy WebLinkAbout(D2) 2023Aug01 City PtA Contrct Street Progrm (2)City of Port Arthur
Capital Street
Program
AUGUST 01, 2023, CITY COUNCIL UPDATE
South 1st Ave – Sabine Pass
TxDOT funded 75% / 25% matching
Elite Construction - Completed May 25th, 2023
Contract Amount $782,887
Mechanic Street – Sabine Pass
TxDOT Funded 75% / 25%
Matching
Available TxDOT Funding of
$2,374,625
Construction Plans / Spec’s
ready for Letting August 30,
2023
Sewer Line Rehabilitation
Complete
Woodworth Blvd from Thomas Blvd to Lakeshore Drive
Plans complete May 1st , 2023 - $7.2 Million Budget
5th & 6th Street
Completed April 24, 2023
Gulf Coast Construction
Contract Total = $ 1,733,007
AUGUST 1, 2023 – STREET CONTRACT TOTALS
$ 9,572,924.00
$ 3,737,229.45
$ 4,138,899.00
$ 2,069,528.00
$19,518,580.45
CONTRACTORS TOTALS BY
DISTRICT YEAR 2021-2023
JULY 2021 PLANED STREET PROGRAM (FISCAL
YEAR 2021-2022
TOTAL DISTRICT 1 $ 2,360,543.00
TOTAL DISTRICT 2 $ 2,347,640.00
TOTAL DISTRICT 3 $ 1,376,405.56
TOTAL DISTRICT 4 $ 4,886,745.00
GRAND TOTAL $ 10,971,333.56
District 1
Contract
Allco Construction $4,377,370
Start March 6, 2023 – 365 Calendar Days
8th Ave @ 8th Street NO.STREET NAME CONSTRUCTION LIMITS TENTATIVE START
DATE
1 Beaumont Ave (Thomas Blvd to 7th St) - (ST3009)Nov-23
2 Nashville Ave (11th St. to Rev Ransom Howard St.) -
(ST3011)Oct-23
3 Allien Place (Procter St to Seawall) - (ST3013)Jun-23
4 14th St. (Bluebonnet Ave. to Woodworth Blvd.) -
(ST3016)July/Aug 23
5 14th St.(Woodworth Blvd. to 4th Ave) - (ST3017)July/Aug 23
6 29th St (SE End to 4th Ave) - (ST3018)Dec-23
7 W 6th St.(Abe Lincoln Ave. to Harry Denbo Ave.) -
(ST3021)Jan-24
8 Avant Ave.(Proctor St. to Seawall) - (ST3024)May-23
9 8th Ave.(Thomas Blvd to 9th St.) - (STXXXX)Week of 3/13
10 8th Ave. (9th St. to 8th St.) - (STXXXX)Week of 3/13
11 8th Ave. (8th St. to 7th St.) - (STXXXX)Week of 3/13
12 8th Ave. (7th St to Procter St) - (STXXXX)Week of 3/13
13 15th St.(Woodworth Blvd. to 3rd Ave) - (STXXXX)Week of 3/20 (Tree
Removal Portion)
14 Stilwell Blvd (14th St. to Gillham Circle) - (ST3072)Sep-23
15 West 9th St. (Welford Ave. to Lincoln Ave.) - (STXXXX)Jun-23
16 Welford Ave.(Rev. Ransom Howard - Procter St.) -
(STXXXX)Feb-24
Street Name From Street To Street Pavement
Width (ft)
Pavement
Length (ft) STREET TYPE
2019 CIP
BUDGETED
AMOUNT
CONTRACTED
COST
CONTRACTOR
/ CITY FORCES COMPLETION
DATE
DISTRICT #1
BEAUMONT AVE THOMAS BLVD 7TH ST 22 1,700 Open Ditch Asphalt 103,890$ 355,791$ ALLCO Jun-23
NASHVILLE AVE REV DR RANSOM
HOWARD ST 11TH ST 18 1,234 Open Ditch Asphalt 61,700$ 235,698$ ALLCO May-23
STILLWELL BLVD 14TH ST GILLHAM CIR 40 570 BOULEVARD 292,738$ ALLCO Jun-23
WELLFORD AVE WEST 7TH ST WEST PROCTOR ST 22 985 Asphalt C&G 198,224$ ALLCO May-23
ALLIEN PL PROCTOR ST SEAWALL 23 744 C & G Composite 85,560$ 214,946$ ALLCO Aug-23
14TH ST BLUEBONNET AVE WOODWORTH BLVD 24 1,700 Open Ditch Asphalt 113,350$ 343,922$ ALLCO Sep-23
