HomeMy WebLinkAbout(CMSR 2) Status Report Presentation_06 18 2024S T A T U S RE P O R T O NTHE O P E R A T I O N SCENTER’SRENOVATION S
J u n e 1 8 , 2 0 2 4
Building Overview
Constructed in 1965; Age: 59 years old
Some of the original fixtures still in
use
Flooded during Hurricane Harvey
Located in Flood Zone A (prone to 100-
year flood)
Operations Center - Western Entrance
Current Conditions -Offices
Current Conditions -Offices
Current Conditions -Offices
Current Conditions -Offices
Current Conditions -Men’s Restroom
Current Conditions -Men’s Restroom
Current Conditions -Men’s Restroom
Current Conditions -Exterior
Current Conditions -Exterior
Scope of
Work -
Summary
Long Architecture
Offices
Restrooms
Exterior
New wall, floor, & ceiling finishes
New louvers, vents, & blowers for
air circulation
Relocate water fountains from
restrooms to common area
Ice machine
Minor electrical work
Replace/install toilet & urinal
partitions
Automatic flush valves
Update plumbing fixtures
Make restrooms & showers ADA
compliant
New wall, floor, & ceiling finishes
Replace vanities
Replace double doors &
provide card reader
New pylon sign
Refinish/paint rocket
Repair awning
Repair broken concrete
Structural Report
Findings
Provided to
Architect for
Analysis and
Design
August 14, 2023
Presented RestroomOptions toOperations CenterStaff
January 12, 2024
Met with Long
Architecture to
finalize plans
April 19, 2024
Project Status
June 4, 2024
Plans
Anticipated receipt of final plans: Week of June 17, 2024
Outstanding Items
Architect is requesting a second opinion on floor
coating durability
Final MEP plans
Cost estimate
Next Steps
Bidding
Construction
Q U E S T I O N S