HomeMy WebLinkAbout(CMSR 2) Status Report Presentation_06 18 2024S T A T U S RE P O R T O NTHE O P E R A T I O N SCENTER’SRENOVATION S J u n e 1 8 , 2 0 2 4 Building Overview Constructed in 1965; Age: 59 years old Some of the original fixtures still in use Flooded during Hurricane Harvey Located in Flood Zone A (prone to 100- year flood) Operations Center - Western Entrance Current Conditions -Offices Current Conditions -Offices Current Conditions -Offices Current Conditions -Offices Current Conditions -Men’s Restroom Current Conditions -Men’s Restroom Current Conditions -Men’s Restroom Current Conditions -Exterior Current Conditions -Exterior Scope of Work - Summary Long Architecture Offices Restrooms Exterior New wall, floor, & ceiling finishes New louvers, vents, & blowers for air circulation Relocate water fountains from restrooms to common area Ice machine Minor electrical work Replace/install toilet & urinal partitions Automatic flush valves Update plumbing fixtures Make restrooms & showers ADA compliant New wall, floor, & ceiling finishes Replace vanities Replace double doors & provide card reader New pylon sign Refinish/paint rocket Repair awning Repair broken concrete Structural Report Findings Provided to Architect for Analysis and Design August 14, 2023 Presented RestroomOptions toOperations CenterStaff January 12, 2024 Met with Long Architecture to finalize plans April 19, 2024 Project Status June 4, 2024 Plans Anticipated receipt of final plans: Week of June 17, 2024 Outstanding Items Architect is requesting a second opinion on floor coating durability Final MEP plans Cost estimate Next Steps Bidding Construction Q U E S T I O N S