HomeMy WebLinkAboutPR 23396: DALLAS AVENUE AND FORT WORTH AVENUE SUPPLEMENT FEE REQUEST City of Port Arthur
Transit Department
Memorandum
To: Ron Burton,City Manager
From: Ivan Mitchell,Transit Director it\.k.
Date: October 12,2023
Re: P.R.23396—Dallas Avenue and Fort Worth Avenue Supplement Fee Request
Nature of Request:Authorize the City Manager to extend the contract with the Solco Group,LLC
(TSG)for engineering and design services for Port Arthur Transit's(PAT)parking lot expansion
located at 320 Dallas Avenue,and for reconstruction and drainage repairs on Dallas and Fort Worth
Avenues and pay supplemental cost.
Background:Resolution No. 21-249 authorized the City Manager to negotiate a contract with the
Solco Group,LLC.,for engineering and design services for Port Arthur Transit's(PAT)parking lot
expansion with overhead canopies. The Texas Department of Transportation(TxDOT)awarded PAT
funds to construct a 13,000 square foot parking lot to accommodate its growing fleet of transit
vehicles. In addition,PAT will construct several overhead canopies to protect the vehicles from the
elements as well as install conduit for future electric vehicle charging. Resolution No.21-287
authorized the City Manager to execute a contract with TSG,for engineering and design services for
Port Arthur Transit's(PAT)parking lot expansion with overhead canopies in the amount not to
exceed$131,284.00.
PAT was awarded Federal Transit Administration funds in the amount of$904,750.00($723,800
federal/$180,950 local)under the Section 5324 Emergency Relief Program in December 2018. PAT
selected TSG to provide engineering and design services for reconstruction and drainage repairs on
Dallas and Fort Worth Avenues which are adjacent to its facilities. Resolution No.21-384 authorized
a contract amendment which increased the contract amount by$59,951.00 to a new contract total in
the amount not to exceed$191,235.00.
Resolution No. 22-265 authorized the City Manager to approve an additional cost of$6,120.00 to the
contract for the reconstruction of driveway portions between San Antonio and Dallas Avenues which
increased the contract total cost to$197,355.00.
The reconstruction and drainage repairs on Dallas Avenue and Fort Worth Avenue are underway.
TSG has requested additional compensation in the amount of$15,500.00 to cover engineering design
and construction administration costs incurred during the performance of the project that were not in
the original scope.The new contract total is in the amount not to exceed$212,905.00.
Pr
One out of three projects in TSG's existing scope of work is complete therefore PAT is requesting to
extend the contract through November 30,2024,to ensure completion of all.
Recommendation:It is recommended that the City Council approve proposed P.R. 23396 to extend
the TSG's contract through November 30,2024,and increase the contract by an additional
$15,500.00,to a new contract total in the amount not to exceed$212,905.00.
Budgetary/Fiscal Effect:Funding to pay for the design and engineering services is available in
Transit Capital Account 401-70-530-8512-00-60-000 PROJECT#TR11430.
P.R. No. 23396
10/12/2023 IM
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A THIRD
AMENDMENT TO THE CONTRACT WITH THE SOLCO GROUP, LLC OF
BEAUMONT, TEXAS FOR ENGINEERING AND DESIGN SERVICES FOR PORT
ARTHUR TRANSIT'S (PAT) PARKING LOT EXPANSION AT 320 DALLAS AVENUE
AND FOR RECONSTRUCTION AND DRAINAGE REPAIRS ON DALLAS AND FORT
WORTH AVENUES IN THE AMOUNT OF $15,500.00 TO A NEW CONTRACT TOTAL
OF $212,905.00 AND EXTENDING THE CONTRACT THROUGH NOVEMBER 30,
2024; FUNDING IS AVAILABLE IN ACCOUNT NO. 401-70-530-8512-00-60-000,
PROJECT # TR11430
WHEREAS, pursuant to Resolution No. 21-249, the City Manager was authorized to negotiate a
contract with the Solco Group, LLC; and,
WHEREAS, pursuant Resolution No. 21-287, the City Council approved a contract with the
Solco Group, LLC., for engineering and design services for Port Arthur Transit's (PAT) parking lot
expansion with overhead canopies in the amount not to exceed $131,284.00; and,
WHEREAS, pursuant Resolution No. 21-384, the City Council authorized a contract amendment
which increased the contract amount by $59,951.00 to a new contract total of in the amount of
$191,235.00; and,
WHEREAS, pursuant Resolution No. 22-265, the City Council authorized a contract amendment
which increased the contract amount by $6,120.00 to a new contract total of in the amount of$191,235.00
and extended the contract until September 13, 2024; and,
WHEREAS, the City Manager and PAT recommend the third amendment to the contract in the
amount of$15,500.00 to a new total of$212,905.00, and extending the contract through November 31,
2024, a copy of the supplemental fees and the amended scope is attached hereto as Exhibit"A".
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PORT ARTHUR:
THAT,the facts, and opinions in the preamble are true and correct.
THAT, the City Manager is hereby authorized to execute the third amended contract with the
Solco Group, LLC of Beaumont, Texas to continue engineering and design services for PAT's parking lot
expansion with overhead canopies and for reconstruction and drainage repairs on Dallas and Fort Worth
Avenues in the amount of $15,500.00, to a new total of $212,905.00, and extend the contract through
November 30, 2024, in substantially the same for as attached hereto as Exhibit"A".
THAT, a copy of the caption of this Resolution be spread upon the minutes of the City
Council.
