Date: December 28, 2023
To: The Honorable Mayor and City Council
Through: Ron Burton, City Manager
From: George Davis, Director of Pleasure Island
RE: P.R. 23533 —Executing change order No. i to the contract between the City of
Port Arthur and Kraftsman Commercial Playgrounds and Water Parks,
decreasing the contract amount by$20,992.74 to a new contract total of
$728,965.01 for the construction of a playground at 1520 West TB Ellison
Pkwy(Lakefront Park)on Pleasure Island
Introduction:
The intent of this Agenda Item is to request the City Council's approval of P. R. No. 23533
authorizing the City Manager to execute change order No. 1 to the contract between the City
of Port Arthur and Kraftsman Commercial Playgrounds and Water Parks of Spring, Texas,
decreasing the contract amount by $20,992.74 to a new contract total of$728,965.01 for the
construction of a playground at 1520 West TB Ellison Pkwy (Lakefront Park) on Pleasure
Island.
Background:
Pursuant to Resolution No. 22-574,the City of Port Arthur awarded a contract to Kraftsman
Commercial Playgrounds and Water Parks to construct a playground at Lakefront Park on
Pleasure Island. Initially,the contractors planned to use a concrete base, however, they
realized that the ground was in better condition than they thought, so they used base materials
instead. The construction of the playground is complete, a comprehensive safety inspection of
equipment, under the Consumer Product Safety Commission's guidelines has been completed
and certification of compliance was completed by a National Playground Safety Inspector.
Budget Impact:
None
Recommendation:
It is recommended that the City Council approve P.R.No.23533 authorizing the City Manager
to execute change order No. 1 to the contract between the City of Port Arthur and Kraftsman
Commercial Playgrounds and Water Parks of Spring, Texas, decreasing the contract amount
by $20,992.74 to a new contract total of$728,965.01 for the construction of a playground at
1520 West TB Ellison Pkwy(Lakefront Park) on Pleasure Island.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
P. R. #23533
12/19/2023 gd
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN
THE CITY OF PORT ARTHUR AND KRAFTSMAN COMMERCIAL
PLAYGROUNDS AND WATER PARKS OF SPRING, TEXAS,
DECREASING THE CONTRACT AMOUNT BY $20,992.74 TO A
NEW CONTRACT TOTAL OF $728,965.01 FOR THE
CONSTRUCTION OF A PLAYGROUND AT 1520 WEST TB
ELLISON PKWY (LAKEFRONT PARK) ON PLEASURE ISLAND
WHEREAS, per Resolution No. 22-574, the City Council awarded a contract to
Kraftsman Commercial Playgrounds and Water Parks through BuyBoard Cooperative
Purchasing Program Contract Number 679-22, for the construction of a playground at 1520 West
T.B. Ellison Pkwy (Lakefront Park) in the total amount not to exceed $749,957.75; and,
WHEREAS, during the construction, Kraftsman Commercial Playgrounds and
Water Parks did not use concrete as a base for the playground and used base materials instead
which resulted in a decreased amount of$20,992.74; and
WHEREAS, Change Order No. 1 (attached hereto as Exhibit "A") has been
submitted to reflect the decreased amount which resulted in the new total contract amount of
$728,965.00; and,
WHEREAS, the construction of the playground at Lakefront Park on Pleasure
Island has been completed and a comprehensive safety inspection of equipment under the
(CPSC) Consumer Product Safety Commission's guidelines and certification of compliance with
(NPSI)National Playground Safety Inspector as delineated in Exhibit"B"; and,
WHEREAS, staff recommends that the City Council authorize the City Manager to
execute Change Order No. 1 decreasing the contract amount by $20,992.74 to a new total
contract amount of$728,965.00; now therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR, TEXAS:
P. R. #23533
12/19/2023 gd
Section 1. That the facts and opinions in the preamble are true and correct.
Section 2. That the City Manager of the City of Port Arthur is hereby
authorized and directed to execute, on behalf of the City of Port Arthur, Change Order No. 1, to
delete the using of concrete as a base for the playground at 1520 West TB Ellison Pkwy, thereby
decreasing the contract amount by $20,992.74, for a new total contract amount of$728,965.01
and authorize the remaining final payment to Kraftsman Commercial Playgrounds and Water
Parks of Sping, Texas.
