HomeMy WebLinkAboutPR 23476: CHANGE ORDER NO. 1, MARSH WATERPROOFING OF VIDOR, TEXAS, PHASE III REPAIRS TO POMPEIIAN VILLA Memorandum
City of Port Arthur, Texas
Robert A. "Bob"Bowers Civic Center
To: The Honorable Mayor and City Council
Through: Ron Burton, City Manager
From: Adam J Saunders, Civic Center Dir
RE: Proposed Resolution No. 23476
On August 1, 2023, the City Council approved Resolution No. 23-317 for Phase III repairs to
Pompeiian Villa. When the Porte Cochere was removed it was determined additional work was
needed on the roof area in order to properly receive the new structural support for the Porte
Cochere. Included in this was the need to remove and replace a large section of the roof,
including shingles and lathing, plywood and rakes, ridges, starters and all accessories required.
This work will be Change Order No. 1.
The cost of Change Order No. 1 is $11,900.00. The original cost for this work was $230,000.00.
With the addition of this change order, the total amount of this work is increased to $241,900.00.
Marsh Waterproofing of Vidor, Texas, has agreed to do the work for $11,900.00 out of Account
No. 307-21-049-8512-00-10-000-, Project No. BU0015.
ANALYSIS/CONSIDERATION:
Pompeiian Villa needs additional work to the Phase III repairs due to unforeseen damages.
Change Order No. 1 will take care of this additional work.
BUDGETARY AND FISCAL EFFECT
Funds are available in Account No. 307-21-049-8512-00-10-000, Project No. BU0015.
STAFFING EFFECT
None
RECOMMENDATION
It is recommended that the City Council approve the City Manager to execute Change Order No.
1 to the contract with Marsh Waterproofing of Vidor, Texas, for additional repairs at the
Pompeiian Villa, in in the amount of$11,900.00.
P.R. No. 23476
11/17/23 AJS
PAGE 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE
ORDER NO. 1 TO THE CONTRACT WITH MARSH WATERPROOFING OF VIDOR,
TEXAS FOR ADDITIONAL REPAIRS AT THE POMPEIIAN VILLA IN THE
AMOUNT OF $11,900.00 TO A NEW TOTAL OF $241,900.00. FUNDS AVAILABLE IN
ACCOUNT NO. 307-21-049-8512-00-10-000,PROJECT NO. BU0015
WHEREAS, the City Council approved Resolution No. 23-317 at the August 1, 2023
Council Meeting, authorizing an agreement with Marsh Waterproofing of Vidor, Texas, for
Phase III repairs at the Pompeiian Villa in the amount of$230,000.00; and,
WHEREAS, it has been determined additional repairs are needed due to unforeseen
damages revealed after the demolition of the area in preparation to install a new Porte Cochere;
and,
WHEREAS, Marsh Waterproofing of Vidor, Texas,has submitted Change Order No. 1
for this additional work in the amount of$11,900.00; and,
WHEREAS, approval of Change Order No. 01 is deemed an appropriate action.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT,the facts and opinions in the preamble are true and correct.
THAT,the City Council hereby authorizes the City Manager to execute Change Order
No. 1 to the contract with Marsh Waterproofing of Vidor, Texas for additional repairs at the
Pompeiian Villa, in substantially the same form as attached here to Exhibit"A".
THAT,the funding for saidChange Order No. 1 is $11,900.00, to a new total of
$241,900.00.
THAT a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED, AND APPROVED, this day of 2023 AD, at a
Regular Meeting of the City Council of the City of Port Arthur, Texas by the following Vote:
P.R. No. 23476
11/17/23 AJS
PAGE 2 of 2
AYES: Mayor: ,
Councilmembers: ,
NOES: .
