HomeMy WebLinkAboutPR 23350: SLUDGE REMOVAL FOR WATER PLANT RESERVOIR, CHANGE ORDER NO. 1 AND CLOSEOUT 0
rn
INTEROFFICE MEMORANDUM
Date: September 18, 2023
To: The Honorable Mayor and City Council
Through: Ronald Burton, City Manager
From: Calvin Matthews, P.E., Water Utilities Director
RE: PR 23350—Sludge Removal for Water Plant Reservoir, Change Order No. 1
and Closeout
Introduction:
The intent of this Agenda Item is to seek the City Council's approval of Change Order No. 1
for the extra sludge removal by $2,859.34 and close out documents for the City of Port Arthur
Sludge Removal for the Water Plant Reservoir Project with American Process Group, LLC.,
and to authorize the City Manager to release the retainage invoice of$52,413.72.
Back round:
The Council passed Resolution No. 23-154 to award American Process Group, LLC. for the
Sludge Removal service for the Water Purification Plant Reservoir Project, in the original
contract amount of$1,045,415.00.
Change Order No. 1 has an increase of$2,859.34 for the extra 23.59 tons of sludge removal.
Budget Impact:
Change Order No. 1 will increase the total project cost by $2,859.34
The new contract amount is $1,048,274.34. Funds are available in Account No. 405-40-000-
8516-00-00-000, Project No. WS-0018-CON.
Recommendation:
It is recommended that the City Council adopt Proposed Resolution No. 23350, to adjust the
project scope and total contract price, authorize the release of retainage, and close out the
project, as described/outlined above.
"Remember, we are here to serve the Citizens of Port Arthur"
PR No. 23350
9/18/23 bw
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 1 TO THE
CONTRACT WITH AMERICAN PROCESS GROUP, LLC.
OF TACOMA, WASHINGTON FOR THE SLUDGE
REMOVAL SERVICE FOR THE WATER PURIFICATION
PLANT RESERVIOR PROJECT, INCREASING THE
CONTRACT AMOUNT BY $2,859.34 AND ACCEPT THE
PROJECT COMPLETION TO RELEASE THE
RETAINAGE. THE FINAL CONTRACT TOTAL IS
$1,048,274.34, ACCOUNT NO. 405-40-000-8516-00-00-000,
PROJECT NO.WS-0018-CON.
WHEREAS, pursuant to Resolution No. 23-154, City Council awarded a contract to
American Process Group,LLC. of Tacoma, Washington, for the 7500 tons of Sludge Removal for
the Water Purification Plant Reservoir Project for the amount of$1,045,415.00; and,
WHEREAS, American Process Group, LLC. has submitted Change Order No. 1 for the
extra 23.59 tons of sludge removed,with an increase of$2,859.34(Exhibit"A"),bringing the new
contract amount to $1,048,274.34; and,
WHEREAS, American Process Group, LLC. has completed the project to the satisfaction of the
Project Engineer and the City staff; and,
WHEREAS, Sludge Removal for the Water Purification Plant Reservoir Project has been
completed in general accordance with City standards; and,
WHEREAS,the retainage for this project is due, as the work is completed and billed, and
the project engineer approves the release of retainage to American Process Group, LLC., in the
amount of$ 52,413.72 (see Exhibit"B").
NOW THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR:
PR No.23350
9/18/23 bw
Page 2 of 3
THAT,the facts and opinions in the preamble are true and correct; and,
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
execute Change Order No. 1 (Exhibit"A")to the contract with American Process Group, LLC. of
Tacoma, Washington, increasing the contract amount by $2,859.34, to a new contract total of
$1,048,274.34 and to accept the Sludge Removal at the Water Purification Plant Reservoir Project
completion, and authorize the Release of Retainage to American Process Group, LLC, in the
amount of$52,413.72 (Exhibit"B").
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED,AND APPROVED THIS day of , 2023 at a
Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor •
Councilmembers
NOES:
Thurman Bill Bartie
Mayor
PR No. 23350
9/18/23 bw
Page 3 of 3
ATTEST: APPROVED AS TO FORM:
(///tia t9,1),./tizip
Sherri Bellard , Va ecia Tizno
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
Ronald Burton
Ci an e
Calvin Matthews, .E.
