HomeMy WebLinkAbout(P 3) Sigma Presentation - PA Health Department 10.24.23 - Progress REV2CITY OF PORT ARTHUR
HEALTH DEPARTMENT
CONSTRUCTION PROGRESS
October 24, 2023
CITY OF PORT ARTHUR HEALTH DEPARTMENTExterior View - Before
CITY OF PORT ARTHUR HEALTH DEPARTMENTExterior View - Before
4
KEY PLAN
EXTERIOR BUILDING DESIGN
EXTERIOR SIGNAGE DIRECTORY
CITY OF PORT ARTHUR HEALTH DEPARTMENT
Exterior View – Current Construction
CITY OF PORT ARTHUR HEALTH DEPARTMENT
Exterior View – Current Construction
CITY OF PORT ARTHUR HEALTH DEPARTMENT
Interior View – Current Construction
CITY OF PORT ARTHUR HEALTH DEPARTMENT
Interior View – Current Construction
CITY OF PORT ARTHUR HEALTH DEPARTMENT
Interior View – Current Construction
CITY OF PORT ARTHUR HEALTH DEPARTMENT
Interior View – Current Construction
CITY OF PORT ARTHUR HEALTH DEPARTMENT
Interior View – Current Construction
CITY OF PORT ARTHUR HEALTH DEPARTMENT
Interior View – Current Construction
PROJECT
SCHEDULE
ID Task Mode Task Name Duration Start Finish %Comple Resource Names
1 Building
2 Mobilization / MEP Cut & Cap
286 days Wed 10/26/22 Wed 11/29/23 93%
2 days Wed 10/26/22 Thu 10/27/22 100%
3 Interior Mass Demolition 20 days Fri 10/28/22 Thu 11/24/22 100%
4 Partition Layout 10 days 100%
5 Sawcut & Underslab Plumbing R/I 25 days 100%
6 RTU Framed Openings & In-Fills 15 days 100%
7 Form & Pour Plumbing Trenches 10 days 100%
8 Frame Interior Partitions 30 days 100%
9 Set Door Frames 15 days 100%
10 Install Folding Partition Supports 5 days 100%
11 MEP Overhead & In-Wall Rough-In 65 days 100%
12 Plywood at Mansard Walls 10 days 100%
13 Set RTU Curbs 10 days 100%
14 Roofing 25 days 100%
15 Insulate / Drywall Partitions 157 days 100%
16 Tape, Float, Texture & Paint 40 days
Fri 11/25/22 Thu 12/8/22
Fri 12/9/22 Thu 1/12/23
Fri 1/13/23 Thu 2/2/23
Fri 1/13/23 Thu 1/26/23
Fri 1/27/23 Thu 3/9/23
Fri 3/10/23 Thu 3/30/23
Fri 3/10/23 Thu 3/16/23
Fri 12/9/22 Thu 3/9/23
Fri 2/3/23 Thu 2/16/23
Fri 2/3/23 Thu 2/16/23
Fri 2/17/23 Thu 3/23/23
Fri 3/24/23 Mon 10/30/23
Mon 6/19/23 Fri 8/11/23 100%
17 Mon 7/10/23 Fri 8/18/23 100%
18 Mon 8/21/23 Fri 9/29/23 100%
19 Mon 10/16/23 Fri 11/10/23 63%
20 Mon 8/28/23 Fri 9/22/23 90%
21 Mon 10/2/23 Fri 10/20/23 90%
22 Mon 8/21/23 Fri 9/1/23 100%
23 Mon 9/4/23 Fri 10/6/23 100%
24 Thu 11/16/23 Wed 11/29/23 0%
25 Thu 11/23/23 Wed 11/29/23 100%
26 Thu 11/23/23 Wed 11/29/23 100%
27 Thu 11/23/23 Wed 11/29/23 80%
28 Wed 11/1/23 Tue 11/28/23 0%
29
Ceiling Grid 30 days
Light Fixture, Grilles, Fire Alarm Trim 30 days
Porcelain Tile at Restrooms 20 days
Cabinets 20 days
Specialties / Wall Protections / Signage 15 days
Commission MEP Systems 10 days
Ceiling Tile 25 days
Flooring 10 days
Folding Partition at Conference Room 5 days
Doors & Hardware 5 days
Finish Paint Walls 5 days
Clean & Punch 20 days
Substantial Completion 1 day Wed 11/29/23 Wed 11/29/23 0%
30
31 Fri 12/16/22 Wed 11/22/23 58%
32 Fri 12/16/22 Tue 12/27/22 100%
33 Wed 12/28/22 Tue 1/17/23 100%
34 Wed 2/1/23 Tue 3/14/23 100%
35 Wed 3/15/23 Tue 4/4/23 100%
36
Site & Exterior 244 days
Layout & Sawcut Paving and Foundatio 8 days
Demo Paving and Foundations 15 days
FRP Paving and Foundations 30 days
Erect Entry Canopy Steel 15 days
Framing and Roofing at Entry Canopies 20 days Wed 4/5/23 Tue 5/2/23 100%
37 Paint Exposed Steel at Entry Canopies 10 days 100%
38 Curtainwall System at Entry Canopies 120 days 20%
39
Wed 5/3/23 Tue 5/16/23
Thu 6/8/23 Wed 11/22/23
Wed 7/12/23 Tue 7/25/23 100%
40 Wed 7/12/23 Tue 8/8/23 100%
41 Wed 8/9/23 Tue 8/29/23 75%
42 Wed 8/9/23 Tue 8/15/23 100%
43 Tue 9/19/23 Mon 10/2/23 0%
44 Mon 10/30/23 Fri 11/3/23 0%
45
Masonry Point Up and Clean Exterior W 10 days
Masterline Wall Panels at Mansard 20 days
Building Signage and Directories 15 days
Dumpster Fencing 5 days
Landscaping (Allowance) 10 days
Power Wash Parking Lot/Sidewalks 5 days
Parking Striping/Wheelstops/Signage 5 days Mon 11/6/23 Fri 11/10/23 0%
Building
100%
100%
100%
100%
100%
Form & Pour Plumbing Trenches
Frame Interior Partitions
Set Door Frames
Install Folding Partition Supports
MEP Overhead & In-Wall Rough-In
Plywood at Mansard Walls
100%
100%
100%
100%
100%
100%
63%
90%
Specialties / Wall Protections / Signage
100%
100%
Flooring
Folding Partition at Conference Room
100%
80%
Clean & Punch
Substantial Completion
Site & Exterior
Layout & Sawcut Paving and Foundations
Demo Paving and Foundations
FRP Paving and Foundations
Erect Entry Canopy Steel
Framing and Roofing at Entry Canopies
Paint Exposed Steel at Entry Canopies
20%
Masonry Point Up and Clean Exterior Walls
Masterline Wall Panels at Mansard
Building Signage and Directories
Dumpster Fencing
0%
0%
Parking Striping/Wheelstops/Signage
16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 3 10 17 24 31 7 14 2Nov '22 Dec '22 Jan '23 Feb '23 Mar '23 Apr '23 May '23 Jun '23 Jul '23 Aug '23 Sep '23 Oct '23 Nov '23 Dec '23 Jan '24 Feb '24 Mar '24 Apr '24
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
PA Health Department (Updated 10-23-23)