HomeMy WebLinkAboutPR 15539: ARCENEAUX & GATES CWSRF TWDB PROJECTSPUBLIC WORKS DEPARTMENT
COUNCIL ACTION MEMO
TO Stephen B. Fitrgibbons, City Manager
FROM Ross E. Blackketter, P.E., Director of Public Works
SUB]ECT P.R. #15539 - Chg of Scope for Arceneaux & Gates for CWSRF TWDB Projects
DATE 28 September 2009
RECOMMENDATION:
I recommend that the City Council approve Proposed Resolution No. 15539, revising the scope
of the contract with Arceneaux & Gates Consulting Engineers, Inc. to include additional design
phase services for the Sanitary Sewer Rehabilitation - CWSRF TWDB Projects, increasing the
budget for these services by $56,500 to a total of $421,500.
BACKGROUND:
In Resolution 09-238, the City entered into a contract with Arceneaux & Gates Consulting
Engineers, Inc. (Arceneaux) for the engineering design services for sanitary rehabilitation that
are to be funded by a Texas Water Development Board Clean Water State Revolving Fund grant
from the American Reinvestment and Recovery Act (ARRA).
Because of the very short time frame to prepare plans and specifications, Arceneaux incurred
additional expenses involved in preparing the application, bidding the construction projects,
coordinating with the TWDB, etc. This additional work is for an amount of $56,500, bringing
the contract to a total of $421,500.
BUDGETARY/FISCAL EFFECT:
Funding is available in Project 426016, 426-1625-532.54-00.
EMPLOYEE/STAFF EFFECT:
None.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 15539, revising the scope
of the contract with Arceneaux & Gates Consulting Engineers, Inc. to include additional design
phase services for the Sanitary Sewer Rehabilitation - CWSRF TWDB Projects, increasing the
budget for these services by $56,500 to a total of $421,500.
Ross E. Blackketter, P.E.
Director of Public Works
REB/reb
Z: \engineer\Documents\Cams\A&G-ChgofScope-ARRA. doc
P.R. No. 15539
09/28/09 reb
RESOLUTION NO.
A RESOLUTION AUTHORIZING ADDITIONAL SERVICES FOR THE
CONTRACT APPROVED JUNE 2, 2009 BETWEEN THE CITY OF
PORT ARTHUR AND ARCENEAUX & GATES CONSULTING
ENGINEERS, INC. OF PORT ARTHUR, TEXAS FOR PROFESSIONAL
SERVICES RELATED TO THE TWDB CWSRF (ARRA) GRANT
INCREASING THE BUDGET FOR THIS ENGINEERING SERVICE BY
$56,500 TO A TOTAL OF $421,500. ACCOUNT 426-1625-532.54-
00, PROJECT 426016.
WHEREAS, on June 2, 2009, the City Council of the City of Port Arthur
---mot ux a es onsu ing ngmeers o o ur;
Texas for professional services related to basic design services in the not-to-exceed
amount of $365,000; and,
WHEREAS, the Texas Water Development Board has awarded $15,080,000 to
the City of Port Arthur for sanitary sewer projects; and,
WHEREAS, Arceneaux & Gates Consulting Engineers, Inc. was instrumental in
completing the necessary plans and specifications in the short time available; and,
WHEREAS, Arceneaux & Gates Consulting Engineers, Inc. incurred additional
expenses for application preparation, preparing and bidding the construction projects,
coordinating with the TWDB, etc. in the amount of $56,500 (see Exhibit "A'~; now,
therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
P.R. No. 15539
Page 2
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, revising the scope of services to include the application preparation and
preparing and bidding the construction projects, increasing the budget for engineering
design and construction phase services by $56,50D to a total of $421,500 (Project
426016, 426-1625-532.54-00,), is herein approved, and the City Manager is authorized
to execute said Change of Scope as attached in Exhibit "B"; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of
the City Council.
READ, ADOPTED AND APPROVED this the _ day of A.D. 2009
at a meeting of the City of Port Arthur, Texas by the following vote:
Ayes: Mayor:
Counciimembers:
N
Mayor
Attest:
City Secretary
P.R. No. 15539
Page 3
APPROVED A~ TO FORM:
City Attorney ]~ ~ m.nJ ~e1nA{,~ ~,~~
APPROVED FOR ADMINISTRATION:
Stephen B. Ftrgibbons
City Manager
_~~(
Deborah Echols, C.P.A.
Director of Finance
~„~~ ~ e~
Ross E. Blackketter, P.E.
Director of Public Works
Z:\engineer\DocumenCs\Resolutions\PR15539.doa
EXHIBIT A
Ross Blackketter
From: Ron Arceneaux [ron@ageng.comj
Sent: Monday, September 28, 2009 9:20 AM
To: 'Ross Blackketter
Cc: 'Path Trahan';'Joe Wilson'
Subject: TWDB-CWSRF-ARRA
Ross,
The original contract maximum amount far design phase services including geotechnical is $365,000. The services we
provided that were not a part of the original scope included:
1. Grant application preparation
2. Engineering report -this also yielded additional design work for plant improvements not originally budgeted
(i.e. aeration basin)
3. Green Business Case
4. Environmental (Categorical Exclusions)
5. Acceleration of scheduled delivery of construction plans and application
6. Preparation of three contrails for pipe bursting/sliplining
7. Reproduction of grant application and supporting documents
8. Delivery to Austin
9. Additional responses to TWDB staff questions
10. Attendance at TW DB meeting for receipt of grant.
We request additional authorization up to $56,500.00 for these services provided. Let me know how to proceed.
Thanks.
ron arceneaux, pe, pls
arceneaux & gates inc.
3501 turtle creek drive
suite 102
port arthur, tx 77642
409.724.7888 0
409.724.1447 f
409.284.6517 c
EXHIBIT B
CHANGE OF SCOPE NO. 01
DATE: September 28, 2009
ORIGINAL AGREEMENT DATE: June 2, 2009
ARCENEAUX & GATES CONSULTING ENGINEERS, INC.
A&G PROJECT NUMBER: CPA-490
PROJECT DESCRIPTION: Sewer System Rehabilitation - CWSRF TWDB Projects
CHANGE IN SCOPE: Additional services to include Construction Phase Services.
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT amount: $365,000
CURRENT CONTRACT PRICE (adjusted by previous SCOPE CHANGE): $365,000
The Contract Amount due to this SCOPE CHANGE will be (increased/decreased) by:
$56, 500
The new CONTRACT AMOUNT including the SCOPE CHANGE will be: $421,500
CHANGE TO CONTRACT TERM:
ORIGINAL CONTRACT term: 150 days
CURRENT CONTRACT TERM (adjusted by previous SCOPE CHANGE): 150 days
The Contract Term due to this SCOPE CHANGE will be increased/decreased) by:
The new CONTRACT TERM including the SCOPE CHANGE will be: 150 days
ARCENEAUX & GATES CONSULTING ENGINEERS, INC.
Signature
Ronald J. Arceneaux. P.E.. R.P.L.S.
Printed Name
CITY OF PORT ARTHUR
Stephen B. Fitzgibbons
City Manager
Z:lengineer\Documents\Contracts\Change Orders44&G ScopeChg No. 1 28Sep09.doc