Loading...
HomeMy WebLinkAboutPR 23209: CITY MANAGER TO EXECUTE ON BEHALF OF PAT CHANGE ORDER NO. 1 FOR AAA ASPHALT PAVING, INC. City of Port Arthur Transit Department Memorandum To: Ronald Burton,City Manager From: Ivan Mitchell,Transit Director Date: September 28,2023 Re: P.R.23209—A resolution authorizing the City Manager to execute on behalf of PAT, change order No. 1 for AAA Asphalt Paving,Inc. Nature of Request: Authorize the City Manager to execute change order No.1 in the amount of $55,200.00 to AAA Asphalt Paving Inc. for Port Arthur Transit's(PAT)Dallas and Ft. Worth Avenue road reconstruction project. Background: Pursuant to Resolution No. 23-079, City Council awarded a contract to AAA Asphalt Paving, LLC. to reconstruct Dallas and Ft. Worth Avenues in the amount not to exceed $509,352.00. As construction ensued, design and material adjustments have occurred resulting in additional expenses and savings. Change order No. 1 is to address underground water utility lines that need to be removed and replaced. The replacement was realized once Dallas Avenue was excavated by AAA. This will result in a net contract increase of$55,200.00 for a new contract amount of$564,552.00. A detailed breakdown of change order No. 1 is provided in the packet. Recommendation: It is recommended that the City Council approve proposed P.R 23209. This resolution would authorize the City Manager to execute on behalf of PAT change order No. 1. Budgetary/Fiscal Effect: Funding to pay for this capital project is budgeted in PAT's capital budget. P.R. No. 23209 09/28/2023 IM RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 FOR THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND AAA ASPHALT PAVING, INC. INCREASING THE CONTRACT AMOUNT BY $55,200.00 TO A NEW CONTRACT AMOUNT OF $564,552.00, FOR PORT ARTHUR TRANSIT'S DALLAS AND FORT WORTH AVENUES ROAD RECONSTRUCTION PROJECT; FUNDS AVAILABLE IN ACCOUNT 401-70-530-8525-00-60-000, PROJECT DR1P06. WHEREAS, pursuant to Resolution No. 23-079, the City Council authorized the City Manager to enter into a contract with AAA Asphalt Paving, Inc. for the road reconstruction and drainage repairs of Dallas and Fort Worth Avenues in an amount not to exceed $509,352.00; and, WHEREAS, upon excavation AAA discovered it needs to remove and replace underground water utility lines on Dallas Avenue which is resulting in the contract increase of $55,200.00, as delineated in Exhibit"A"; and, WHEREAS, PAT is recommending that the City of Port Arthur by its City Manager approve Change Order No. 1 for a net project increase of $55,200.00 for a new contract amount not to exceed $564,552.00. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT,the facts and opinions in the preamble are true and correct. THAT, the City Manager is hereby authorized to execute on behalf of PAT, Change Orders No. 1 (Exhibit"A"). THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED this day of A.D. 2023 at a Regular Meeting of the City of Port Arthur, Texas by the following vote: AYES: Mayor: Councilmembers: P.R. No.23209 09/28/2023 IM NOES: . Thurman"Bill" Bartie, Mayor ATTEST: Sherri Bellard, City Secretary AP ROVED AS TO FORM: -7k- CP - ,e-X-'1.1 Oav c 19ilidei izeno, City Attorney APPROVED FOR ADMINISTRATION: APPROVED AS TO AVAILABILITY OF FUNDS: 401-70-530-8512-00-60-000 k CiLl\-1-\74') CW-Y--1) Ronald Burton Kandy Daniel City Manager Director of Finance el.,, , ,144,, Clifton Williams, CPPB Ivan Mitchell Purchasing Manger Transit Director P.R. No. 23209 09/28/2023 IM Exhibit "A" PORT ARTHUR TRANSIT DALLAS &FORT WORTH AVENUE ROAD REHABILITATION County: JEFFERSON Project: 1707 Change Order Number: 8 Rev.5 Date: 8/2/2023 Location: DALLAS AVENUE Statement of Equipment and Labor Equipment Labor Make/Model/Size Hours Rate Amount Name Hours Rate Amount Regular OT Regular OT 0.00 FOREMAN 0.00 0.00 LABORER 0.00 OPERATOR 0.00 SUBTOTAL 0.00 SUBTOTAL 0.00 LABOR MARKUP 25% 15%MARKUP 0.00 LABOR BURDEN MARKUP 55% EQUIPMENT TOTAL 0.00 TOTAL 0.00 Statement of Materials Description Rate Unit Quantity Amount Remove&dispose of existing 12"AC Pipe Dallas Ave(Subcontractor) $ 90.00 LF 120 $ 10,800.00 Install 16"HDPE DIPS Pipe W/Offsets,Reducers,Couplings,Gate Valve&Reducing Tee (AAA X SUB) Dallas Ave $ 370.00 LF 120 $ 44,400.00 SUBTOTAL $ 55,200.00 25%MARKUP TOTAL $ 55,200.00 Statement of Subcontracted Rates Description Rate Unit Quantity Amount SUBTOTAL 5%MARKUP TOTAL Total of Equipment,Labor, Materials,and Subcontracting $ 55,200.00