14TH ST WOODWORTH BLVD 4TH AVE 27 1,500 Asphalt C & G 202,500$ 286,676$ ALLCO Jul-23
15TH ST WOODWORTH BLVD 3RD AVE 27 1,000 Asphalt C&G 175,195$ ALLCO Jul-23
29TH ST SW END 4TH AVE 24 953 Open Ditch Asphalt 46,670$ 302,785$ ALLCO Jul-23
W 6TH ST ABE LINCOLN AVE HARRY DENBO AVE 20 1,200 Open Ditch Asphalt 93,330$ 220,405$ ALLCO May-23
W 9TH ST WELLFORD AVE LINCOLN AVE 28 2,150 Asphalt C&G 609,916$ ALLCO Jun-23
AVANT AVE PROCTOR ST SEAWALL 23 706 C & G Composite 81,190$ 104,621$ ALLCO Aug-23
7TH AVE THOMAS BLVD PROCTOR ST 20 2,845 Asphalt C&G 522,526$ ALLCO Sep-23
8TH AVE THOMAS BLVD PROCTOR ST 20 2,845 Asphalt C&G 685,012$ ALLCO Aug-23
SOUTH 1ST AVE GRANGER CANAL PORT SABINE PASS 24 1,452 CONCRETE PAVEMENT 813,744$ ELITE May-23
5TH & 6TH ST ATLANTA NASHVILLE 26 3,728 Asphalt C&G 1,733,007$ GULF COAST Apr-23
W 7TH ST SH82 MLK BLVD ABE LINCOLN AVE 30 2,911 Asphalt C&G 1,468,959$ GULF COAST May-19
AUSTIN AVE 19TH ST LAKESHORE DR 24 6,018 Asphalt C&G 281,172$ LD CONST Feb-22
14TH ST HOUSTON AVE STILLWELL BLVD 24 1,895 Asphalt C&G 168,126$ LD CONST Mar-23
DALLAS AVE 19TH ST THOMAS BLVD 24 5,622 Asphalt C&G 559,461$ LD CONST Mar-22
7.91 MILES TOTAL DISTRICT 1 2,360,543$ 9,572,924$
District 2 & 3 Contract
29th Street @ 9th Ave
NO.STREET NAME CONSTRUCTION LIMITS START DATE
1 Duff Dr (Procter St to Lakeshore Dr) - (ST3035)
2 Pecos Ave (Lewis Dr to 7th St) - (ST3038)
3
Williams Ave (Lewis
Dr to 6th Ave) -
(ST3039)
Williams Ave (Lewis Dr to 6th Ave) - (ST3039)
4 Lakefront Dr (T.B. Ellison Pkwy to N. Levee) - (ST4002)Complete
5 Lakefront Dr (T.B. Ellison Pkwy to S. Levee) - (ST4002)Complete
6 Ferndale Dr (Lombardy Dr to North Park Dr) - (ST1P13)
7 10th Ave (West 42nd St to 40th St) - (ST3049)
8 28th St (9th Ave to KCS RR Tracks) - (ST3050)4/15/2023
9 32nd St (Woodrow Dr to Twin City Hwy) - (ST3051)
10 7th Ave (39th St to32nd St) - (ST3053)
11 Evergreen Dr (Ferndale Dr to Griffin Dr) - (ST3054)
12 Lansing Ave (39th St to 42nd St) - (ST3055)
13 5th Ave (28th St to 25th St) - (ST3059)Complete
14 28th St (4th Ave to 8th Ave) - (ST3060)Complete
15 40th St (9th Ave to West of 10th Ave to DE) - (ST3049)
16 Tyrrell Pkwy (32nd St to Woodlawn St) - (ST4006)
17 Woodrow Dr (32nd St to Rosedale Dr) - (ST4003)
18 West Park Dr (32nd St to South Park Dr) - (ST4005)
19 Sunken Court (Rosedale Dr to Lombardy) - (ST4007)4/24/2023
20 Evergreen Dr Bernhardt Dr to 39th St 4/10/2023
Gulf Coast - $7,734,508
DISTRICT #2
DUFF DR LAKESHORE DR PROCTOR ST EXT 21 644 Asphalt C & G 67,620$ 182,526$ GULF COAST
LAKE FRONT DRIVE T.B. ELLISON NORTH LEVEE RD 30 2,460 Open Ditch Asphalt 293,293$ 397,531$ GULF COAST Feb-23
LAKE FRONT DRIVE T.B. ELLISON SOUTH LEVEE RD 24 883 Open Ditch Asphalt 125,600$ 230,560$ GULF COAST Mar-23
PECOS AVE 7TH ST LEWIS DR 21 1,659 Asphalt C & G 174,195$ 462,653$ GULF COAST
