INTEROFFICE MEMORANDUM
Date: September 29, 2023
To: The Honorable Mayor and City Council
Through: Ronald Burton, City Manager
From: Flozelle C. Roberts,EIT MEng, MBA, Public Works Director 1/
RE: P.R.23182—Gates Building Asbestos Remediation and Demolition Change
Order No. 1 —Removal and Disposal of Unforeseen Building Materials
Introduction:
This agenda item requests the City Council's approval of Change Order Number 1 for additional
fees associated with the removal and disposal of unforeseen materials during demolition,
abatement, and cleaning of the Gates Building.
Background:
Resolution 23-307 authorized the execution of a contract with Sitek Omni Services, LLC (Sitek
Omni) of Spring, Texas, for the demolition, abatement, and microbial cleaning of the Gates
Building. Sitek Omni and the Public Works Department performed a site visit where materials
beyond those listed in the contract were found. The materials,consisting of styrofoam insulation
panels and sheetrock demising and associated ductwork, showed signs of mold and termite
invasion. Therefore, additional funds are needed to remediate the additional findings.
Budget Impact:
The budgetary impact for the additional work is $20,800.00, and will be funded by the Capital
Improvement Fund—City Facility Improvements Account, 307-21-049-8512-00-10-000.
"Remember,we are here to serve the Citizens of Port Arthur"
444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
Recommendation:
It is recommended that the City of Port Arthur City Council approves Proposed Resolution
23182 authorizing and allocating additional funds for the removal and disposal of unforeseen
building materials during the demolition, abatement, and microbial cleaning of the Gates
Building for$20,800.00.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
PR No.23182
09/29/2023 FCR
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT
BETWEEN THE CITY OF PORT ARTHUR AND SITEK OMNI
SERVICES, LLC OF SPRING, TEXAS, FOR THE REMOVAL
AND DISPOSAL OF UNFORESEEN BUILDING MATERIALS
DURING DEMOLITION,ABATEMENT,AND CLEANING OF
THE GATES BUILDING WITH A BUDGETARY IMPACT OF
$20,800.00.FUNDING IS AVAILABLE IN ACCOUNT NO.307-
21-049-8512-00-10-000 (CAPITAL IMPROVEMENT FUND —
CITY FACILITIES IMPROVEMENTS), PROJECT NO.
BU0016-CON
WHEREAS, Resolution 23-307 authorized the execution of a contract with Sitek Omni
Services, LLC of Spring, Texas, through the Region 5 ESC Southeast Texas Cooperative
Purchasing Organization to demolish, abate, and clean the Gates Professional Building for the
amount of$148,800.00; and,
WHEREAS, Sitek Omni has submitted Change Order Number One(1), attached hereto as
Exhibit A, requesting additional funds for the removal and disposal of unforeseen building
materials encountered during base scope work, which consists of styrofoam insulation panels,
sheetrock demising, and ductwork behind the sheetrock demising wall; and,
WHEREAS, the budgetary impact for the additional work is $20,800.00, and will be
funded by the Capital Improvement Funds—City Facility Improvements Account.
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR:
THAT,the facts and opinions in the preamble are true and correct; and,
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
approve Change Order Number One (1)to the contract with Sitek Omni Services, LLC of Spring,
A. m
PR No.23182
09/29/2023 FCR
Page 2 of 3
Texas, increasing the contract amount by $20,800.00, in substantially the same form as attached
hereto as Exhibit A; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ,ADOPTED AND APPROVED this the day of , A.D.
2023, at a meeting of the City of Port Arthur, Texas,by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Thurman Bill Bartie
Mayor
ATTEST:
Sherri Bellard, TRMC
City Secretary
APPROVED AS TO FORM:
hAlux-p3
Valecia R Tizeno Esq.
