Loading...
HomeMy WebLinkAboutPR 23783: RATIFY THE EMERGENCY REPAIR FOR CHANGE ORDER NO. 4 OF MAIN WASTEWATER PLANT (WWTP) IMPROVEMENT PROJECT }, City of ort rthu�_ Texas INTEROFFICE MEMORANDUM WATER UTILITY DEPARTMENT-ADMINISTRATION Date: May 23, 2024 To: The Honorable Mayor and City Council Through: Ronald Burton, C.P.M., City Manager From: Calvin Matthews, P.E., Water Utilities Director RE: PR No. 23783 —Ratify the Emergency Repair for Change Order No. 4 of Main Wastewater Plant(WWTP) Improvement Project Introduction: This agenda item is seeking the Council's approval to ratify Change Order No. 4 for emergency repair with ALLCO, LLC for the Main Wastewater Treatment Plant (WWTP) Improvement Project with an increased budget amount of$389,801.00 to the new updated contract amount of$67,840,265.43. Background: Resolution No. 22-147 awarded the Main Wastewater Plant(WWTP) Improvement Project to ALLCO, LLC of Beaumont, Texas for the total amount of$73,643,227.00. The construction phase is managed by Freese&Nichols, lnc. On August 2, 2022, Resolution No. 22-329, approved Change Order No. 1 for value engineering performed by Freese&Nichols, Inc., ALLCO, LLC, Golden Triangle Consulting Engineers, and the City of Port Arthur staff in the deduction amount of$6,234,049.00. On December 20, 2022, Resolution No. 22-586, approved Change Order No. 2 including, Primary Clarifiers subgrade stabilization, Drying Beds demo, Demo and Remove CSS, Helical Piles, and Brentwood PVC TF Media price increase and reduction for the removal of VE Lighting Package, use of bank sand for pipe bedding, and remove Admin Building improvements in the deduction amount of$73,564.57 and 75-day time extension with a final project end date of December 17, 2026. On December 19, 2023, Resolution No. 23-556, approved Change Order No. 3 for an increased amount of$114,851.00 to replace 4 Trickling Filter Effluent Butterfly Valves with Slide Gates and add an expansion joint to Aeration Basin Buttress Wall. Change order No. 4 is an emergency repair to prevent the comple6 failure of the 30" force main from the lift station for an increased contract amount of $389,801.00 for additional piping to reach the existing 30" force main and to reroute the discharge piping of the existing 10" pump at the Main Outfall Lift Station to the existing 36" force main. In addition, to install a line stop at the 36" DI influent pipe to reroute the flow through 440 LF of 24" HDPE. Budget Considerations: The original contract price is $73,643,227.00 Change Order No. 1 decreased the contract amount by $6,234,049.00 Change Order No. 2 decreased the contract amount by $73,564.57 Change Order No. 3 increased the contract amount by $114,851.00 Proposed Change Order No. 4 for $389,801.00 will increase the new total contract amount to $67,840,265.43. The funding is available in Account No. 405-40-000-8516-00-00-000, Project No. WS0023 Recommendation: Recommend City Council approve PR No. 23783 to authorize the City Manager to ratify the emergency repair of Change Order No. 4 as per the work detailed in the attached Memo dated April 5, 2024 by Freese &Nichols, Inc.,as described/outlined above. PR No. 23783 5/23/2024 cm Page 1 of 3 RESOLUTION NO. A RESOLUTION RATIFYING THE CITY MANAGER'S DECISION FOR THE EMERGENCY REPAIR (CHANGE ORDER NO. 4) TO THE MAIN WASTEWATER TREATMENT PLANT IMPROVEMENT PROJECT WITH ALLCO, LLC OF BEAUMONT, TEXAS, FOR AN INCREASE AMOUNT OF $389,801.00 TO A NEW TOTAL CONTRACT AMOUNT OF $67,840,265.43 FUNDING IS AVAILABLE IN ACCOUNT NO. 405-40-000-8516-00-00-000, PROJECT NO.WS0023. WHEREAS, the City Council approved Resolution No. 22-147, awarding the Main Wastewater Treatment Plant Rehabilitation project to ALLCO, LLC of Beaumont, Texas for the total amount of$73,643,227.00; and, WHEREAS, on August 2, 2022, Resolution No. 22-329, approved Change Order No. 1 to reduce the contract amount by $6,234,049.00 for Value Engineering performed by Freese & Nichols, Inc., ALLCO, LLC, Golden Triangle Consulting Engineers and the City of Port Arthur staff for a new contract amount of$67,409,178.00; and, WHEREAS, on December 20, 2022, Resolution No. 22-586, approved Change Order No. 2 for a decreased amount of$73,564.57 including, Primary Clarifiers subgrade stabilization, Drying Beds demo, Demo and Remove CSS, Helical Piles, and Brentwood PVC TF Media price increase and reduction for the removal of VE Lighting Package, use of bank sand for pipe bedding, and remove Admin Building improvements to a new contract amount of $67,335,613.43 and add 75-day time extension with a final project end date of December 17, 2026; and, WHEREAS, on December 19, 2023, Resolution No. 23-556, approved Change Order No. 3 for an increased amount of $114,851.00 to replace 4 Trickling Filter Effluent Butterfly Valves with Slide Gates and add an expansion joint to Aeration Basin Buttress Wall, to a new contract amount of$67,450,464.43; and, PR No.23783 5/23/2024 cm Page 2 of 3 WHEREAS, Change Order No. 4 is ratifying the emergency repair on the 30"force main for an increased amount of $389,801.00 by installing additional piping with a 10" pump to reroute the force main, 36" Line Stop, and HDPE Bypass pipping, to a new contract amount of $67,840,265.43. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT,the facts and opinions in the preamble are true and correct; and, THAT, the City Council hereby ratifies the City Manager's decision for emergency repair (Change Order No. 4) as per the Memo dated April 5, 2024 (Attachment "A") for a cost of $389,801.00 with ALLCO, LLC of Beaumont, Texas for the Main WWTP Improvements project, to a new projected budgetary amount of$67,840,265.43; and, THAT, funding is available in Account No. 405-40-000-8516-00-00-000, Project No. WS0023; and, THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED THIS day of , 2024 at a Regular Meeting of the City Council of the City of Port Arthur, Texas,by the following vote: AYES: Mayor Councilmembers NOES: PR No. 23783 5/23/2024 cm Page 3 of 3 Thurman Bill Bartie Mayor ATTEST: APPROVED AS TO FORM: Sherri Bellard J M. Black City Secretary I rim City Attorney APPROVED FOR ADMINISTRATION: APPROVED AS FOR AVAILIBILITY OF FUNDS: a� bt c 6 p;vitit Ronald Burton, C Lynda(Lyn) Boswell, MA, I A-CM City Manager Director of Finance Li C ti Calvin Matthews, P.E. C _ on E. Williams, Jr., CPPB Water Utilities Director Purchasing Manager ATTACHMENT A (MEMO DATED APRIL 05,2024) ,t /pm FREESE 11200 Broadway St.,Suite 2320 + Pearland,Texas 77584 + 832-456-4700 + FAX 817-735-7491 April 5,2024 Calvin Matthews, PE Director of Water Utilities City of Port Arthur Texas 444 4th Street Port Arthur,TX 77640 Re: Project No. R15056 Port Arthur Main WWTP Improvements:Change Order No.004 Dear Mr. Matthews: Included with this letter is Change Order No.004 for the above referenced project.This letter is to serve as a narrative for the items included in this Change Order No.005 with supporting documentation attached. Item No. 1:Additional Piping and 10"Pump Reroute @ MOLS After Allco completed the exploratory excavations at the Main Outfall Lift Station (MOLS), it was realized that the underground piping was not per the record drawings that the design was based on along with discovered two underground concrete junction boxes. These unforeseen conditions require additional material to route the bypass header manifold piping around the underground concrete boxes and additional piping to reach the existing 30" force main.This line item also includes the cost to reroute the discharge piping of the existing 10"Gorman Rupp pump that was at the MOLS to the existing 36"Force Main through the dry well. Total Cost:$246,607.00 Additional Days:0 Calendar Days Item No.2:36" Line Stop and HDPE Bypass Piping @ WWTP The IFC plans called for the 36"Force Main from the MOLS to be temporarily bypassed through the existing 30" Ductile Iron Pipe. After completing