WILLIAMS AVE 6TH ST LEWIS DR 25 1,989 Asphalt C & G 248,625$ 578,587$ GULF COAST
PROCTOR ST EXT RR TRK DUFF DR 22 8,500 OPEN DITCH 519,445$ 1,885,372$ REBID
1.45 MILES TOTAL DISTRICT 2 2,860,841$ 3,737,229$
Street Name From Street To Street Pavement
Width (ft)
Pavement
Length (ft) STREET TYPE
2019 CIP
BUDGETED
AMOUNT
CONTRACTED
COST
CONTRACTOR
/ CITY FORCES COMPLETION
DATE
DISTRICT #3
10TH AVE 40TH ST DEAD END 18 1,008 Open Ditch Asphalt 50,400$ 165,335$ GULF COAST
28TH ST 9TH AVE KCS RR TRACKS 20 1,232 Open Ditch Asphalt 68,444$ 232,252$ GULF COAST
32ND ST WOODROW DR TWIN CITY HWY 22 2,918 Open Ditch Asphalt 229,350$ 525,242$ GULF COAST
7TH AVE 39TH ST 32ND 18 2,637 Open Ditch Asphalt 58,489$ 429,520$ GULF COAST
EVERGREEN DR FERNDALE DR GRIFFING DR 18 1,042 Asphalt C & G 78,150$ 369,869$ GULF COAST
FERNDALE DR LOMBARDY DR NORTH PARK DR 20 2,060 Asphalt C & G 166,866$ 300,417$ GULF COAST
LANSING AVE 42ND 39TH ST 19 1,588 Open Ditch Asphalt 11,400$ 253,669$ GULF COAST
SUNKEN COURT LOMBARDY DR SOUTH PARK DR 40 1,240 BOULEVARD 202,063$ 223,270$ GULF COAST
TYRRELL PKWY 32ND ST WOODLAWN 20 1,112 Asphalt C & G 214,245$ 312,227$ GULF COAST
WOODROW DR 32ND ST ROSEDALE DR 20 775 Asphalt C & G 202,073$ 303,918$ GULF COAST
WEST PARK DR 32ND ST SOUTH PARK DR 20 783 Asphalt C & G 141,980$ 222,624$ GULF COAST
5TH AVE 28TH 25TH 18 1,151 Open Ditch Asphalt 51,156$ 219,523$ GULF COAST Mar-23
28TH ST 4TH AVE 8TH AVE 20 1,541 Open Ditch Asphalt 85,600$ 264,738$ GULF COAST Mar-23
40TH ST 9TH AVE GSU INTERURBAN
ROW 20 455 Open Ditch Asphalt 132,801$ GULF COAST
60TH US 69 9TH AVE 20 3,789 Open Ditch Asphalt 183,494$ GULF COAST Nov-21
4.42 MILES TOTAL DISTRICT 3 2,038,838$ 4,138,899$
District 1 & 4
Complete-June
2022
LD Construction – $2,213,300
Completed 31 Streets
Completed June 6th , 2022
8.75 Total Miles Rehabilitated
NO.STREET NAME CONSTRUCTION LIMITS DISTRICT LENGTH STATUS
1 AUSTIN AVE GULFWAY TO 19TH STREET 1 1,196 Complete
2 AUSTIN AVE 19TH STREET TO DD#7 1 200 Complete
3 AUSTIN AVE 8TH STREET TO 6TH STREET 1 722 Complete
4 AUSTIN AVE PROCTER TO 4TH STREET 1 360 Complete
5 14TH STREET HOUSTON AVE TO FORTWORTH AVE.4 1,083 Complete
6 14TH STREET FORTHWORTH AVE TO AUSTIN AVE.4 360 Complete
7 14TH STREET AUSTIN AVE. TO STILLWELL BLVD.4 3,717 Complete
8 50TH STREET LINKWOOD ST. TO SHORTLINE ST.4 1,096 Complete
9 60TH STREET HAZEL AVE. TO DIAMOND ST.4 2,180 Complete
10 60TH STREET DIAMOND ST. TO LEVEE 4 1,644 Complete
11 63RD STREET JADE AVE. TO KATY - BOBBY ST.4 1,958 Complete
12 63RD STREET PAT AVE TO DIAMOND STREET 4 6,276 Complete
13 ALABAMA AVE DORSEY TO HALL STREET 4 1,301 Complete
14 DALLAS AVE THOMAS DR TO GULFWAY 4 1,821 Complete
15 DALLAS AVE GULFWAY TO 19TH STREET 4 1,078 Complete
16 DALLAS AVE 19TH STREET TO DD#7 4 200 Complete
17 DALLAS AVE 5TH TO REV RANSOM HOWARD AVE 4 720 Complete
18 DALLAS AVE REV RANSOM HOWARD TO 8TH STREET 4 360 Complete
