INTEROFFICE MEMORANDUM
WATER UTILITY DEPARTMENT-ADMINISTRATION
Date: December 7, 2023
To: The Honorable Mayor and City Council
Through: Ronald Burton, City Manager
From: Calvin Matthews, P.E., Water Utilities Director
RE: PR No. 23518 — Approve Main Wastewater Plant (WWTP) Improvement
Project Change Order No. 3
Introduction:
This agenda item intends to seek the Council's authorization to execute Change Order No. 3
with ALLCO, LLC for the Main Wastewater Treatment Plant (WWTP) Improvement Project
with an increased budget amount of $114,851.00'to the new updated contract amount of
$67,450,464.43.
BackMround:
Resolution No. 22-147 awarded the Main Wastewater Plant(WWTP) Improvement Project to
ALLCO, LLC of Beaumont, Texas for the total amount of$73,643,227.00. The construction
phase is managed by Freese&Nichols, Inc.
On August 2, 2022, Resolution No. 22-329, approved Change Order No. 1 for value
engineering performed by Freese &Nichols, Inc., ALLCO, LLC, Golden Triangle Consulting
Engineers, and the City of Port Arthur staff in the deduction amount of$6,234,049.00.
On December 20, 2022, Resolution No. 22- 586, approved Change Order No. 2 including,
Primary Clarifiers subgrade stabilization, Drying Beds demo, Demo and Remove CSS,
Helical Piles, and Brentwood PVC TF Media price increase and reduction for the removal of
VE Lighting Package, use of bank sand for pipe bedding, and remove Admin Building
improvements in the deduction amount of$73,564.57 and 75-day time extension.
Freese & Nichols, Inc. recommend Change Order No. 3 for an increased amount of
$114,851.00 to replace 4 Trickling Filter Effluent Butterfly Valves with Slide Gates and add
an expansion joint to Aeration Basin Buttress Wall.
Budget Considerations:
The original contract price is $73,643,227.00
Change Order No. 1 decreased the contract amount by $6,234,049.00
Change Order No. 2 decreased the contract amount by $73,564.57
Proposed Change Order No. 3 will increase the contract amount by $114,851.00 to the new
total contract amount of$67,450,464.43.
The extra funding was approved for FY24 and is available in Account No. 405-40-000-8516-
00-00-000, Project No. WS0023
Recommendation:
Recommend City Council approve PR No. 23518 to execute Change Order No. 3 with
ALLCO, LLC of Beaumont, Texas, as described/outlined above.
PR No.23518
12/2/23 JL
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 3 FOR THE MAIN
WASTEWATER TREATMENT PLANT IMPROVEMENT
PROJECT WITH ALLCO, LLC OF BEAUMONT, TEXAS,
INCREASING THE CONTRACT AMOUNT BY $114,851.00
TO A NEW TOTAL CONTRACT AMOUNT OF
$67,450,464.43 WITH FUNDING AVAILABLE IN
ACCOUNT NO. 405-40-000-8516-00-00-000, PROJECT NO.
WS0023.
WHEREAS, the City Council approved Resolution No. 22-147, awarding the Main
Wastewater Treatment Plant Rehabilitation project to ALLCO, LLC of Beaumont, Texas; and,
WHEREAS, on August 2, 2022, Resolution No. 22-329, approving Change Order No. 1
to reduce the contract amount by $6,234,049.00 for Value Engineering performed by Freese &
Nichols, Inc., ALLCO, LLC, Golden Triangle Consulting Engineers and the City of Port Arthur
staff for a new contract amount of$67,409,178.00; and,
WHEREAS, on December 20, 2022, Resolution No. 22-586, approved Change Order
No. 2 including, Primary Clarifiers subgrade stabilization. Drying Beds demo, Demo and
Remove CSS, Helical Piles, and Brentwood PVC TF Media price increase and reduction for the
removal of VE Lighting Package, use of bank sand for pipe bedding, and remove Admin
Building improvements in the deduction amount of$73,564.57 and 75-day time extension with a
final project end date of December 17, 2026; and,
WHEREAS, Freese & Nichols, Inc. has recommended Change Order No. 3 for an
increased amount of $114,851.00 to replace four (4) Trickling Filter Effluent Butterfly Valves
with Slide Gates and add an expansion joint to the Aeration Basin Buttress Wall.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT,the facts and opinions in the preamble are true and correct; and,
PR No. 23518
12/2/23 JL
Page 2 of 3
THAT,the City Manager of the City of Port Arthur is hereby authorized and directed to
execute Change Order No. 3 (Attachment "A") for an increase of $114,851.00 with ALLCO,
LLC of Beaumont, Texas for the Main WWTP Improvements project, to a new projected
budgetary amount of$67,450,464.43; and,
THAT, funding is available in Account No. 405-40-000-8516-00-00-000, Project No.