the exploratory excavations at the MOLS it was realized the 30" Force Main is Bar Wrapped Concrete Cylinder Pipe, not Ductile Iron, and could not handle the capacity of the bypass pumps. In order to continue the work at the WWTP,a line stop had to be installed at the 36" DI influent pipe to reroute the flow through 440 LF of 24" HDPE. Total Cost:$143,194.00 Additional Days:0 Calendar Days To summarize,this Change Order No.004 has an overall cost increase of$389,801.00 and 0 additional calendar days to the contract time.There will be a subsequent change order for the additional days incurred for these changes. I hope the above narrative, along with the included supporting documentation, provides adequate information to be able to process this Change Order. Please don't hesitate to reach out to me if you need any further explanation or backup documentation. Sincerely, Rami Abusheikh, P.E. Construction Manager cc:Jess Liao,Hani Tohme,Murali Erat,Matt Cartwright PTR22379 T:\4.0 CONSTRUCTION\4.40 Contract Mod\4.43 Chg Orders\Change Order No.4 Change Order No.4 Project Port Arthur Main WWTP Improvements Project Number Owner City of Port Arthur R15056 Contractor Allco,LLC TX 875 Construction Manager Rami Aubhseikh,P.E. PTR22379 Design Professional Murali Erat,P.E. PTR22380 CoPA Account No. 169-07-015-8516-00-40-000;404-40-000-8516-00-00-000 Design Professional ARP002-GRE-WWT; TW-0003-CON Change Order No. 004 Date 3/27/2024 Item Description Additional Days Change Amount 1 Differing subsurface conditions @ MOLS 0 $ 246,607.00 2 36"DI Influent Pipe Linestop 0 $ 143,194.00 4 / $ 6 7 8 9 / $ Net Change in Contract Price this Change Order $ 389,801.00 Net Change in Contract Time this Change Order 0 Days The compensation in this Change Order is the full, complete, and final compensation for all costs Contractor may incur because of or relating to this change whether said costs are known, unknown,foreseen, or unforeseen at this time, including without limitation, any cost for delay, extended overhead, ripple or impact cost, or any other effect on changed or unchanged Work because of this Change Order. The changes in Contract Times are the complete and final adjustments for impacts to the ability of Contractor to complete the Work within the Contract Times and are the only adjustments to which Contractor is entitled.All terms and provisions of the Contract Documents remain in effect except as specifically modified by this Change Order. Original Contract Amount: $ 73,643,227.00 Net from Previous Change Orders: $ (6,192,762.57) Total Amount of This Change Order: $ 389,801.00 Percent Change in Contract Amount of this Change Order: 0.53% Total Percent Change from Oriignal Contract Amount to Date: -7.88% New Contract Amount: $ 67,840,265.43 Origin)Contract Duration: 1,580 Calendar Days Additional Contract Days from Previous Change Orders: 75 Calendar Days Additional Contract Days this Change Order: 0 Calendar Days Revised Contract Time: 1,655 Calendar Days Original Final Completion Date: 10/3/2026 Previous Final Completion Date: 12/17/2026 Revised Final Completion Date: 12/17/2026 Change Order No.4 Page 1 of 2 Change Order No.4 Recommended by Design Professional: Recommended by Construction Manager: Murali Erat, PE Date Rami Abusheikh, PE Date (Freese and Nichols,Inc.) (Freese and Nichols,Inc.) Approved by Contractor: Approved by Owner: 67://// _ 9 Brandon Harrison Date Calvin Matthews, PE Date Vice-President Director of Water Utilities Allco, LLC City of Port Arthur Change Order No.4 Page 2 of 2 Cm•of (rtItu'f 7, ;ts INTEROFFICE MEMORANDUM Date: January 25,2024 To: Ronald Burton, City Manager From: Calvin Matthews, P.E. Water Utilities Director RE: Emergency Repair on Main Wastewater Treatment Plant(WWTP) Improvement Project- Main Outfall Lift Station(MOLS) Change Due to the field conditions varying from the historical data on the Main Wastewater Plant Improvement Project,the contractor found the critical condition of