INTEROFFICE MEMORANDUM
Date: October 27, 2023
To: The Honorable Mayor and City Council
Through: Ron Burton, City Manager
From: Flozelle C. Roberts, EIT, MEng, MBA, CPM; Director of Public Works
RE: PR23376: Sabine Pass Boat Ramp: Change Order No. 2—Modification to Fish
Cleaning Station; add rubber bumpers;remove Alternates 1 and 2. Project No. PR0007-
CON.
Introduction:
The intent of this Agenda Item is to authorize the City Manager to approve Change Order No. 2 with
Elite Contractors & Equipment, LTD of Kirbyville, Texas for the modification of the Fish Cleaning
Station, installation of additional rubber bumpers, removal of concrete curb and gutter, and removal of
Alternates 1 and 2 for the Sabine Pass Boat Ramp Project for a deduction of$65,058.00.
Background:
Pursuant to Resolution 22-450,the City of Port Arthur entered into an agreement with Elite Contractors
& Equipment, LTD, of Kirbyville, Texas, for the construction of the Sabine Pass Boat Ramp and Area
Improvements Project for$2,132,929.00.
Pursuant to Resolution 23-423, approved by Council, Elite Contractors & Equipment, LTD, of
Kirbyville, Texas, submitted Change Order No. 1 for the installation of a monument slab, electrical
conduit for the artificial reef marker at the boat ramp,and installation of coal tar epoxy at the submerged
portion of the boat ramp.
Elite Contractors & Equipment, LTD, of Kirbyville, Texas, has submitted Change Order No. 2 for the
modification of the Fish Cleaning Station,installation of additional rubber bumpers,removal of concrete
curb and gutters, and removal of Alternates 1 and 2 for the Sabine Pass Boat Ramp Project for a
deduction from the contract amount of$65,058.00.
Budget Impact:
Funding for this is available in the Capital Improvements Project Account PR0007-CON; 152-60-415-
8525-00-00-000; and, American Rescue Plan Act (ARPA) Account 169-07-015-8525-00-40-000;
Project No. ARP013. Change Order No. 2 represents a deduction from the original contact amount.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
S:\Engineering\PUBLIC WORKS\PW-ENGINEERING\C.I.P.PROJECTS\Year 2022\Sabine Pass Boat Ramp\Change Orders\Change Order 2\Agenda Memo Sabine Pass CO 2.docx
PPP
Recommendation:
It is recommended that the City of Port Arthur City Council approve PR23376 that authorizes the City
Manager to approve Change Order No. 2 with Elite Contractors & Equipment, LTD, of Kirbyville,
Texas, modification of the Fish Cleaning Station,installation of additional rubber bumpers,removal of
concrete curb and gutter, and removal of Alternates 1 and 2 for the Sabine Pass Boat Ramp Project for
a deduction to the contract amount of$65,058.00.
•
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
PR 23376
10/27/2023 mje
Page 1 of 4
Updated
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 2 TO THE CONTRACT BETWEEN THE CITY OF PORT
ARTHUR AND ELITE CONTRACTORS & EQUIPMENT, LTD, OF
KIRBYVILLE, TEXAS, TO MODIFY THE FISH CLEANING STATION, ADD
RUBBER BUMPERS AND REMOVE ALTERNATES 1 AND 2 AT THE SABINE
PASS BOAT RAMP IMPROVEMENT PROJECT IN SABINE PASS, TEXAS
FOR A DEDUCTION IN THE AMOUNT OF $65,058.00. FUNDING IS
AVAILABLE IN CAPITAL IMPROVEMENTS PROJECT ACCOUNT 152-60-
415-8525-00-00-000; PROJECT NO PR0007-CON; AND AMERICAN
RESCUE PLAN ACT (ARPA) ACCOUNT 169-07-015-8525-00-40-000,
PROJECT NO. ARP013.