q
City Attorney
PR No.23182
09/29/2023 FCR
Page 3 of 3
APPROVED FOR ADMINISTRATION:
on d Burt = ozelle 0 Roberts, ' , MEng, MBA, CPM
City Manager Directet Public 'S s
APPROVED AS FOR AVAILABILITY OF FUNDS:
OCkAA-,Z.) *LA&
Kandy Danie 9 Clifton E. Williams,Jr.,CPPB
Director of Finance Purchasing Manager
1'R No.23183
Exhibit A
Srirek Omni
*Selective and Structural Demolition • TDSHS Asbestos License #80-1070
*Asbestos and Lead Abatement • TDSHS. Lead License #2110624
Hazardous and Mold Remediation • TDLR Mold License #RCO-1218
September 29, 2023
Flozelle C. Roberts
Director of Public Works
City of Port Arthur
444 4th Street
Port Arthur, Texas 77640
(409) 983-8501
Flozelle.Robertsgportarthurtx.gov
SUBJECT: Proposal for Additive Demolition Work
Former Medical Building at 3617 Gates Blvd. in Port Arthur
Sitek Proposal#23-09-24
Sitek Contract Number for Region 5 ESC: 20230404 (Env. Services)
Sitek Contract Number for Region 5 ESC: 20230403 (Emergency Response)
Flozelle,
Sitek Omni Services, LLC (Sitek) submits following proposal, consisting of the selective
demolition and associated microbial cleaning of various interior materials encountered
beyond those identified in the original bid for work at the former medical building
located at 3617 Gates Boulevard in Port Arthur, Texas.
1. SCOPE OF WORK
Sitek responsible for:
A. Provide generators for electrical power needs and water as needed for work
added scope work.
B. Provide a Conex box on-site for storage of tools and equipment.
C. Selectively remove and dispose of the following building materials encountered
during base scope of work:
➢ Styrofoam Insulation Panels with Mold Contamination (panels coating
interior of perimeter concrete walls — metal bracketing to be cleaned for
mold and remain in-place);
➢ Sheetrock Demising Wall at Main Entry;
➢ Ductwork Behind Sheetrock Demising Wall at Main Entry (over exterior
entry canopy).
D. Systematically remove demolition debris from the work areas to avoid excessive
accumulation of debris on the floor. Load out will be via push-carts, dollies and
by hand (as necessary). Load all demolition debris into Sitek-supplied waste
dumpsters for transport to landfill for disposal as trash.
P.O. Box 361, Spring,Texas 77383-0361
Office Phone: 281-812-1461
.trek Omni
E. Leave all work areas in "broom-clean"clean condition, free of any loose debris.
City of Port Arthur responsible for:
A. Provide access to the work areas and parking for Sitek personnel and parking for
Sitek Omni-supplied truck and waste dumpsters.
B. Provide the services of an independent third-party Industrial Hygiene firm
(Honesty) for the purpose of providing final visual inspections.
C. Replacement of materials removed by Sitek during the selective demolition
work.
IT. PROCEDURES
Sitek Omni Services, LLC is a certified asbestos abatement (TDSHS License #80-
1070) and demolition contractor in Texas. All local, state and federal EPA and
OSHA codes regarding selective demolition shall be strictly implemented. Prior to
commencement of work, the owner and contractor are to mutually agree upon
project logistics, phasing and scheduling.
III. DISPOSAL
All asbestos containing materials will be handled, transported and disposed of as per
federal, state and local regulations to an EPA approved landfill. All demolition
debris generated will be removed from the site disposed of as trash at a licensed
landfill.
IV. SCHEDULING
Sitek proposes completion of the listed scopes of work within approximately eight
(8)working shifts, working Monday through Thursday up to 10 hours per shift(7am
—5pm).
V. PRICING
Lump sum price per listed additive demolition scope of work: S 20,800.00
The pricing provided is valid for 60 calendar days from the date of this proposal.
The pricing listed does not include any sales tax applicable to this scope of work.
VI. INSURANCE
Sitek carries occurrence-type General Liability coverage totaling $3 million per
occurrence and $3 million general aggregate with an additional $10 million
umbrella. Sitek also carries a $2 million Pollution Liability policy. Sitek's program
also includes Auto Liability, Employer's Liability and statutory limits for Worker's
Compensation. Liability and workers compensation policies are provided through
Starr Indemnity & Liability Company and Federal Insurance Company and are AM
Best Rated A+, XIV.
Page 2 of 3
Sitek#23-09-24
Ossmil
w..ar1111111h ur
We wish to thank you for your consideration and look forward to continuing work with
you on this added scope of work encountered during base scope work. Should this
proposal meet with your approval, please sign below, and return via email or fax as a
notice to proceed with the work.
Sincerely,
Jw
Jon K. Woodard
Vice President—Sales
cc: Dan@honestyenvironmental.com
Note: Please sign as authorization to proceed with the selective additive interior
demolition work and associated microbial cleaning listed in this proposal for the
former medical building located at 3617 Gates Boulevard in Port Arthur, Texas
and return via fax or email.
Name Date
Title
Page 3 of 3
Sitek#23-09-24