WS0023; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED AND APPROVED THIS day of , 2023 at a
Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor
Councilmembers ;
NOES:
Thurman Bill Bartie
Mayor
PR No. 23518
12/2/23 JL
Page 3 of 3
ATTEST: APPROVED AS TO FORM:
i½t
(ALP
Sherri Bellard Tizepo
City Secretary City Attorney
APPROVED FOR ADMINISTRATION: APPROVED FOR FUNDING:
Q
Ronald Burton Lynda oswell
City Mana_-er Finance Director
# /1'
Calvin Matthews, '.E. Clifton illiams,CPPB
Water Utilities Director Purchasing Manager
ATTACHMENT A
(CHANGE ORDER NO. 3)
FR E E S E innovative approaches
PracIF�ZNICHOLS Outstanding
irngses
a Outstanding service
11200 Broadway St.,Suite 2320 + Pearland,Texas 77584 + 832-456-4700 + FAX 817-735-7491 www.freese.com
May 11, 2023
Calvin Matthews, PE
Director of Water Utilities
City of Port Arthur Texas
444 4th Street
Port Arthur,TX 77640
Re: Project No. R15056 Port Arthur Main WWTP Improvements: Change Order No.003
Dear Mr. Matthews:
Included with this letter is Change Order No. 003 for the above referenced project.This letter is to serve
as a narrative for the items included in this Change Order No. 003 with supporting documentation
attached.
Item No. 1: Replace 4 Trickling Filter Effluent Butterfly Valves with Slide Gates
After Allco completed the demolition of the items identified on Sheet TF-M1: Trickling Filter
Demolition Plans at Trickling Filter"A",they attempted to close off the 30"Effluent Butterfly Valve
to assist with isolating and cleaning out Trickling Filter"A". It was discovered that all four of the
existing Butterfly Valves for the Trickling Filters were inoperable. This was brought up during a
Monthly Progress Meeting where it was requested of Allco to submit proposals for several
different options to replace the Butterfly Valves. All proposals were evaluated, and the decision
was made to proceed with replacing all four(4) Butterfly Valves with Slide Gates.Allco submitted
CP-010.1 for this unforeseen condition with a total cost of $104,340.00. Freese & Nichols, Inc.
agrees with their cost.
Total Cost: $104,340.00 Additional Days: 0 Calendar Days
Item No. 2:Add Expansion Joint to Aeration Basin Buttress Wall
Note 1 on Sheet AB-S1:Buttress Wall Plan and Sections states that the "basin shall be dewatered
during buttress wall and footing construction". Dewatering the basins is required to relieve the
pressure from the water in the Aeration Basin against the basin's wall that is cracking and bowing
outwards. After Allco had completed installing the rebar and formwork for the Buttress Wall, it
was discovered that one of the gates for the basin is not sealing making it not possible to dewater
the basin. Freese & Nichols, Inc. structural engineers revaluated the design and decided that it
would be acceptable to install the Buttress Wall without dewatering the Aeration Basin if an
expansion joint was added to the Buttress Wall. To add the expansion joint Allco will need to
remove a majority of the formwork that has already been installed, make modifications to the
rebar, reinstall the formwork, and then place the concrete for the Buttress Wall in two separate
placements. Allco submitted CP-011 with a total cost of $10,511.00 for all the labor and effort
required to add the expansion joint to the Buttress Wall. Freese & Nichols, Inc. agrees with their
cost.
