INTEROFFICE MEMORANDUM
Date: April 12, 2024
To: The Honorable Mayor and City Council
Through: Ron Burton, City Manager
From: John Cannatella,PE, City Engineer
RE: PR. No. 23721 — Stonegate Drainage Improvement Project. Change Order No. 1 for Value
Engineering Savings reduction and project modifications cost addition. Project No. DR1PO4.
Introduction:
The intent of this agenda item is to seek City Council's approval for the City Manager to execute Change
Order No. 1 with Brystar Contracting, Inc. (Brystar)of Beaumont, Texas, for value engineering savings
of$1,638,750.00;adding$686,859.00 for lowering the culvert boxes by one foot(1')at the golf course due
to pipeline conflicts;and adding$101,201.10 for reinforced concrete liner to the bottom of the ditch because
of water table issues. The original contract amount of$18,672,548.00 is reduced by the net of$850,689.90
to the new contract amount of$17,821,858.10. Project No.DR1PO4.
Background:
Pursuant to Resolution No. 18-231, the City of Port Arthur adopted the 2018 Disaster Recovery and
Resiliency Plan(DRRP) for recovery activities following Hurricane Harvey. The City of Port Arthur,
as part of the DRRP recovery activities, identified flood and drainage problems within the community
of Stonegate. Pursuant to Resolution No. 20-021, Stuart Consulting Group, of Houston, Texas, was
approved to provide design specifications and a final bid package for the Stonegate Drainage
Improvement Project.
The Stonegate Drainage Improvement Project was prepared for bidding. The Purchasing Department
advertised competitively qualified bidders on September 9, 2023 and September 15, 2023 under Bid
Number P23-069. Bids were opened on Wednesday, October 11,2023,with three vendors responding,
Allco, LLC, of Beaumont, Texas; BDS Constructors, LLC, of Vidor, Texas; and Brystar Contracting,
Inc., of Beaumont, Texas. After review by the Public Works Engineering Division staff, it was
determined that Brystar Contracting, Inc., of Beaumont, Texas,provided the lowest responsible bid for
$18,672,548.00. Pursuant to Resolution No. 23-561, the City of Port Arthur's City Council approved
awarding the Stonegate Drainage Improvement Project to Brystar for the amount of$18,672,548.00.
"Remember,we are here to serve the Citizens of Port Arthur"
444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
Pursuant to Resolution No. 24-060, the City of Port Arthur's City Council gave approval for the City
Manager to enter into a professional engineering services contract for construction management and
value engineering with Chica&Associates,Inc., (Chica)of Beaumont,Texas for the Stonegate Project.
City staff, Chica, and Brystar performed value engineering on the project saving a total amount of
$1,638,750.00. The amount of$686,859.00 was then added for lowering the culvert boxes by one foot(1')
at the golf course due to pipeline conflicts. Also, $101,201.10 was added for reinforced concrete liner at the
bottom of the ditch because of water table issues. The original contract amount of$18,672,548.00 is reduced
by the net of$850,689.90 to the new contract amount of$17,821,858.10 for Change Order No. 1.
Budget Impact:
Funds from the Hazard Mitigation Grant Account No. 154-00-000-8515-00-10-000 ($12,678,536.25) and
Community Development Block Grant DR Account No. 148-00-000-8515-00-10-000($3,522,416.69)will not
be impacted. Project No.DR1PO4.
Recommendation:
It is recommended that the City of Port Arthur's City Council approve PR No. 23721 authorizing the City
Manager to accept Change Order No. 1, from Chica& Associates, Inc., of Beaumont, Texas, that reduces the
original contract amount of $18,672,548.00 by the net of $850,689.90 to the new contract amount of
$17,821,858.10.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
ow-
PR No.23721
4/12/2024 mje
Page 1 of 5
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN
THE CITY OF PORT ARTHUR AND BRYSTAR CONTRACTING,
INC. OF BEAUMONT, TEXAS FOR THE STONEGATE DRAINAGE
IMPROVEMENT PROJECT FOR VALUE ENGINEERING SAVINGS
THAT REDUCES THE CONTRACT BY $850,689.90 AND
MODIFIES AREAS OF THE PROJECT ON JIMMY JOHNSON
BOULEVARD. FUNDS AVAILABLE IN THE HAZARD
MITIGATION GRANT ACCOUNT NO. 154-00-000-8515-00-10-
000 AND THE COMMUNITY DEVELOPMENT BLOCK GRANT DR
ACCOUNT NO. 148-00-000-8515-00-10-000 ARE NOT
IMPACTED. PROJECT NO. DR1PO4.
