INTEROFFICE MEMORANDUM
Date: September 28, 2023
To: The Honorable Mayor and City Council
Through: Ronald Burton, City Manager
AP/ _
From: Flozelle C. Roberts,EIT, MEng, MBA, Public Works Director b
RE: P.R.23139—El Vista Pump Station Repairs Amendment No. 1 —Extending the
Time for Project Completion
Introduction:
This agenda item requests the City Council's approval of Amendment Number One(1)to extend
the completion date for the design of the El Vista drainage pump station improvements.
Background:
Resolution 23-228 authorized the execution of a contract with LJA Engineering of Beaumont,
Texas, for the El Vista drainage pump station improvements. LJA Engineering notified the
Public Works Department of its difficulty securing a geotechnical subconsultant to perform the
necessary work, which affects the approved schedule. LJA Engineering provided a letter
detailing the circumstances surrounding the delay. The firm proposes design completion by
January 19, 2024.
Budget Impact:
There is no budgetary impact for this amendment.
Recommendation:
It is recommended that the City of Port Arthur City Council approves Proposed Resolution
23139 extending LJA Engineering's design contract for the El Vista Drainage Pump Station
improvements.
"Remember,we are here to serve the Citizens of Port Arthur"
444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
PR No.23139
09/28/2023 FCR
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE AMENDMENT NO. 1 TO THE CONTRACT
BETWEEN THE CITY OF PORT ARTHUR AND LJA
ENGINEERING OF BEAUMONT, TEXAS,EXTENDING THE
EL VISTA DRAINAGE PUMP STATION PROJECT
DURATION BY 75 CALENDAR DAYS UNTIL JANUARY 19,
2024. THERE IS NO BUDGETARY IMPACT FOR THE
EXTENSION.
WHEREAS, Resolution 23-228 authorized the execution of a four-month contract with
LJA Engineering of Beaumont, Texas, to design various improvements at the El Vista Drainage
Pump Station, including the removal and replacement of the concrete lining in the pump station's
upstream forebay channel, the discharge pipe, and the flap gates on the downstream side of the
pump station to maintain the station's operational efficiency; and,
WHEREAS, LJA Engineering has submitted Amendment Number One (1), attached
hereto as Exhibit A, requesting the extension of the design completion date by 75 calendar days
until January 19, 2024; and,
WHEREAS,there is no increase in the project's cost.
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
approve Amendment Number One (1)to the contract with LJA Engineering of Beaumont, Texas,
increasing the duration of the project by 75 calendar days until January 19, 2024, in substantially
the same form as attached hereto as Exhibit A; and,
PR No.23139
09/28/2023 FCR
Page 2 of 3
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ,ADOPTED AND APPROVED this the day of ,A.D.
2023, at a meeting of the City of Port Arthur, Texas,by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Thurman Bill Bartie
Mayor
ATTEST:
Sherri Bellard,TRMC
City Secretary
APPROVED AS TO FORM:
(1,(ird A'L- d2)
)1Val?Lte-47ia R. Teno 9
Es .
City Attorney
PR No.23139
09/28/2023 FCR
Page 3 of 3
APPROVED FOR ADMINISTRATION:
Ronald Burton, CPM Flozelle oberts,E , Eng, MBA, CPM
City Manager Director f ublic W r
APPROVED AS FOR AVAILABILITY OF FUNDS:
kKov. cx 6614
Kandy Daniel y Clifton E. Williams,Jr.,CPPB
Director of Finance Purchasing Manager
PR No.23139
EXHIBIT A
114
2615 Calder Avenue,Suite 500.Beaumont,Texas 77702
LJA ENGINEERING t 409.833.3363 f 4098330317 LJAcom TBPE F-1386 TBPLS 10105600
September 28, 2023
Mrs. Flozelle G. Roberts, EIT, Meng, MBA
Director of Public Works
City of Port Arthur
444 4th Street
Port Arthur,Texas 77640
Re: El Vista Pump Station Improvements
Dear Mrs. Roberts,
UA entered into an agreement with the City of Port Arthur on July 7, 2023 for the El Vista Pump Station
Improvements. In our proposal, we estimated that the project would take approximately 4 months to
complete the final plans. We immediately began working on the project by developing the scope for
surveying field services. The surveying field services were scheduled for and completed on August 9,2023.
Additionally,we contacted a firm, Braun Intertec(Braun), in early August to provide geotechnical borings
and soils analysis. Unfortunately, it took much longer than anticipated to receive the geotechnical
proposal and ultimately to sign a work authorization with Braun. The issues were at the admin. and legal
counsel levels in regard to existing Master Sub-Consultant Agreements between UA and Braun. Once the
issues were resolved,the executed sub-consultant work authorization was returned to UA on Wednesday,
September 27,2023. However,the transmittal email stated that with Braun's current backlog,the earliest
availability for drilling will be October 23.
With the borings field exploration being estimated to be delayed until late October,the laboratory testing
will be completed within two weeks after the field exploration,and a final report will be issued from Braun
two weeks after the lab testing(per Braun's proposal). We have begun working on the analysis and design
of the proposed improvements to the forebay. However,our design may need to be revised based on the
conclusions from the final geotechnical report.
Due to the delays in getting the work authorization signed and the projected drilling date, UA is asking for
the schedule to be amended. We now anticipate that we will be finished with final design for submittal
to the City for review by January 19, 2024.
Please let me know if you have any questions or need additional information.