Total Cost:$10,511.00 Additional Days:0 Calendar Days
PTR22379 T:\4.0 CONSTRUCTION\4.40 Contract Mod\4.43 Chg Orders\Change Order No.3
Item No. 3:Abnormal Weather Days from December 2022 through March 2023: 0 Days.
The contract documents designate a fixed amount of "Anticipated Bad Weather Delays" per a
given month and when the number of"Bad Weather Days", where rain "equals or exceeds 0.25
inches", go over the "Anticipated Bad Weather" days, that is defined as an "Abnormal Weather
Condition" and "the contractor is entitled to an equitable adjustment in the Contract Times".
From the month of December 2022, up through the end of March 2023, the project has
experienced 0 Abnormal Weather Days.
Total Cost: $0.00 Additional Days: 0 Calendar Days
To summarize, this Change Order No. 003 has an overall cost increase of$114,851.00 and 0 additional
calendar days to the contract time.
I hope the above narrative, along with the included supporting documentation, provides adequate
information to be able to process this Change Order.Please don't hesitate to reach out to me if you need
any further explanation or backup documentation.
Sincerely,
Rami Abusheikh, P.E.
Construction Manager
cc:Jess Liao,Hani Tohme,Brian Wallace,Murali Erat
PTR22379 T:\4.0 CONSTRUCTION\4.40 Contract Mod\4.43 Chg Orders\Change Order No.3
a
Change Order No.3
Project Port Arthur Main WWTP Improvements Project Number
Owner City of Port Arthur R15056
Contractor Allco,LLC TX 875
Construction Manager Rami Aubhseikh,P.E. PTR22379
Design Professional Murali Erat,P.E. PTR22380
CoPA Account No. 169-07-015-8516-00-40-000;404-40-000-8516-00-00-000
Design Professional ARP002-GRE-WWT; TW-0003-CON
Change Order No. 003 Date 12/5/2023
Item Description Additional Days Change Amount
1 Replace 4 Trickling Filter Effluent Butterfly Valves with Slide Gates 0 $ 104,340.00
2 Add Expansion Joint to Aeration Basin Buttress Wall 0 $ 10,511.00
3 Abnormal Weather Days from December 2022 through March 2023 0 $ 0.00
4 $ -
6 / $
7 / $ -
9 / $
Net Change in Contract Price this Change Order $ 114,851.00
Net Change in Contract Time this Change Order 0 Days
The compensation in this Change Order is the full, complete, and final compensation for all costs Contractor may incur because of or
relating to this change whether said costs are known, unknown,foreseen,or unforeseen at this time, including without limitation,any
cost for delay, extended overhead, ripple or impact cost, or any other effect on changed or unchanged Work because of this Change
Order. The changes in Contract Times are the complete and final adjustments for impacts to the ability of Contractor to complete the
Work within the Contract Times and are the only adjustments to which Contractor is entitled.All terms and provisions of the Contract
Documents remain in effect except as specifically modified by this Change Order.
li Original Contract Amount: $ 73,643,227.00
Net from Previous Change Orders: $ (6,307,613.57)
Total Amount of This Change Order: $ 114,851.00
Percent Change in Contract Amount of this Change Order: 0.16%
Total Percent Change in Contract Amount to Date: -8.41%
New Contract Amount: $ 67,450,464.43
Origin!Contract Duration: 1,580 Calendar Days
Additional Contract Days from Previous Change Orders: 75 Calendar Days
Additional Contract Days this Change Order: 0 Calendar Days
Revised Contract Time: 1,655 Calendar Days
Original Final Completion Date: 10/3/2026
Previous Final Completion Date: 12/17/2026
Revised Final Completion Date: 12/17/2026
I
Change Order No.3 Page 1 of 2
Change Order No.3
Recommended by Design Professional: Recommended by Construction Manager:
Hit.‘al;164#,,,vt.
12/05/2023 �\ 12/05/2023
Murali Erat, PE Date RarrirAb eeikh, PE Date
(Freese and Nichols,Inc.) (Freese and Nichols,Inc.)
