HomeMy WebLinkAboutPR 23638: PAT, CHANGE ORDER NO. 1 FOR DELK CONSTRUCTION, INC. City of Port Arthur Transit Department Memorandum To: Ronald Burton,City Manager From: Ivan Mitchell,Transit Director Date: April 5,2024 Re: P.R 23638—A resolution authorizing the City Manager to execute on behalf of PAT, change order No. 1 for De&Construction,Inc. Nature of Request: Authorize the City Manager to execute change orders No.1 in the amount of $6,000.00 to Delk Construction,Inc.for Port Arthur Transit's(PAT)new storage building. Background: Pursuant to Resolution No. 22-470, City Council awarded a contract to Delk Construction,Inc.to construct PAT's new storage building in the amount not to exceed$185,000. As construction ensued, design and material adjustments have occurred resulting in additional expenses and savings. This resulted in a net contract increase of$6,000.00 for a new contract amount of$191,000.00. A detailed breakdown of change order No. 1 is provided in the packet Recommendation: It is recommended that the City Council approve proposed P.R. 23638. This resolution would authorize the City Manager to execute on behalf of PAT change order No. 1. Budgetary/Fiscal Effect:Funding to pay for this capital project is budgeted in PAT's capital budget. P.R. No. 23638 4/5/2024 IM RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 FOR THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND DELK CONSTRUCTION, INC. OF NEDERLAND, TEXAS INCREASING THE CONTRACT AMOUNT BY $6,000.00 TO A NEW CONTRACT AMOUNT OF $191,000.00 FOR PORT ARTHUR TRANSIT'S STORAGE BUILDING CONSTRUCTION; FUNDS AVAILABLE IN ACCOUNT 401-70-530-8512-00-60-000, PROJECT TR2035B.CAP.BUI WHEREAS, pursuant to Resolution No. 22-470, the City Council authorized the City Manager to enter into a contract with Delk Construction, Inc. for PAT's new storage building in an amount not to exceed$185,000.00;and, WHEREAS, PAT is recommending that the City of Port Arthur by its City Manager approve Change Order No. 1 for a net project increase of $6,000.00 for a new contract amount not to exceed$191,000.00,as delineated in Exhibit"A". NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the facts and opinions in the preamble are true and correct. THAT, the City Manager is hereby authorized to execute on behalf of PAT, Change Order No. I (Exhibit"A"). THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ,ADOPTED AND APPROVED this day of A.D. 2024 at a Regular Meeting of the City of Port Arthur,Texas by the following vote: AYES: Mayor: Councilmembers: NOES: P.R.No. 23638 4/5/2024 IM Thurman Bill Bartie,Mayor ATTEST: Sherri Bellard, City Secretary AP =fr :TL lame M. Black,Interim City Attorney APPROVED FOR ADMINISTRATION: APPROVED AS TO AVAILABILITY OF FUNDS: 401-70-530-8512-00-60-000 2 s,0-7,6 604 _a Ronald Burton, CPM Lynda Boswell City Manager Director of Finance ' I ` , 114, Clifton illiams,CPPB Ivan Mitchell Purchasing Manger Transit Director P.R. No.23638 4/5/2024 IM Exhibit "A" CHANGE OWNER ORDER ARCHITECT X CONTRACTOR FIELD OTHER PROJECT: Transit Station Storage Building CHANGE ORDER NUMBER: 1 (name,address) 444 4th Street Port Arthur,Texas 77641 DATE: 1-May-23 TO CONTRACTOR: Delk Construction,Inc. ARCHITECTS PROJECT NO. 21-0632 (name,address) P.O. Box 1424 Nederland,Texas 77627 CONTRACT DATE: 19-Dec-22 CONTRACT FOR: Transit Station Storage Bldg. The Contract is changed as follows: Add to relocate electrical lines $6,000.00 Not valid until signed by the Owner,Architect and Contractor The original(Guaranteed Maximum Price)was........................... $ 185,000.00 Net change by previously authorized Change Orders......... ......... ...... .................... $ 0.00 The(Guaranteed Maximum Price)prior to this Change Order was $ 185,000.00 The(Guaranteed Maximum Price)will be increased 0.00 by this Change Order In the amount of. , $ 6,000.00 The new(Guaranteed Maximum Price)including this Change Order will be $ 191,000.00 The Contract Time will be unchanged by(revised due to delays )days. The date of Substantial Completion as of the date of this Change Order therefore is urchanged. NOTE: This Summery does Oct reflect changes in the Contract Sum,Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive. AHUitT J CONTRACTOR OWNER Southtex Surveyors&Engineers ()ELK CONSTRUCTION,INC City Of Port Arthur 3737 Doctors Driv P.O.Box 1424 444 4th Street Port Arthur TEx s 77642 Nederland.Texas 77827 Port Arthur,Texas 77641 By By 45 DATE DATE