WHEREAS, pursuant to Resolution No. 18-231, the City of Port Arthur adopted the 2018
Disaster Recovery and Resiliency Plan (DRRP) for recovery activities following Hurricane Harvey;
and,
WHEREAS, the DRRP included mitigation planning and investment in infrastructure to
rebuild/repair streets, utilities, public facilities, water, sewer, and drainage in addition to
identifying areas in the 100 year flood zone frequently flooded during previous storms or
significant rain events; and,
WHEREAS, the community of Stonegate was selected as an area that has experienced
significant flooding due to rain events, flash flooding and drainage related issues; and,
WHEREAS, pursuant to Resolution No. 20-021, Stuart Consulting Group of Houston,
Texas, was approved to provide design specifications and a final bid package for the Stonegate
area; and,
PR No.23721
4/12/2024 mje
Page 2 of 5
WHEREAS, the Stonegate Drainage Improvement Project was let for bidding under Bid
Number P23-069 on September 9, 2023 and September 16, 2023, by the Purchasing
Department; and,
WHEREAS, three (3) bids were received from Allco, LLC, of Beaumont, Texas; BDS
Constructors, LLC, of Vidor, Texas; and Brystar Contracting, Inc., of Beaumont, Texas; and,
WHEREAS, bids were opened, and evaluated by the Purchasing Department, the Public
Works staff, and Stuart Consulting Group, on Wednesday, October 11, 2023, with Brystar
Contracting, Inc., of Beaumont, Texas being the lowest qualified bidder for $18,672,548.00;
and,
WHEREAS, pursuant to Resolution No. 23-561, the Port Arthur City Council authorized
the City Manager to enter into an agreement with Brystar Contracting, Inc., (Brystar) of
Beaumont, Texas, for $18,672,548.00 for the Stonegate Drainage Improvement Project; and,
WHEREAS, pursuant to Resolution No. 24-060, the Port Arthur City Council authorized
the City Manager to enter into a professional engineering services contract for construction
management and value engineering with Chica & Associates, Inc., of Beaumont, Texas for the
Stonegate Project; and,
WHEREAS, City staff, Chica, and Brystar performed value engineering on the project
saving a total amount of $1,638,750.00. The amount of $686,859.00 was then added for
lowering the culvert boxes by one foot (1') at the golf course due to pipeline conflicts. Also,
$101,201.10 was added for reinforced concrete liner at the bottom of the ditch because of water
table issues, see Exhibit A; and,
PR No.23721
4/12/2024 mje
Page 3 of 5
WHEREAS, Change Order No. 1 reduces the original contract amount of $18,672,548.00
by the net of $850,689.90 to the new contract amount of $17,821,858.10; and,
WHEREAS, approval of PR No. 23721 authorizing the City Manager to execute Change
Order No. 1 with Brystar Contracting, Inc. of Beaumont, Texas, for value engineering savings
of $1,638,750.00; adding $686,859.00 for lowering the culvert boxes by one foot (1') at the golf
course due to pipeline conflicts; and adding $101,201.10 for reinforced concrete liner to the
bottom of the ditch because of water table issues, reducing the original contract amount of
$18,672,548.00 by the net of $850,689.90 to the new contract amount of $17,821,858.10, is
herein deemed an appropriate action; now, therefore;
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, the City Manager of the City of Port Arthur is hereby authorized to execute Change
Order No. 1 with Brystar Contracting, Inc. of Beaumont, Texas, for value engineering savings
of $1,638,750.00; adding $686,859.00 for lowering the culvert boxes by one foot (1') at the golf
course due to pipeline conflicts; and adding $101,201.10 for reinforced concrete liner to the
bottom of the ditch because of water table issues, reducing the original contract amount of