the existing sewer force main which will cause the completed failure on MOLS. The emergency changes are needed immediately including an additional 30" ductile iron pipe and fittings underground,to construct the bypass pumping manifold, additional fittings to build the 30" line around the discovered junction boxes, remove failed pump No. 3 from the dry-well and pipe temporary 10" Gorman Rupp pump to discharge header to maintain lift station capacity, a special connection must be made at the lift station site and the wastewater treatment plant site, the 24" bypass, and 440 LF of 24"HDPE(Attachment). The changes will also result in the construction time extension. The total expenditure for the repairs was expected to be around$389,801.00 and will be charged under the CIP Account No.405-40-000-8516-00-00-000, No.WS0023. I,Pamela Langford on behalf of Ronald Burton,hereby approve the emergency repairs by ALLCO, LLC. AA-0 (._.}• a.)1-0 Pamela Langford Assistant City Manager "Remember, we are here to serve the Citizens of Port ,Arthur" ' Design Build A ll C 0 Design Management General Contactor Corporate Office—P.O.Box 3684,Beaumont,TX 77704 Phone 409.860.4459 Fax 409.860.3857 Central Texas—P.O.Box 11807,College Station,TX 77842 Phone 979.260.1000 Fax 979-450-7310 Houston Office—5065 Westheimer,Ste.1150,Houston,TX 77056 Phone 713.222.1331 Fax 713.936.4858 January 23,2024 Attn: Calvin Matthews, P.E. City of Port Arthur 444 4th Street P.O. Box 1089 Port Arthur,Texas 77640 Re: Port Arthur WWTP—MOLS changes Dear Calvin: Please find below, a description for the required changes to the project due field conditions varying from the historical data: 1. The existing 30"force main is not located as shown on the contract drawings. It also is constructed of concrete cylinder pipe, not ductile iron as shown. This difference requires additional 30"ductile iron pipe and fittings underground, in order to construct the bypass pumping manifold. 2. There was also found, 2 large existing buried concrete junction boxes not shown on the plans. This required additional fittings to build the 30" line around the junction boxes. 3. Removed failed pump No. 3 from drywelI and piped temporary 10" Gorman Rupp pump to discharge header to maintain lift station capacity. 4. In order to connect the 30"ductile iron pipe to the concrete cylinder,a special connection had to be made at the lift station site and the wastewater treatment plant site. 5. Upon start up of the bypass pumps this week, a rupture occurred on the concrete cylinder pipe in the road leading to the lift station. Upon investigation, it has been found that the 30" concrete cylinder pipe force main is not structurally sound and will not be able to be used for bypass pumping as per the contract drawings. The pricing for the above work is as follows: Material $ 143,921.00 Labor 33,388.00 Payroll Taxes 16,026.00 Equipment 21,106.00 $214,441.00 Overhead& Profit 32,166.00 $246,607.00 ' Design Build A �C O Construction Management General Contactor r Corporate Office—P.O.Box 3684,Beaumont,TX 77704 Phone 409.860.4459 Fax 409.860.3857 Central Texas—P.O.Box 11807,College Station,TX 77842 Phone 979.260.1000 Fax 979-450-7310 Houston Office—5065 Westheimer,Ste.1150,Houston,TX 77056 Phone 713.222.1331 Fax 713.936.4858 Mr. Calvin Matthews, P.E. City of Port Arthur Page 2 As discussed on the jobsite, the revised plan was to install a 36" line stop and a 36"x 18" hot tap, in order to bypass to allow for 2 tie-ins. We have found that a 36" line stop has a built-in 24" bypass, so a separate hot tap will not be required. We have included 440 LF of 24" HDPE to be run on top of the ground to the existing headworks. The pricing for this work is as follows: Material $ 41,059.00 Labor 11,120.00 Payroll Taxes 5,338.00 Subcontract—line stop 55,000.00 Equipment 12,000.00 $ 124,517.00 Overhead& Profit 18,677.00 $ 143,194.00 Let me know if you have any questions. Sincerely, ALLCO LLC Egitneti Keith Burrell