WHEREAS, the Texas Parks & Wildlife Department (TPWD) has dedicated
$1,000,000.00 by way of a grant, from the Harvey Fisheries Disaster Relief Grant Program for
the reconstruction of the Sabine Pass Boat Ramp; and,
WHEREAS, pursuant to Resolution No. 20-425, City Council agreed to participate and
accept the grant funding of $1,000,000.00 for the reconstruction of the Sabine Pass Boat
Ramp to be deposited into the CIP Account 152-60-415-8525-00-00-000; and,
WHEREAS, pursuant to Resolution 22-450, the Port Arthur City Council authorized the
City Manager to enter into an agreement with Elite Contractors & Equipment, LTD, of
Kirbyville, Texas, for the reconstruction of the Sabine Pass Boat Ramp for the $2,132,929.00,
and a time of completion of 270 calendar days; and,
WHEREAS, pursuant to Resolution 23-423, approved Change Order No. 1 submitted by
Elite Contractors & Equipment, LTD, of Kirbyville, Texas, for the installation of a monument
slab and electrical conduit for the artificial reef marker at the boat ramp and the application of
coal tar epoxy at the mudline as a protective coating for the submerged portion of the boat
PR 23376
10/27/2023 mje
Page 2 of 3
Updated
ramp for the amount to $74,723.00 changing the original contract amount of $2,132,929.00 to
the new contract amount of $2,207,652.00; and,
WHEREAS, Elite Contractors & Equipment, LTD, of Kirbyville, Texas, has submitted
Change Order No. 2 for the modification of the Fish Cleaning Station, the addition of rubber
bumpers, the removal of concrete curbs and gutters, and the removal of Alternates 1 and 2 for
a deduction to the contract of $65,058.00; See Exhibit A; and,
WHEREAS, Change Order No. 2 reduces the contract amount of $2,207,652.00 by
$65,058.00 to the new contract amount of $2,142,594.00; and,
WHEREAS, approval of PR23376 for Change Order No. 2 is herein deemed an
appropriate action; now therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, Change Order No. 2 is herein approved and the City Manager is authorized to
execute the change in the contract between the City of Port Arthur and Elite Contractors &
Equipment, LTD, of Kirbyville, Texas, for a deduction in the amount of $65,058.00; and,
THAT, Change Order No. 2 reduces the contract amount of $2,207,652.00 by
$65,058.00 to the new contract amount of $2,142,594.00; and,
THAT, a copy of the Resolution shall be spread upon the Minutes of the City Council.
READ, ADOPTED AND APPROVED this the day of , A.D.,
2023, at a of the City Council of the City of Port Arthur, Texas, by the
following vote: Ayes: Mayor:
PR 23376
10/27/2023 mje
Page 3 of 3
Updated
Councilmembers:
Noes:
Thurman Bill Bartle
Mayor
ATTEST:
Sherri Bellard
City Secretary
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION
4-7(
Val Tizeno, Esquire Ron Burton
City Attorney City Manager
APPROVED AS TO AVALIABILITY OF FUNDS:
Kandy Daniel
Finance Director
Flozelle C. Roberts, EIT, MEng, MBA, CPM
Director or Public Works
f fic
k.
Clifton Williams, CPPB
Purchasing Manager
EXHIBIT A
CITY OF PORT ARTHUR
Public Works Engineering
DATE: OCTOBER 27,2021 Updated
PROJECT: SAHINE PASS BOAT RAMP
OWNER: CITY OP PORT ARTHUR
CONTRACTOR: ELITE CONTRACTORS&EQUIPMENT,LTD
CHANGE ORDER NOs 2
THE FOLLOWING CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE HEREBY MADE:
Adjust the Estimated Quantities to reflect the Actual Quantities used in the completion of the project:
Item Item Description Unit Original Unit Prke Orlglnai Amount Total Quantity New Amount
No. Code quantity
r, Reinforce Concrete Curb and Gutter(Deietel IF 110 S 78 00 5 10.14n cO _ ��-110.1 i
' Per TPWO additional Rubger Bumpers and modify Fish Cleaning Station L5 _ _ _0 S 14.89/00 I 5 15.892 00
AI: 01A Rework:rot existing asphalt base.comoact in place IDeletel —IV J30 5 4900 S 15,J711 00 730 S (35JI0 nUf
air 02A 2"RAMC Type D over existimt stabilized material(Delete) SY 11n S 4800 1 S 35.nin 0U 730 5 (3S 040001
TOTAL CHANGE ORDER $ (65.050.00;i
ORIGINALCONTRACiAMOUNT I$ 2,132,929,00 NEW CONTRACT $ 24067r871
AMOUNT .00
ORIGINAL CONTRACT AMOUNT:IS 2,132.929 00 I
TOTAL AMOUNT OF CHANGE ORDER NO.1: $ 74,72 3.00
TOTAL AMOUNT OF CHANGE ORDER NO.2: . 165.05N 00)
TOTAL PERCENT OF CHANGE ORDER NO.1&2: 0.4Sst
NEW CONTRACT AMOUNT: S 2.142.59400
CONTRACT COMPLETION DATE: December 31,2023
NO CALENDAR DAYS HAVE BEEN ADDED TO CHANGE ORDER NO.1
PAREPARED AND VERIFIED BY: REVIEWED BY:
_ 4
n e Dotson,PE.Mt*ti Shipman,Inc, M.le lerEdwar , S,MPA;CIP Manager
APPROVED BY: APPROVED BY: ,--..—...-
Ce C ,� 10/30/23
Cody Ellis ,ject M imager,Elite Contractors A Equipment,LTD lohn Cam:stein:,PE,Oty Engineer
/a/ 30 /.? 3
APPROVED BY: APPROVED BY:
Flotelle C.Roberts,EIT,MEng,MBA,CPM,Director of Publk Works Clifton Williams,CPPB,Purchasing Manager
APPROVED BY:
Ron Burton,City Manager
C:\Users\JCannatella_ch\Documents\BCItyPtA\NParks Pro)ects\SabinePass Boat Ramp\Construction\Change Order\SP Boat Ramp CO2 Rev2