HomeMy WebLinkAbout(P3) Fire Station No. 3, 2024 0227_Council PresentationCITY OF PORT ARTHUR FIRE STATION #3
1
PROJECT OVERVIEW
EXTERIOR DESIGN
PROPOSED TIMELINE
CITY OF PORT ARTHUR FIRE STATION #3
2
CITY OF PORT ARTHUR FIRE STATION #3
3
CITY OF PORT ARTHUR FIRE STATION #3
4
CITY OF PORT ARTHUR FIRE STATION #3
5
PROPOSED TIMELINE
SCHEMATIC DESIGN
Submit Final Program January 31, 2023
Submit Final SD Package February 28, 2023
Submit Statement of Probable Cost March 15, 2023
Meeting with City Manager March 28, 2023
SD Community Meeting April 12, 2023 Present SD to Council April 26, 2023
DESIGN DEVELOPMENT
DD Begins April 27, 2023
Submit Final DD Package May 31, 2023
CONSTRUCTION DOCUMENTS
CD Begins June 1, 2023
Submit 50% CD July 7, 2023
Submit 80% CD July 28, 2023
Submit 95% CD to Plan Review January 26, 2024
Submit 100% CD for Bidding March 4, 2024*
BIDDING
Bidding April 4, 2024
Contract Negotiations (Contractor) May 3, 2024
CONSTRUCTION
Estimated Construction Start May 6, 2024
Estimated Construction Completion April 2025
*Pending approval from permitting department