INTEROFFICE MEMORANDUM
Date: January 19,2024
To: The Honorable Mayor and City Council
Through: Ron Burton,City Manager
From: John Cannatella,PE,City Engineer
RE: PR No. 23560:Various Streets Roadway Improvement Projects-District 2&3. Change
Order No. 5 for the removal and replacement of seventeen driveways on Tyrrell Parkway
from 32nd Street to Woodlawn Drive for$102,136.00 submitted by Texas Materials Group,
Inc. -Gulf Coast Area of Beaumont,Texas.
Introduction:
The intent of this agenda item is to authorize the City Manager to execute Change Order No. 5 for the Various
Streets Roadway Improvement Project - District 2 & 3 for the removal and replacement of seventeen (17)
driveways on Tyrrell Parkway from 32"d Street to Woodlawn Drive for$102,136.00.
Background:
Pursuant to Resolution No. 22-399 the City of Port Arthur awarded a contract for the Various Streets Roadway
Improvements Project;District 2&3 to Texas Materials Group,Inc.-Gulf Coast Area of Beaumont,Texas. The
contract was advertised and bid under Project No. P22-074 for the rehabilitation of twenty-three(23)streets for
the amount of$10,208,437.93.
Pursuant to Resolution No. 22-451,Change Order No. 1,approved by Port Arthur's City Council,removed four
(4)streets from the twenty-three(23)streets,changing the new number of streets to a total of nineteen(19)streets.
The original contract amount of$10,208,437.93 was reduced by $2,473,929.00 to the new contract amount of
$7,734,508.93. Change Order No. 1 also reduced the original number of contract completion days from 700
calendar days by 110 days to 590 calendar days.The new contract completion date is October 2,2024.
Pursuant to Resolution No. 23-200, Change Order No. 2, approved by Port Arthur's City Council, removed 7th
Street from Stadium Road to Williams Avenue; added Evergreen Drive from Bernhardt Drive to the Dead
End, added cement stabilized backfill, and adjusted quantities on the remaining streets for the amount of
$499,205.60. Change Order No. 2 increased the previous contract amount of$7,734,508.93 by $499,205.60 to
the new contract amount of$8,233,714.53.
Pursuant to Resolution No. 23-259, Change Order No. 3, approved by Port Arthur's City Council, was for
additional work performed on Lakefront Street on Pleasure Island from the South Levee Road to T. B. Ellison
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
S:\Englneenng\PUBLIC WORKS\PW-ENGINEERING\C.I.P.PROJECTS\Year 2022\VARIOUS STREETS Phase 2 Dist 2-3\Change Orders\Change Order 5\Agenda Memo Dist 2-3 Change Order U 5.dor
Parkway. This section of roadway was not part of the original scope of repair work and sits adjacent to the Frisbee
Golf Course.An Emergency Letter was sent to the City Manager outlining the new scope of work,increasing the
contract by$196,098.09 to the new contract amount of$8,429,812.62.
Pursuant to Resolution No. 23-406, Change Order No.4, approved by Port Arthur's City Council,removed and
replaced eighty-seven(87)driveways and added cement stabilized sand for the amount of$544,729.31 increasing
the contract amount of$8,429,812.62 to the new contract amount of$8,974,541.93.
Change Order No. 5 is being submitted by Texas Materials Group,Inc.—Gulf Coast Area of Beaumont, Texas,
for the removal and replacement of seventeen(17)driveways on Tyrrell Parkway from 32nd Street to Woodlawn
Drive for the amount of$102,136.00 increasing the contract amount of$8,974,541.93 to the new contract amount
of$9,076,677.93.
Budget Impact:
Funds are available in the Street Program,Capital Improvements Project Account No.307-21-053-8517-00-10-
000.
Recommendation:
It is recommended that the City of Port Arthur's City Council approve PR No. 23560 with Texas Materials
Group,Inc.—Gulf Coast Area of Beaumont,Texas,authorizing the City Manager to execute Change Order
No. 5 to the Various Streets Roadway Improvement Project-District 2 & 3, removing and replacing
seventeen(17)driveways for the amount of$102,136.00 increasing the contract amount of$8,429,812.62 to the
new contract amount of$9,076,677.93.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
PR No.23560
1/19/2024 mje
Page 1 of 4
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 5 TO THE CONTRACT BETWEEN THE CITY OF
PORT ARTHUR AND TEXAS MATERIALS GROUP, INC. — GULF
COAST AREA OF BEAUMONT, TEXAS, FOR THE VARIOUS STREETS
ROADWAY IMPROVEMENTS PROJECT-DISTRICTS 2 & 3, FOR
SEVENTEEN ADDITIONAL DRIVEWAYS ON TYRRELL PARKWAY
FROM 32ND STREET TO WOODLAWN DRIVE, THAT INCREASES THE
CONTRACT AMOUNT BY $102,136.00 TO THE NEW CONTRACT
AMOUNT OF $9,076,677.93. FUNDING IS AVAILABLE IN THE
CAPITAL IMPROVEMENT PROJECT ACCOUNT 307-21-053-8517-
00-10-000.
WHEREAS, Pursuant to Resolution No. 22-399, Port Arthur's City Council awarded
a contract for the Various Streets Roadway Improvements Project-Districts 2 & 3 to Texas
Materials Group, Inc. - Gulf Coast Area of Beaumont, Texas, with a projected budgetary
impact of $10,208,437.93; and,
WHEREAS, pursuant to Resolution No. 22-451, approved by Port Arthur's City
Council, Change Order No. 1 removed four streets from the improvement program and
reduced the original contract amount of $10,208,437.93 by $2,473,929.00 resulting in
the new contract amount of $7,734,508.93; and,
WHEREAS, additionally, Change Order No. 1 reduced the original number of
contract completion days from 700 calendar days by 110 days to 590 calendar days
resulting in the new contract completion date of October 2, 2024; and,
WHEREAS, pursuant to Resolution No. 23-200, Change Order No. 2, approved by
Port Arthur's City Council, removed 7th Street (Stadium Road to Williams Avenue), added
Evergreen Drive (Bernhardt Drive to Dead End), added cement stabilized backfill, and
PR No.23560
1/19/2024 mje
Page 2 of 4
adjusted quantities for the remaining streets; Change Order No. 2 also added
$499,205.60 to the contract, increasing the previous contract amount of $7,734,508.93
to the new contract amount of $8,233,714.53; and,
WHEREAS, pursuant to Resolution No. 23-259, Change Order No. 3, approved by
Port Arthur's City Council, addressed additional repair work performed on Lakefront Street
on Pleasure Island from South Levee Road to T. B. Ellison Parkway increasing the contract
amount by $196,098.09 to the new total amount of $8,429,812.62; and,
WHEREAS, pursuant to Resolution No. 23-406, Change Order No. 4, approved by
Port Arthur's City Council, added eighty-seven (87) driveways and cement stabilized sand
and increased the contract amount of $8,429,812.62 by $544,729.31 to the new contract
amount of $8,974,541.93; and,
WHEREAS, Change Order No. 5 is being submitted by Texas Materials Group,
Inc. - Gulf Coast Area of Beaumont, Texas, for the removal and replacement of seventeen
(17) driveways increasing the contact amount of $8,974,541.93 by $102,136.00 to the
new contract amount of $9,076,677.93; and,
WHEREAS, approval of PR No. 23560 for Change Order No. 5 is herein deemed
an appropriate action; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, Change Order No. 5 is herein approved and the City Manager is hereby
authorized to execute said Change Order No. 5 to the contract between the City of Port
Arthur and Texas Materials Group, Inc. - Gulf Coast Area of Beaumont, Texas; and,
PR No. 23560
1/19/2024 mje
Page 3 of 4
THAT, Change Order No. 5, presented by Texas Materials Group, Inc. - Gulf Coast
Area of Beaumont, Texas, will add seventeen (17) driveways to Tyrrell Parkway from 32nd
Street to Woodlawn Drive increasing the previous contract amount of $8,974,541.93 by
$102,136.00 to the new total contract amount of $9,076,677.93, and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the
City Council.
READ, ADOPTED AND APPROVED this the day of , A.D.
2024 at a meeting of the City of Port Arthur, Texas by the following
vote: Ayes: Mayor:
Councilmembers:
Noes:
Thurman Bill Bartle
Mayor
ATTEST:
Sherri Bellard
City Secretary
PR No. 23560
1/19/2024 mje
Page 4 of 4
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION:
Lilfra kALty §
Valecia zeno, Esquire Ron Burton
City Attorney City Manager
APPROVED AS FOR AVAILABILITY OF
FUNDS:
Lyn a "Lyn" Boswell, MA, IC -CM
Director of Finance
John Can ella, PE
City Engineer
Clifton Williams, CPPB
Purchasing Manager
EXHIBIT A
CITY OF PORT ARTHUR
Public Works Engineering
DATE: JANUARY 19,2024
PROJECT: VARIOUS STREET REHABILITATION-DIST 2&3
OWNER: CITY OF PORT ARTHUR
CONTRACTOR: GULF COAST A CRH COMPANY OF BEAUMONT,TX
CHANGE ORDER NO.: 5
THE FOLLOWING CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE HEREBY MADE:
Adjust the Estimated Quantities to reflect the Actual Quantities used in the completion of the project:
Item Item Description Unit Original Unit Price Original New Quantity Added New Amount
No. Code Quantity Amount
Tyrrell Parkway(32nd St.to Woodlawn Dr.)(ST4006)
1 DRIVEWAYS:REMOVE EXISTING DRIVEWAYS-QTY 17
DRIVEWAYS:REPLACE WITH CONCRETE DRIVEWAY-QTY 17 SF 0 $ 32.00 $ - 3191.75 $ 102,136.00
TOTAL CHANGE ORDER $ 102,136.00
NEW CONTRACT
ORIGINAL CONTRACT AMOUNT
$ 8,974,541.93 AMOUNT $ 9,076,677.93
ORIGINAL CONTRACT AMOUNT: $ 10,208,437.93
TOTAL AMOUNT OF CHANGE ORDER NO.1: 2,473,929.00)
TOTAL AMOUNT OF CHANGE ORDER NO.2: $ 499,205.60
TOTAL AMOUNT OF CHANGE ORDER NO.3: $ 196,098.09
TOTAL AMOUNT OF CHANGE ORDER NO.4: $ 544,729.31
TOTAL AMOUNT OF CHANGE ORDER NO.5: $ 102,136.00
PERCENT OF CHANGE ORDER NO.1: -24.23%
PERCENT OF CHANGE ORDER NO.2: 4.89%
PERCENT OF CHANGE ORDER NO.3: 2.50%
PERCENT OF CHANGE ORDER NO.4: 5.34%
PERCENT OF CHANGE ORDER NO.5: 1.00%
TOTAL PERCENT OF CHANGE ORDER NOs.1,2,3,4&5: -10.51%
NEW CONTRACT AMOUNT: $ 9,076,677.93
ORIGINAL CONTRACT COMPLETION DATE: October 2,2024
NO CALENDAR DAYS HAVE BEEN ADDED TO CHANGE ORDER NO.5
INSPECTED BY: PREPARED BY:,4 et lo er., •t 12_
/r 1 � - -
Gregory K.Casmire,ER;Inspector M.7nifer Edw r ,BAAS,MPA;CIP Manager
APPROVED BY: APPROVED BY:
Zach Leggett,Project Manager;Gulf Coast a CRH Company John Cannatella,PE,City Engineer
APPROVED BY: APPROVED BY:
1 .9\X
Dr.Hani Tohme,PE,Consultant Clifton Williams,CPPB,Purchasing Manager
APPROVED BY:
Ron Burton,City Manager
S:\Engineering\PUBLIC WORKS\PW-ENGINEERING\C.I.P.PROJECTS\Year 2022\VARIOUS STREETS Phase 2_Dist 2-3\Change Orders\Change Order 5\Dist 2-3 Change Order#5