READ,ADOPTED AND APPROVED this day of October 2023 at a Regular meeting of
the City of Port Arthur, Texas by the following vote: AYES:
Mayor:
Councilmembers:
P.R. No. 23396
•
10/12/2023 IM
NOES: .
Thurman "Bill" Bartie, Mayor
ATTEST:
Sherri Bellard, City Secretary
APP OVED AS TO FORM:
U&AP e'Yt- • ' I , I/ -U
al Tizeno, City Attorney
APPROVED FOR ADMINISTRATION: APPROVED AS TO AVAILABILITY
OF FUNDS:
401-70-530-8512-00-60-000
PROJECT #: TR11430
:k0,-- ___ d 0 UL1l..A---70
Ronald Burton Kandy Daniel
City Manager Director of Finance NClifto Williams, CPPB Ivan itchell
Purchasing Manger Transit Director
• P.R. No. 23396
10/12/2023 IM
Exhibit "A"
•
IFSS
THE SOLCO GROUP, LLC
TRANSPORTATION PPLANNING/ENGINEERING/RESEARCH/ADVICE/CONSULTING
October 10, 2023
Mr. Ivan Mitchell
Transit Manager
Port Arthur Transit
344 Procter Street
Port Arthur, TX 77640-6450
Subject: Rehabilitation and Drainage Repairs of Dallas Avenue and Fort Worth Avenue in Downtown
Port Arthur, Texas - Street Intersection Drainage Status Update -TSG Project No. 2021- 08-1087A—
Out of Scope-Supplemental Fee Request
Dear Mr. Mitchell(Ivan):
The reconstruction and drainage repairs on the block surrounding the Port Arthur Transit Terminal Building
(Dallas Avenue and Fort Worth Avenue)are underway.The Solco Group(TSG) is requesting consideration for
a supplemental agreement to cover additional engineering design and construction administration costs
incurred during the performance of the project. The supplemental request includes completed and upcoming
out of scope work.
The original scope of the Dallas Avenue and Fort Worth Avenue Rehabilitation and Repairs Project included
pavement rehabilitation(asphalt milling and overlay),curb and gutter repairs,sidewalk rehabilitation,and minor
drainage improvements.
During construction the following items were identified requiring supplemental work including unanticipated
meetings and plan revisions due to differing site conditions and conflicts.
1. Conflict of proposed duct-bank conduits for Entergy, AT&T and Spectrum with the angled existing 12"
Asbestos Cement Waterline. TSG prepared supplemental plans addressing the conflict and
replacement of the asbestos waterline with HDPE.
2. Prepared supplemental plan for the addition of waterline replacement across Ft Worth Avenue
3. Prepared supplemental plan of electrical duct-bank conduits across Ft Worth Avenue
4. Prepared supplemental plan to raise the sidewalk and ADA ramp on the southwest corner of Dallas
Avenue and Procter Street.
5. Additional Coordination and Meetings with City on Waterline/Conduit/Drainage
6. Additional Construction Administration. Original construction completion date - July 16th. Revised
construction completion date due to change orders—August 23rd.
A man-hours tabulation of the out-of-scope hours is shown in attachment'A' for$15,500.00. Therefore, TSG
is requesting a Supplemental Agreement in the amount of$15,500.00 as calculated in Attachment A,enclosed.
THE SOLCO GROUP,LLC549 4th Street,Suite 209A, Port Arthur, TX 77640
WWW.TheSolcoGroup.com
TSB
THE SOLCO GROUP, LLC
TRANSPORTATION PPLANNING/ENGINEERING/RESEARCH/ADVICE/CONSULTING
Sincerely,
.A4i,eficz7)
Kelvin L. Solco, P.E., MBA
The Solco Group, LLC 409-
237-0200 -office
817-564-6895—cell
Enclosures: TSG man-hours tabulation—Out of Scope Work
cc: Simon Karingithi P.E., Project Manager, The Solco Group, LLC
THE SOLCO GROUP,LLC 549 4th Street,Suite 209A,Port Arthur, TX 77640
WWW.TheSolcoGroup.com
148'
THE SOLCO GROUP, LLC
TRANSPORTATION PPLANNING/ENGINEERING/RESEARCH/ADVICE/CONSULTING
PA Transit
Road and Drainage Project
TSG man-hours tabulation
Out of Scope Work Principal I Professional Project Technical 1 Total
TSG#2021-08-1087A Project MGR Engineer Manager Clerical Hours
Supplemental plans addressing the
conflict and replacement of the
asbestos waterline with HDPE. 6 8 6 0 20
Supplemental plan for the addition of
waterline replacement across Ft
Worth Avenue 6 8 6 0 20
Supplemental plan of electrical duct-
bank conduits across Ft Worth
Avenue 6 8 6 0 20
Supplemental plan to raise the
sidewalk and ADA ramp on the
southwest corner of Dallas Avenue
and Procter Street. 8 8 5 0 21
Additional Coordination and Meetings
with City on Waterline / Conduit /
Drainage 8 8 5 1 22
Revised construction completion date
due to change orders—August 23ro. 10 4 5 1 20
QA/QC+Admin support(Proof and
invoicing) 10 0 0 4 14
Sub Total hours 54 44 33 6 137
Direct salary costs $8,100.00 $4,180.00 $2,970.00 $300.00 $15,550.00
THE SOLCO GROUP,LLC549 4nI Street,Suite 209A,Port Arthur, TX 77640
WWW.TheSol coGroup.com