HomeMy WebLinkAbout(D2) 2023Aug01 City PtA Contrct Street ProgrmCity of Port Arthur Capital Street Program August 01, 2023, city council update 1 South 1st Ave – Sabine Pass TxDOT funded 75% / 25% matching Elite Construction - Completed May 25th, 2023 Contract Amount $782,887 2 Mechanic Street – Sabine Pass TxDOT Funded 75% / 25% Matching Available TxDOT Funding of $2,374,625 Construction Plans / Spec’s ready for Letting August 30, 2023 Sewer Line Rehabilitation Complete 3 Woodworth Blvd from Thomas Blvd to Lakeshore Drive Plans complete May 1st , 2023 - $7.2 Million Budget 4 5th & 6th Street Completed April 24, 2023 Gulf Coast Construction Contract Total = $ 1,733,007 5 AUGUST 1, 2023 – STREET CONTRACT TOTALS 6 District 1 Contract Allco Construction $4,377,370 Start March 6, 2023 – 365 Calendar Days 8th Ave @ 8th Street 7 8 District 2 & 3 Contract 29th Street @ 9th Ave Gulf Coast - $7,734,508 9 10 District 1 & 4 Complete-June 2022 LD Construction – $2,213,300 Completed 31 Streets Completed June 6th , 2022 8.75 Total Miles Rehabilitated 11 12 First Phase from 36th Street to 30th St Second Phase from 30th St to Evergreen Drive Four (4) lane concrete pavement with improved 32nd and 25th street intersections Estimated Project Cost $14.1 Million Received CDBG-DR Grant - $1 Million for Utility Adjustments Additional funding sources TxDOT / US DOT 9th Ave Widening Project – from 36th St to KCS RR tracks 13 9th Ave Utility Relocations 9th Ave from 36th to 30th street 9th Ave from 30th to KCS RR tracks 14 West 7th from Houston Ave to SH82 (MLK) Port of Port Arthur Freight Access 15 Challenges 16 Street Program – GIS Inventory Map 17