Section 3. That a copy of the caption of this Resolution be spread upon the
Minutes of the City Council.
READ, ADOPTED AND APPROVED THIS day of , A.D.,
2024, at a Regular Meeting of the City Council of the City of Port Arthur, by the following vote:
AYES:(Mayor)
Councilmembers:
NOES:
Thurman"Bill" Bartie
Mayor
ATTEST:
Sherri Bellard
City Secretary
P. R. #23533
12/28/2023 gd
APPROVED AS TO FORM:
121-P -e.
al Tizeno, sq.
City Attorney
APPROVED AS TO ADMINISTRATION:
Ron Burton
City Ma ger
N
George avis
Director of Pleasure Island
APPROVED AS TO AVAILABILITY OF FUNDS:
AO 69JV-a1-1
Lynda :oswell
Director of Finance
61.iiet, (Jiaoi,
Cliff n Williams, CPPB
Purchasing Manager
P. R. #23533
12/28/2023 gd
cc »
EXHIBIT A
CHANGE ORDER NO. 1
ORIGINAL AGREEMENT DATE: November 9, 2022
PROJECT DESCRIPTION: Construction of a playground at Lakefront Park on Pleasure Island
CHANGE IN SCOPE:
#1: Reduction in using base materials instead of concrete.
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT PRICE: $749,957.75
CURRENT CONTRACT PRICE: $749,957.75
The Contract Amount due to this CHANGE ORDER#1 will decrease by: $20,992.74
The new CONTRACT AMOUNT including the CHANGE ORDER will be: $728,965.01
ORIGINAL CONTRACT DAYS: _N/A
NEW CONTRACT DAYS: N/A
SIGNED AND AGREED TO on the day of , 2024.
KRAFTSMAN COMMERCIAL PLAYGROUNDS
AND WATER PARKS
By:
Print Name:
Title:
SIGNED AND AGREED TO on the day of , 2024.
CITY OF PORT ARTHUR
By:
Ron Burton,
City Manager
)$ BU
�� K rafts man QUOTE#Q77997-1
COMMERCIAL PLAYGROUNDS & Date:09/27/2023
KRAFTSMAN WATER PARKS Project:27559
_ 19535 Haude Road Created By:Ryan Slott
t4, ` o� Spring,TX 77388
TSMANp0:4" Phone: (281)353-9599 Fax: (281)353-2265
Page 1 of 2
BILL TO SHIP TO
Port Arthur, City of ` 409-982-4675
George Davis
Fun Island Playground Fun Island Playground
PO Box 1089 Pleasure Island (Under Bridge)
Port Arthur,TX 77641 Port Arthur,TX 77640
Terms:
Percentage Completed Draws
QTY Code Description Size Weight Color Unit Price Ext. Price
Change Order 1
-6035 CONC4RB Concrete Pad,4"thick concrete pad with, rebar reinforced, $14.09 -$85,033.15
broom finish,minimum 500 sq.ft.
6035 BASE-4 Compacted Stabilized base,installed at a 4"depth. By: Per Foot $8.25 $49,788.75
Kraftsman
-1 DISC -$4,251.66 $4,251.66
Deduct for Discount issued on original order
Item Subtotal: -$30,992.74
Shipping & Handling:
Equipment Subtotal: -$30,992.74
Tax: $0.00
Install: $10,000.00
Total: -$20,992.74
Initials
P. R. #23533
12/28/2023 gd
EXHIBIT "B"
6` 0,..
. .,, , Kraftsman Commercial Playgrounds and Water Parks
"'® 19535 Haude Road
KR AFTS MA N Spring,Texas 77388
281-353-9599
\. Kraftsmanplay.com
George Davis
City of Port Arthur
PO Box 1089
Port Arthur, TX 77641
RE: Fun Island Depot
Installation of Playground Structure
Dear Mr. George Davis,
I conducted a complete safety inspection of equipment under CPSC (Consumer Product Safety
Commission Guidelines) and certification of compliance with NPSI (National Playground Safety
Inspector Criteria). The review was conducted for components, structural integrity, functional
integrity, and general safety criteria.
The unit was found to be installed in compliance per the manufacturers' instructions.
1
Res ectfully submitted,
Pope.064.4-_____
Korey Soderberg
Certified Playground Safety Inspector
Certificate#_57347-426
1