Thurman Bill Bartie, Mayor
ATTEST:
Sherri Bellard, City Secretary
ROVED AS TO FORM:
APtilTd (2-rt, 19Julti 4
lecia T zeno, City Attorney
APPROVED FOR ADMINISTRATION:
Ronald Burton, City Manager
APPROVED AS TO FUND AVAILABILITY:
dD67 -4iiti t,✓d),,,,,
Lynda .oswell, Director of Finance Clifton Williams, CPPB, Purchasing Manager
EXHIBIT "A"
CHANGE ORDER
PROJECT: Pompeii Villa - Phase III CHANGE ORDER NO: 1
CONTRACTOR: Marsh Waterproofing DATE: 11.01.2023
240 S Main St ARCHITECT'S PROJECT NO.: 22023
Vidor,Texas 77662 CONTRACT DATE: 07.19.2023
CONTRACT FOR: Renovations
This Contract is changed as follows:
DESCRIPTION UNIT QTY UNIT $ TYPE TOTALS
CPR1 Tile Roof Replacement
remove existing roof-800 sq ft
remove existing wood shingles and lathing
install new 3/4"treated plywood over existing ship lap
install new ice and water shield over treated plywood
install new tile using stainless steel nails or screws
includes all rakes, ridges, starters and all accessories rF $ 11,900.00
SUBTOTAL $ 11,900.00
CONTRACTOR'S FEE $ -
SUBTOTAL $ 11,900.00
BONDS & INSURANCE $ -
TOTAL $ 11,900.00
**See attached breakdown
Not valid until signed by the Owner,Architect and Contractor
The original Contract Sum was $ 230,000.00
Net change by previously authorized Change Orders $The Contract Sum prior to this Change Order was $ 230,000.00
The Constract Sum will be increased by this Change Order in the amount of $ 11,900.00
The new Contract Sum including this Change Order will be $ 241,900.00
The Contract Time will be increased by zero (00) days
The date of Substantial Completion as of the date of this Change Order therefore remains 2/15/2024
NOTE:The summary does not reflect changes in the Contract Sum or Contract Time which have been authorized by Construction Change Directive.
The LaBiche Architectural Group, Inc. Marsh Waterproofing City of Port Arthur
7999'9l y v , Suite 101 240 S Main St, Ste#2 3401 Culture Ctr Dr
T 77706 Vidor,Texas 77662 Port Arthur, Texas 77642
By: By:-�! LI < By:
Date: /7/V '1 Date: 1 I — — 23 Date:
¢E.D 4R
1 N .Lad'ic5%
w a _ _ cn
c
•
11592
C OF 1
e-91‘4red C--ifee‘.
Specializing in Building Restoration
Physical Address: Mailing Address:
240 South Main St.Suite#2 P.O.Drawer 968
Vidor,TX 77662 Vidor,TX 77670-0968
Ph#409-769-0459
Toll free:1-866-251-0234
Fax#409-769-1682
Email: mwaterproofing@aol.com
November 1,2023
Attn: LaBiche Architectural Group
RE: Pompeiian Villa—Change Order
Our recommendations and specifications are based on the information received from your
engineer or representative. We will furnish at the above building, all labor, materials,tools,
equipment, supervision, Workmen's Compensation, Public Liability and Property Damage
Insurance necessary to complete in a thoroughly workmanlike manner all the work described
below:
Scope of Work: Tile Roof Replacement
• Remove existing tile roof—800 sq.ft.
• Remove existing wood shingles and lathing.
• Install new ;/"treated plywood over existing ship lap.
• Install new ice and water shield over treated plywood.
• Install new tile using stainless steel nails or screws.
• Includes all rakes,ridges, starters and all accessories required.
Price: $11,900 plus all applicable tax
Respectfully Submitted,
fl+n,Mars
President
Marsh Waterproofing, Inc.
Acceptance Signature& Date:
NOTES —THIS PROPOSAL IS ONLY VALID FOR 30 DAYS
• If needed, Owner to furnish two(2) 110-volt amp outlets and one (1)220 volt 50-amp
single phase outlet and connect contractors power cord as supplied by contractor.
• If needed, Owner to furnish cold water at spigot in work area.
• If needed, Owner will cooperate with contractor in moving cars, etc. to minimize the
risk of overspray.
• This proposal does not include any asbestos removal, encapsulation, or disposal of the
same.
• We are not responsible for the relocation or covering of any product or production
areas that could get damaged by dust, dirt, falling deck or water during the project.
• If needed, Owner will furnish interior and exterior storage area,parking space for
trucks and storage trailers.
• If needed, Owner to move all non-permanently mounted items away from surfaces to
be treated.
• If needed, Owner to cut back any existing landscaping a minimum of two feet away
from the building prior to work commencing if needed.
• The scope of work under this contract expressly does NOT include investigation,
detection, abatement, replacement, removal or detoxification of and Hazardous
Environmental Condition.
{ • "Hazardous Environmental Condition"means any type or form of asbestos, lead or
fungus, including mildew, mold, rot,rust,mycotoxins, spores, scents or byproducts
produced or released by fungi.
• Our quote is based on the fact that this specification meets your insurance company
approval and local code approval.