HomeMy WebLinkAbout(P2) S2G_Port-Arthur_CityCouncilPresentation (16-9 widescreen)_Sullivan_v2.1-9Oct2023-330dpi, bnp (2)S2G Program –October 2023
Garrett Sullivan, Project Manager
Port Arthur Project –Media Roundtable
bit.ly/PortArthurProject
(case sensitive)
•Construction of a region-wide risk reduction system,
along with ecosystem restoration, will improve our
ability to respond to future storms and address long-
term impacts of sea level rise & land subsidence.
•The Port Arthur Project is a component of the Sabine
Pass to Galveston Bay Program (S2G) which includes
project areas in the cities of Port Arthur (Jefferson),
Freeport (Brazoria), and Orange (Orange).
•The objectives of the overall S2G Program include:
•Reducing risks to human life from storm surge;
•Reducing economic damages to residents,
businesses, and infrastructure;
•Enhancing energy security by reducing storm
surge risk to petrochemical facilities; and
•Reducing adverse physical impacts to waterways
used for commercial and recreational activities.
Texas Coast Regional Approach
Port Arthur Project Executive Overview
The Port Arthur Project, one of three S2G projects, is located in
Southeast Texas, approximately 12 miles from the Gulf of Mexico, on
the west side of Sabine Lake. The Project will make improvements to
an existing Hurricane Flood Protection Project (HFPP) system based
on the 1% Annual Exceedance Probability (AEP) Storm Event
combined with 2070 Relative Seal Level Rise conditions.
The improved Coastal Storm Risk Management (CSRM) system will
increase the level of performance and resiliency of the HFPP.
Authority: Section 1401 (3)3, Water Resources Development Act of
2018 (P.L. 115-270)
Project Sponsor: Jefferson Co. Drainage District #7 (DD7)
Port Arthur Project Overview
Port Arthur Project (1% AEP and 2070 Relative Sea Level Rise)
Construct 21 new road/railway closure structures
Install erosion protection (stone-armoring) at multiple locations
Construct concrete fronting protection at 11 existing pumping stations
along the CSRM levee system
Port Arthur Project (1% AEP and 2070 Relative Sea Level Rise)
Raise approximately 10.95 miles of existing earthen levees
(ranging from 14.5 ft to 20.5 ft) NAVD88 in elevation
Construct or reconstruct approximately 5 miles of new concrete
floodwalls (ranging from 17.5 ft to 24.5 ft) NAVD88 in elevation
Construct approximately 4.1 miles of new earthen levee at multiple
locations (ranging in height from 1 to 14 ft)
Project Funding
o USACE is partnering with Jefferson
County Drainage District # 7, the
Non-Federal Sponsor, to design and
construct the Port Arthur Project.
o Civil works projects like this are
cost-shared between the Federal
Government and the Non-Federal
sponsor. The Federal Government
is responsible for 65% of the cost
and the Non-Federal sponsor is
responsible for 35% of the cost.
o Total Project funding equals $863M
35%65%
USACEDD7
Project Features
o Construct or reconstruct 5 Miles of New Concrete
Floodwall (Ranging from 17.5 ft to 24.5 ft in height)
o Replace existing I-Walls with T-Walls
o Provide Levee Erosion Protection (Stone Armoring)
Raise Earthen Levees
o Raise approximately 10.95 Miles of existing earthen
levee (Ranging from 14.5 ft to 20.5 ft in height)
o Provide Levee Erosion Protection (Stone Armoring)
I-Wall T-Wall
Project Features
Twenty-One road & railroad closure structures will be
constructed or replaced on public and private
roadways. There are three types of gates:
o Overhead Trolly Gates
o Roller Gates
o Swing Gates
Project Features
CONCEPTUAL ILLUSTRATION:
PUMP STATION FRONTING PROTECTION
Construct concrete fronting protection at 11 existing
pumping stations along the CSRM levee system
Project Schedule/Timeline
Feasibility Study
Complete
Study authorized
and funded by
Congress
First Construction
Contract Awarded
Construction Begins
Final Design Complete
Project Complete
2031 20312027
PAV03A Project Overview: Design-Bid-Build Contract
Major Project Elements -PAV03A Contract
•Fronting Protection for 3 Pump Stations
(Alligator, Lakeside, and Rodair) ≈ 1,000 ft
•Earthen Levee Raise ≈ 370 ft (Various Areas)
•Concrete Floodwall Replacement ≈ 950 ft
•Sheet Pile Cut-Off Wall Installation
•Levee System Stone Armoring Protection
•Levee All-Weather Surface Road Replace
•Gate Well Structure and Culvert Replacement
Alligator Pump Station Improvements
Lakeside Pump Station Improvements
Replace Gate Well Structure and Culvert
Rodair Pump Station Improvements
PAV03A Contract
PAV03A Project Overview: Design-Bid-Build Contract
o The PAV03A Contract was awarded to Flatiron Constructors on Sep. 8, 2023
o The Contract Award value equals $102.5 Million
o USACE is planning a Pre-Construction Conference during period Nov. 6-10, 2023
o Site Mobilization and Construction Start expected to occur during the early 2024
timeframe (exact date TBD)
o Project duration is 4.5 years ending in June 2028
PAV04 Project Overview: Design-Build Contract
Port Arthur
Rose Hill Park
PAV04 Contract
Major Project Elements -PAV04 Contract
•Earthen Levee Raise ≈ 2,252 ft
•Fronting Protection for 3 Pump Stations
(Lakeview, Stadium Road, & Del-Mar)
≈ 468 ft including Pump Outfall Pipe Ext
•New Concrete Floodwall ≈ 9,496 ft
•Modifications to 9 Gravity Drain Systems
•Levee System Stone Armoring Protection
Stadium Rd Pump
Del-Mar Pump
Fronting Protection
Pump Station Fronting Protection
Lakeview Pump
Concrete Floodwall
PAV04 Project Overview: Design-Build Contract
o Contract Award is scheduled for early August 2024
o Construction Start is planned for Spring timeframe of 2025
o Construction Completion is planned for late Fall timeframe of 2028
S2G Website & Story Map
https://www.swg.usace.army.mil/S2G https://sabine-to-galveston-usace-swg.hub.arcgis.com
Main S2G Website Main S2G Story Map
Port Arthur Project –Media Roundtable
bit.ly/PortArthurProject
(case sensitive)