INTEROFFICE MEMORANDUM
Development Services Department
Code Compliance-Demolition Division
Date: September 12,2023
To: Ronald Burton, City Manager: Pamela Langford, Assistant City Manager/Director of Development Services
From: Darlene Thomas-Pierre. Code Compliance Manager
Re: P. R. NO. 23353 — RATIFYING CHANGE ORDER NO. 1 TO 07/19/2023 CONTRACT (GROUP A)
WITH LARK GROUP, INC., FOR THE REMOVAL OF 408 HALL STREET, IN THE AMOUNT
OF$4,700.00.
COMMENT
Nature of the Request:
Staff recommends that the City Council adopt P. R.No.23353 thereby ratifying Change Order No. 1 to the 07/19/2023(Group
Al contract with Lark Group,Inc.,in the amount of$28,600.00 for demolition of six(6)residential structures located throughout
the city. Change Order No. I removes 408 Hall Street,decreasing the contract amount by$4,700.00,.
Staff Analysis/Considerations:
On June 20,2023, City Council approved Resolution No. 23-267 awarding the contract for Group A to Lark Group, Inc.. in
the amount of$28,600.00, for demolition of six (6) residential properties. On September 7, 2023, Change Order No. 1 was
executed removing 408 Hall Street,due to residence being occupied.This brings the contract to a new total of$23,900.00.
Recommendation:
Staff recommends that the City Council adopt P. R. No. 23193 thereby ratifying Change Order No. 1 to the July 19, 2023
contract(Group A)with Lark Group, Inc.,of Warren,Texas. Change Order No. 1 removes 408 Hall Street,decreasing the
contract amount by$4,700.00,resulting in a new contract amount of$23,900.00.
BudRet Consideration:
Acceptance of this recommendation will not require a budget amendment. Funding is available in Account No. 001-13-035-
5470-00-10-000(General Fund:Other Contractual Service).
STRUCTURES TO BE DEMOLISHED UNDER THIS CONTRACT:
1. 8425 Davis Avenue(Residence)
2. 620 Gizele Street(Residence/Garage/Accessory Building)
3. 408 Hall Street(Residence)
4. 6224 Charles Avenue(Residence/Attached Garage)
5. 5520 Terrace Avenue(Residence/Attached Garage)
6. 5017 Fort Worth Avenue(Residence)
"Remember we are here to serve the Citizens of Port Arthur"
1
P. R. NO. 23353
09/12/23 SR
RESOLUTION NO.
A RESOLUTION RATIFYING CHANGE ORDER NO. 1 TO
THE CONTRACT WITH LARK GROUP, INC., (GROUP A).
REMOVING 408 HALL STREET, DECREASING THE
CONTRACT AMOUNT BY $4,700.00 TO A NEW TOTAL OF
$23,900.00; ACCOUNT NO. 001-13-035-5470-00-10-000
(GENERAL FUND-OTHER CONTRACTUAL SERVICE)
WHEREAS, on June 20, 2023, City Council approved Resolution No. 23-267 awarding the contract
for Group A to Lark Group, Inc., in the amount of $28,600.00. for demolition of six (6) residential
structures located throughout the City; and
WHEREAS,on September 7, 2023, a Change Order was executed to remove 408 Hall Street (due to
residence being occupied); thereby reducing the contract amount by $4,700.00, attached hereto as Exhibit
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
THAT,the City Council of the City of Port Arthur hereby ratifies Change Order No. 1 to the July 19,
2023 (Group A) contract with Lark Group, Inc., of Warren, Texas decreasing the contract amount by
$4,700.00, to a new total of$23,900.00, attached hereto as Exhibit"A".
THAT a copy of the caption of this Resolution be spread upon the Minutes of the City Council.
READ, ADOPTED. AND APPROVED this the 26th day of September, A.D., 2023. at a Regular
Meeting of the City Council of the City of Port Arthur,Texas by the following vote:
AYES: MAYOR:
Councilmembers:
2
Pr
NOES:
P. R. NO. 23353
09/12/23 SR
MAYOR
ATTEST: APPROVED AS TO FORM:
Uazi ey
CITY SECRETARY CITY ATT RNEY
APPROVED FOR ADMINISTRATION:
CITY MANAGER
•
ASSISTANT CITY MANAGER/ CO I AG
DIRECTOR OF DEVELOPMENT SERVICES
APPROVED AS TO AVAILABILITY OF FUNDS: PROVED FOR PURCHASING:
JJ/I 4
I47ItRIM DIRECTO OF FINANCE PURCHASING MANAGER
3
EXHIBIT A
CITY OF PORT ARTHUR
DEMOLITION DIVISION
300 E. 4th Street,Suite 700 (409)983-8209
CONTRACT CHANGE ORDER FOR DEMOLITION WORK
CHANGE ORDER NO. 1
CONTRACTOR: LARK GROUP, INC.
PROJECT: 07/19/2023 Residential Demolition Contract (Group A-General Fund)
PROPERTY
ADDRESS: 408 Hall Street—Residence (Occupied)-(-$4,700.00)
The following contract items are hereby added, altered, or deleted as specified under the
following conditions:
ORIGINAL CONTRACT: $28,600.00 NEW CONTRACT: $23,900.00
1. The contract price $28,600.00 originally agreed to is hereby:
2. increased [] decreased [X] remains the same [ ] in the amount of$4,700.00.
increased [] decreased [] remains the same [ ] in the amount of_
3. This list of changes has been discussed and agreed to by the contractor of record and the
Demolition staff
4. This Change Order shall become part of the original contract as of the effective date
shown below.
The changes to be made by this Change Order are detailed below:
Deletion(s): We are removing the Residence at 408 Hall Street from the contract clue to the
Residence being occupied.
The above list of ch s are hereby declared valid and 'n full effect as of the 7th day of
September,2023. 4
f 'i
City Manager p iair�• anager
Demolition Superviso • 11. Murphy
Lark Enterprises
DTP/SR