Approved by Contractor: Approved by Owner:
Brandon Harrison Date Ronald Burton Date
Vice-President City Manager
Allco, LLC City of Port Arthur
Approved by Owner:
Calvin Matthews, PE Date
Director of Water Utilities
City of Port Arthur
Change Order No.3 Page 2 of 2
Item No. 1
Li CO Design Build
Construction Management
General Contractors
P.O.Box 3684, Beaumont,Texas 77704 Phone:409-860-4459 Fax:409-860-3857
Email:allco@allco.com
February 22, 2023
Freese& Nichols
10497 Town&Country Way,Suite 500
Houston,TX 77024
Attn: Murali Erat
Re: City of Port Arthur
WWTP Improvements Project
Change Proposal 10—Trickling Filter Slide Gate Option
Dear Mr. Erat:at:
Allco proposes the following change order in the amount of $104,340.00 to replace the existing 30" trickling filter
effluent valves with Slide Gates:
DESCRIPTION/COST SUMMARY
Remove and replace the existing 30"trickling filter effluent valves(4ea)w/30"X30"slide gates;See attached quote
from Vision.
Price Per Gate--$26,085.00
Time Extension—TBD
ITEM LABOR MATERIALS EQUIPMENT/FUEL SUBCONTRACTOR MARKUP/OH TOTAL
Replace IF $13,530.44 $73,200.00 $4,000.00 $0.00 $13,609.57 $104,340.00
Valves w/
Slide Gates
Please contact the undersigned if you have questions or issues regarding this matter.
Respectfully,
Allco, LLC
Brandon Harrison
O, O O s C
N O O N • . .
O N
C
N 6 O . ' i . . . .
p = Tr
`° n n q
n y
O N pp v y
el
O —
0
69 69 69 69 69 69 69 69 69 S9 6, St 61 6, N 69 Yi = 0
2
0 Q
y r a C. M
z° z F 0 L co
a
•.• Y a°. O
d '� a g $ . . . . . 8o c0, F' LR.,
4' 1." ° o c 3 8i rJ ` O 0
0 0 0
o a F e c R
t e ` V U °
' . O W un 69 6s W 6s » o /O?VVVC V 69i (A 6, A N Z Vl V
3 tij
u E
F
IC d°
d '5 E
w
TO d
e E Y
Y I.
co
TO
0 W a
Y
d m;o W w cz Y) a, 64 v, 6, v, 64
E.
Ia.
a m o o $ ii.
cs Au
C ppU m F N r F a V y
UO G r C �"al w
C Y ii d
I.
o15
Ii
69ce . h69 69 » A° o0 2 � Ucr) U 5 -Td-
a V] > F g ° v
Q N °Y ° _ A 2 e 2 5 L e C
a a g a F, . w e, n F
O C Y a
0
a' 3 p a Dv �c
a 8 a) a a a
CC ac d.a o: °C
w ° ,a x .
cc• 2 o p :: m N H p8 N = a o o a w..
O N v O d OI C W. O N a N 6 o O pO 6 O •
I. Q °= 4 v U " o ''. a o o r N O r ° R
Z a Y l- A a° ° _ c14. r al 2
< � y o
Y�� Q aX e o .a $ F ..
I r 61 o o a U
O U m co a en .°, . 69 6, 6, 6, 6, 6, 69 69 69 6 69 69 61 69 i Y) A A63 us 14 69 EA
eM 3
eo L
s
o ° o F e U
Y
C S S > E... Ts0 o °
y o
,e U ° OG a F U w
A .ten 1 2 Z vi = F
U Y Y
z , 3 3
C. aS U
qz
al
C ea
s` ..
A' W Y v
a
d L_ ...i L O ..
L1.
- `= P.
3 ° a 3 c = L e Y � o g
0. .a .2 W o y o v $ �
2".9
O gf
m o '� Y
U 'O U .Y. C 11 U ..
5 .
j .` m 6°r. a °'8 .0 8 o Y e
Y L .r. t . •� G Y C '� U�+
Y Y 1
i 8• 3 y o sE g W L
o e e
✓ u a :32reArAO : C)
a` a g - 4.1 oraow =