19 DALLAS AVE 8TH STREET TO THOMAS BLVD 4 1,750 Complete
20 DAVIS AVE HWY 365 TO DORSEY STREET 4 2,543 Complete
21 DIAMOND AVE 60TH TO 63RD STREET 4 2,974 Complete
22 HAZEL AVE 61ST STREET TO HWY 73 ACCESS
ROAD 4 999 Complete
23 HOUSTON AVE H.O. MILLS TO LINKWOOD 4 1,240 Complete
24 LOUSIANA AVE WEAVER STREET TO HWY 365 SERVICE
ROAD 4 799 Complete
25 MISSISSIPPI AVE DORSEY TO HALL STREET 4 1,301 Complete
26 PASTEL AVE HWY 73 TO D.E.4 1,086 Complete
27 SASSINE AVE HWY 365 TO WEAVER 4 1,070 Complete
28 SHIRLEY STREET WEST PORT ARTHUR RD TO 58TH
STREET 4 2,500 Complete
29 SHIRLEY STREET 58TH STREET TO RAY AVE 4 2,269 Complete
30 SHORTLINE AVE W. 50TH ST TO DEAD END 4 646 Complete
31 WEAVER SASSINE TO LOUSIANA 4 754 Complete
TOTAL ( MILES)8.75
Street Name From Street To Street Pavement
Width (ft)
Pavement
Length (ft) STREET TYPE
2019 CIP
BUDGETED
AMOUNT
CONTRACTED
COST
CONTRACTOR
/ CITY FORCES COMPLETION
DATE
DISTRICT #4
DAVIS AVE FM 365 DORSEY ST 18 2,625 Open Ditch Asphalt 160,865$ LD CONST Nov-21
LOUISIANA WEAVER FM 365 20 760 Open Ditch Asphalt 23,567$ LD CONST Feb-22
MISSISSIPPI AVE HALL ST DORSEY ST 20 1,322 Open Ditch Asphalt 82,216$ LD CONST Feb-22
ALABAMA AVE HALL ST DORSEY ST 18 1,317 Open Ditch Asphalt 91,587$ LD CONST
SASSINE WEAVER FM 365 22 810 Open Ditch Asphalt 74,887$ LD CONST Oct-21
60TH ST LEVEE HAZEL AVE 22 3,720 Open Ditch Asphalt 122,450$ 158,088$ LD CONST Nov-21
63RD DIAMOND ST JADE AVE 22 4,190 Open Ditch Asphalt 499,543$ LD CONST Dec-21
14TH ST HOUSTON STILLWELL BLVD 22 1,717 Open Ditch Asphalt 104,930$ 168,126$ LD CONST Mar-22
50TH ST SHORELINE HOUSTON AVE 18 527 Open Ditch Asphalt 26,350$ 39,330$ LD CONST Apr-22
DIAMOND AVE 60TH ST 63RD 18 3,000 Open Ditch Asphalt 168,032$ LD CONST Jan-22
HAZEL AVE SH 73 61ST ST 20 3,660 Open Ditch Asphalt 111,390$ 214,033$ LD CONST Feb-22
HOUSTON AVE LINKWOOD SH 73 HO MILLS 22 1,281 Open Ditch Asphalt 53,145$ LD CONST Jan-22
PASTEL SH73 SHIRLEY 20 762 Open Ditch Asphalt 37,520$ LD CONST Jan-22
SHIRLEY ST RAY 58TH ST 22 2,250 Open Ditch Asphalt 72,039$ LD CONST Mar-22
SHIRLEY ST 58TH WEST PTA ROAD 22 2,630 Open Ditch Asphalt 175,128$ LD CONST Mar-22
SHORTLINE AVE 58TH DEAD END 18 643 Open Ditch Asphalt 51,422$ LD CONST Nov-21
5.91 MILES TOTAL DISTRICT 4 365,120$ 2,069,528$
First Phase from 36th Street to 30th St
Second Phase from 30th St to Evergreen Drive
Four (4) lane concrete pavement with improved 32nd and 25th
street intersections
Estimated Project Cost $14.1 Million
Received CDBG-DR Grant - $1 Million for Utility Adjustments
Additional funding sources TxDOT / US DOT
9th Ave Widening Project – from 36th
St to KCS RR tracks
9th Ave Utility Relocations
9th Ave from 36th to 30th
street
9th Ave from 30th to KCS RR
tracks
West 7th from Houston Ave to SH82 (MLK)
Port of Port Arthur Freight Access
Challenges
Street Program – GIS Inventory Map