$18,672,548.00 by the net of $850,689.90 to the new contract amount of $17,821,858.10; and,
THAT, funding available in the Hazard Mitigation Grant Account No. 154-00-000-8515-
00-10-000 ($12,678,536.25) and Community Development Block Grant DR Account No. 148-00-
000-8515-00-10-000 (3,522,416.69); Project No. DR1PO4, will not be impacted; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
1
PR No.23721
4/12/2024 mje
Page 4 of 5
READ, ADOPTED AND APPROVED this the day of
A.D., 2024, at a of the City Council of the City of Port Arthur, Texas, by
the following vote: Ayes: Mayor:
Councilmembers:
Noes:
Thurman Bill Bartle
Mayor
ATTEST:
Sherri Bellard
City Secretary
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION
Y/41(2/1144--
a es Black Ron Burton, CPM
erim City Attorney City Manager
PR No.23721
4/12/2024 mje
Page 5 of 5
APPROVED AS TO AVALIABILITY OF FUNDS:
1 die,
Lynda "Lyn Boswell, M.A., ICMA-CM
Director of Finance
John Cannatella, PE
City Engineer
Clifton Williams, CPPB
Purchasing Manager
EXHIBIT A
CITY OF PORT ARTHUR
Public Works Engineering
DATE: APRTP 6,2024
PROJECT: STONEGATE DRAINAGE IMPROI
OWNER: CITY OF PORT ARTHUR
CONTRACTOR: BRYSTAR
CHANGE ORDER NO.:01
THE FOLLOWING CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE HEREBY MADE:
Adjust the Estimated Quantities to reflect the Actual Quantities used in the completion of the project:
Item Hem Item Description Unit Original
Unit Price Original Amount New Quantity New Amount
No. Code Quantity $AddRlalnl
EXCAVATION
30 CHANNEL CY 5,350 $ 22.00 $ 117,700.00 5,715 $ 125,730.00 $ 8,030.00
40 PONDS CY 100,000 $ 28.00 $ 2,800,000.00 80,000 $ 2,240,000.00 $ (560,000.00)
BASE MATERIAL
190 CEMENT TREAT(NEW BASE)(6") SY 20,000 $ 38.00 $ 760,000.00 0 $ - $ (760,000.00)
• NEW FLEX BASE(NEW BASE)(6") 5,1 0 $ 30.00 20,000 $ 600,000.00 $ 600,000.00
350 CONC BOX CLUV)(4FT X 2FT) LF 280 $ 650.00 $ 182,000.00 336 $ 218,400.00 $ 36,400.00
380 CONC BOX CLUV)(EFT X 4FT) LF 270 $ 1,100.03 $ 297,000.00 150 $ 165,000.00 $ (132,000.00)
400 CONC BOX CLUV)(7FT X 5F1) IF 66 $ 1,500.00 $ 99,000.00 0 $ - $ (99,000.00)
SEEDING
670 HYDROMULCH SEEDING AC 15 $ 2,800.00 $ 42,000.00 16.24 $ 45,472.00 $ 3,472.00
680 BLOCK SODDING SY 6,000 $ 14.00 $ 84,000.00 0 $ - $ (84,000.00)
RIP RAP
720 RIP RAP(STONE COMMON)(18 IN) TON 725 $ 125.00 $ 90,625.00 695 $ 86,875.00 $ (3,750.00)
NEW LOWER 442 M8C 1'(168 LF) LS $ 29,816.00 1 $ 29,816.00 $ 29,816.00
Extra Excavation
Extra Rock Below Box Culverts
Additional 1'of Headwall
&Wingwall Height
NEW LOWER 6x4 BOX CULVERT 15 $ 9,141.00 1 $ 9,141.00 $ 9,141.00
AT CART PATH 1'(15 LF)
Extra Excavation
Extra Rock Below Box Culvert
Additional l'of Headwall
&Wingwall Height
NEW CONCRETE LINER PER ONSfTE LS $ 101,201.10 1 $ 101,201.10 $ 101,201.10
DISCUSSION SPRIL 3,2024
Original Bid Quantity=175 S.Y. $ (850,689.90)
New Quantity 456.91 S.Y. -
Additional Quntfy=481.91 @$210
SUB-TOTALS $ 4,472,325.00 $ 3,621,635.10 $ (850,611910)
ORIGINAL CONTRACT DEDUCT NEW CONTRACT
AMOUNT $(SAVINGS) AMOUNT
$ 18,672,548.00 • $ 17,821,858.10
ORIGINAL CONTRACT AMOUNT: $ 18,672,548.00
NET FROM PREVIOUS CHANGE ORDERS: $ -
TOTAL AMOUNT OF THIS CHANGE ORDER NO.1: 5 185Q6`e4.90)
PERCENT OF THIS CHANGE ORDER NO.1: -4.56%
TOTAL PERCENT CHANGE ORDERS NO.1: -4.56%
FINAL CONTRACT AMOUNT: $ 17,821,858.10
(NO)CALENDAR DAYS HAVE BEEN ADDED TO THE CONTRACT BY CHANGE ORDER NO.1
NOTICE TO PROCEED DATE:3/14/2024
NUMBER OF CALENDAR DAYS FOR PROJECT:650
ORIGINAL CONTRACT COMPLETION DATE.12-24-2025
NUMBER OF ADDITIONAL CALENDAR DAYS REQUESTED:0
NEW CONTRACT COMPLETION DATE:(WEDNESDAY)12-24-2025
PREPARED BY: APPROVED BY:
Robert K.Balfour,P.E.,Chin&Associates,Inc. John Cannatella,P.E.,City Engineer
APPROVED BY: APPROVED BY:
Brystar,Representative Ron Burton,City Manager