Water Utilities Director
APPROVED AS TO AVAILABILITY
OF FUNDING:
ot,
Kandy Daniel Clifton Williams, CPPB
Finance Director Purchasing Manager
EXHIBIT A
(Change Order No. 1)
CHANGE ORDER NO. 1
ORIGINAL AGREEMENT DATE: August 24,2023
PROJECT DESCRIPTION: Sludge Removal at the Water Purification Plant Reservoir
REASON: Extra 23.59 tons of sludge removal
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT PRICE: $1,045,415.00
CURRENT CONTRACT PRICE (adjusted by previous CHANGE ORDER): $1,045,415.00
The Contract Amount due to this CHANGE ORDER will increase by: $2,859.34
The new CONTRACT AMOUNT including the CHANGE ORDER will be: $1,048,274.34
ORIGINAL CONTRACT DAYS: 120
NEW CONTRACT DAYS: No change
SIGNED AND AGREED TO on the 19th day of September , 2023.
AMERICAN PROCESS GROUP, INC.
Print Name: John DePalma
Title: Project Manager
SIGNED AND AGREED TO on the_day of , 2023.
CITY OF PORT ARTHUR
BY:
RONALD BURTON,
CITY MANAGER
American Process Group LLC
Truck Log Summary
Contract: Port Arthur WTP Biosolids Removal
Project # 23-010
APG
# Net
Date Truck Weight Notes
Loads Tons
23.59 Additional WT Removed
Total - 23.59
# Samples - 1.00
Average #DIV/0! 23.59
American Process Group LLC. INVOICE
1201 Pacific Avenue 6th Floor Tacoma,WA 98402 Date Number
August 24,2023 20242
Remit Payments to:
American Process Group LLC.
946 Boulder Boulevard
Stony Plain,AB, Canada
T7Z 0E6
Bill To: Ship To:
City of Port Arthur Port Arthur Water Treatment Plant
Attn:Accounts Payable 1101 HO Mills Blvd.
PO Box 1089 Port Arthur TX 77641 Port Arthur,TX 77640
Item Description Qty Rate Unit Total
Sludge Removal at the Water Purification Plant
Contract#23-154
August 1-21,2023 Progress Billing
001 Mobilization&Demobilization - $136,340.00 LS $ -
002 Sludge Dewatering, and Transport to City Landfill Additional - $ 121.21 WT $ -
003 Sludge Dewatering, and Transport to City Landfill 23.59 $ 121.21 WT $ 2,859.34
Subtotal $ 2,859.34
Retainage 5.00% $ (142.97)
Sales Tax 0.00% $ -
Invoice Total $ 2,716.38
All Amounts are in US Dollars. Due Net 30 days from Date of Invoice.
If you have any questions pertaining to this invoice please contact our Accounts Receivable Department:
Toll Free(866)960-1480 * Fax(780)968-1482
Residuals Management
Digester Cleaning * Watercourse Remediation * Dewatering * Dredging * Disposal * Lagoon Cleaning * Pumping
EXHIBIT B
(Release of Retainage Invoice)
CITY OF PORT ARTHUR, TEXAS
Retainage Form
Project : Sludge Removal at the Water Purification Plant Reservoir
Contract Number 23-154 Project# WS0018-CON
General Contractor American Process Group. LLC
Construction Day: 120
Percent Completion 100.3% Percent Time Completion : 100.0%
Original Contract Amount $1,045,415.00
Plus Additions: $ 2,759.34
Deducts:
Adjusted Contract Amount: $ 1,048,274.34
Work Performed to Date: $1,048,274.34
Less 5% Retainage $52,413 72
Net Amount Earned to Date:
Original Materials Stored:
Stored Materials Used Previous Periods:
Stored Materials Used This Period:
Total Materials Stored Close of This Period: $
Less 15% Retained on Stored Material; $
Sub-Total:
Less Previous Payments:
****5% Retainage**** $ 52,413.72
RECOMMEND APPROVAL
7 -- (
Jess Li /Utility Engineer
/q2 202,
Calvi atthews/Utility Dep ment Director
American Process Group LLC. INVOICE
OPD 1201 Pacific Avenue 6th Floor Tacoma,WA 98402 Date Number
August 30,2023 20243
Remit Payments to:
American Process Group LLC.
946 Boulder Boulevard
Stony Plain,AB, Canada
T7Z 0E6
Bill To: Ship To:
City of Port Arthur Port Arthur Water Treatment Plant
Attn:Accounts Payable 1101 HO Mills Blvd.
PO Box 1089 Port Arthur TX 77641 Port Arthur, TX 77640
Item Description Qty Rate Unit Total
/ Sludge Removal at the Water Purification Plant
Contract#23-154
Retainage Release
001 Release of 5%Retainage on$1,048,274.34 Contract 0.05 $1,048,274.34 LS $ 52,413.72
Subtotal $ 52,413.72
Retainage 0.00% $
Sales Tax 0.00% $
Invoice Total $ 52,413.72
All Amounts are in US Dollars. Due Net 30 days from Date of Invoice.
If you have any questions pertaining to this invoice please contact our Accounts Receivable Department: