INTEROFFICE MEMORANDUM
WATER UTILITIES DEPARTMENT-
Date: February 1, 2024
To: The Honorable Mayor and City Council
Through: Ronald Burton, City Manager
From: Calvin Matthews, P.E., Water Utilities Director
RE: PR No. 23589—Change Order No. 1 for Landfill Waterline Extension Project
Introduction:
This Agenda Item is to seek the City Council's approval for Change Order No. 1 for the Landfill
Waterline Extension Project with BDS Construction, LLC dba MK Constructors of Vidor, Texas.
Background:
Resolution No. 23-386 awarded the project to BDS Construction, LLC dba MK Constructors of
Vidor,Texas for$1,382,509.00,and Arceneaux Wilson&Cole Engineering Firm of Port Arthur,
Texas is the project engineer and construction manager.
Due to the project award amount being below the original project budgeted cost, the City has
requested the Contractor to extend the proposed water line into the landfill property. The water
line extension entails the addition of 370 ft of 8"PVC pipe,two mechanical joint 45-degree bend
fittings, one fire hydrant assembly, one auto flush valve, and one service tap with RPZ backflow
preventer to serve the landfill office building.
Budget Impact:
The Project was awarded for$1,382,509.00.
Change Order No. 1 is an increase of $74,870.00 for a new total contract amount of
$1,457,379.00.
Funding is available in Account No. 405-40-000-8516-00-00-000, Project No. WS-0008 CON.
Recommendation:
It is recommended that the City Council approve PR 23589 to proceed with Change Order No.
1, as discussed/outlined above.
"Remember,we are here to serve the Citizens of Port Arthur"
PR No. 23589
2/1//24 JL
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT WITH
BDS CONSTRUCTION, LLC DBA MK CONSTRUCTION OF
VIDOR, TEXAS, FOR THE LANDFILL WATERLINE
EXTENSION PROJECT, INCREASING THE CONTRACT
AMOUNT BY $74,870.00 TO THE NEW TOTAL CONTRACT
AMOUNT OF $1,457,379.00 FUNDS ARE AVAILABLE IN
ACCOUNT NO. 405-40-000-8516-00-00-000, PROJECT NO. WS-
0008 CON.
WHEREAS, pursuant to Resolution 23-386, the Landfill Waterline Extension Project
was awarded to BDS Construction, LLC dba MK Constructors of Vidor, Texas with a total
projected budgetary amount of$1,382,509.00; and,
WHEREAS, pursuant to Resolution 21-078, Arceneaux Wilson & Cole Engineering
Firm of Port Arthur, Texas was hired as Construction Engineer to oversee the project; and,
WHEREAS, due to the project award amount being below the original project budgeted
cost, the City has requested the Contractor to extend the proposed water line into the landfill
property; and,
WHEREAS, Arceneaux Wilson& Cole Engineering Firm proposed Change Order No. 1
for the additional project scope, including the installation of 370 ft of 8" PVC water line, two
mechanical joint 45-degree bend fittings, one fire hydrant assembly, one auto flush valve, and
one service tap with RPZ backflow preventer to serve the landfill office building (EXHIBIT
"A") increasing contract amount by $74,870.00 to the new total contract amount of
$1,457,379.00.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT,the facts and opinions in the preamble are true and correct; and,
PR No. 23589
2/1//24 JL
Page 2 of 3
THAT, the City Council hereby approves Change Order No. 1 (EXHIBIT "A") to
increase the amount by $74,870.00 to the new total contract amount of$1,457,379.00; and,
THAT, the funding is available in Account No. 405-40-000-8516-00-00-000, Project No.
WS-0008; and,
THAT, a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ, ADOPTED, AND APPROVED, this day of , 2024, AD,
at a Regular Meeting of the City Council of the City of Port Arthur, Texas by the following
Vote: AYES:
Mayor:
Councilmembers:
NOES:
Thurman Bill Bartie
Mayor
ATTEST:
Sherri Bellard
City Secretary
APPROVED AS TO FORM:
e- ditiicg
Valecia Tize
City Attorney
PR No. 23589
2/1//24 JL
Page 3 of 3
APPROVED F INISTRATION:
Ronald Burton
City Manage
Calvin Matthews, P.E.
Water Utilities Director
APPROVED AS TO FUND AVAILABILITY:
Lyn oswell
Finance Director
U/Of1/4, LA4/4":-.
Clifton Williams, CPPB
Purchasing Manager
EXHIBIT "A"
(CHANGE ORDER NO. 1)
AIM
*VC.)
+MN ARCENEAUX WILSON&COLE
engineering 1 surveying 1 planning
January 31, 2024
Mr. Calvin Matthews, P.E.
City of Port Arthur
Director of Water Utilities
444 4th Street
Port Arthur, Texas 77640
RE. Proposal For Change Order No. 01 for
LANDFILL WATER LINE EXTENSION
AWC Job No. CPA-1010
Mr. Matthews:
Attached is Change Order No. 1 for the Landfill Water Line Extension project. This
change order is for increasing the contract amount by $74,870.00.
Due to the project award amount being below the original project budgeted cost,
the City has requested the Contractor to extend the proposed water line into the
landfill property. This work will allow the City to serve potable water to the landfill
office personnel as they currently do not have access to a potable water source
on site. The extension into the landfill property entails the additions of 370 linear
feet of 8" PVC CertaLok DR 18 water line, two (2) 8" mechanical joint 45-degree
bend fittings, one (1) fire hydrant assembly, one (1) auto flush valve, and one (1) 1"
service tap with RPZ backflow preventer. The City and Engineer have reviewed
the proposed work to be performed and agree it is within the budget and scope
as requested.
This change order will not impact the original contract time. This change order
will increase the original contract amount by$74,870.00. We recommend that the
City of Port Arthur authorize this change order to the contract as submitted. We
have attached Change Order No. 1 which modifies the contract to reflect this
I
409.724.7888
3120 Central Mall Drive
Port Arthur,TX 77642 Engineering Surveying
awceng.com F-161'=14 "0194049
A41%. awn
_.
change for your consideration and action.
Should you have any questions or require additional information, please contact
our office.
ARCENEAUX WILSON&COLELLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
Keith Zotzky, . ., CFM
Vice President of Engineering Services
Attached.
Change Order#01
♦D�
•��
TMAI ARCENEAUX WILSON&COLE
n.yn•c.ln�1+urvcyin�I Pbnr nc)
CHANGE ORDER NO. 1
DATE: January 31, 2024 JOB NO.: CPA-1010
AGREEMENT DATE: October 16, 2023
NAME OF PROJECT: Landfill Water Line Extension
OWNER: CITY of PORT ARTHUR
CONTRACTOR: MK CONSTRUCTORS
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add 370 LF 8" PVC CertaLok DR 18 Installation in Trench at$143/LF. ($52,910.00)
2. Add 2 EA 8" MJ 45 Degree Bend at$580/EA. ($1,160.00)
3. Add 1 EA Fire Hydrant Assembly at$9,300/EA. ($9,300.00)
4. Add 1 Auto Flush Valve at$6,500/LS. ($6,500.00)
5. Add 1 1" Service Tap w/RPZ Backflow Preventer at $5,000/LS. ($5,000.00)
TOTAL $74,870.00
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $1,382,509.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $1,382,509.00
The CONTRACT PRICE due to this CHANGE ORDER will be [increased]
by: $74,870.00
The new CONTRACT PRICE, including this CHANGE ORDER,will be $1,457,379.00
I
1 of 2
♦�_ CHANGE ORDER NO. 1
.41emaimic
January 31, 2024
" Job No. CPA-1010
ARCENEAUX WILSON&COLE
englnecrir.g I surveying I oI rw,,
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 180 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 0 Calendar Days
CURRENT DATE OF COMPLETION: May 26, 2024
CONTRACT TIME due to this CHANGE ORDER will be increased by
The New DATE OF COMPLETION: May 26, 2024
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred
by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED Y ENGINEER: ACCEPTED BY:
ARCENEAUXV N & COLE LLC (CONTRACTOR, OFFICER OR OWNER)
MK CONSTRUCTORS
ACCEPTED BY:
CITY of PORT ARTHUR
I
2 of 2