HomeMy WebLinkAboutPR 23877: PORT ACRES DRAINAGE IMPROVEMENT PROJECT: CHANGE ORDER NO. 3 City of
o r t rlfru�
www.PortArthurTx.gov
INTEROFFICE MEMORANDUM
Date: August 16, 2024
To: The Honorable Mayor and City Council
Through: Ron Burton, City Manager
From: John Cannatella, City Engineer
RE: PR No. 23877: Port Acres Drainage Improvement Project: Change Order No. 3 from
Allco, LLC, of Beaumont, Texas, for the relocation of the sanitary sewer on 64th
Street,the addition of fifteen(15) calendar days, and the addition of 150 LF of
water lines. Project No. DR1P03A.
Introduction:
The intent of this Agenda Item is to seek Port Arthur City Council's approval for the City Manager to
execute Change Order No. 3 with Allco, LLC, (Allco) of Beaumont, Texas, for the relocation of the
sanitary sewer on 64th Street,the addition of fifteen(15) calendar days, and the addition of 150 LF of
water lines for the amount of$196,037.00. Project No. DR1P03A.
Background:
Pursuant to Resolution No. 18-231, the City of Port Arthur adopted the 2018 Disaster Recovery and
Resiliency Plan(DRRP)for recovery activities following Hurricane Harvey. The City of Port Arthur,
as part of DRRP recovery activities, identified flood and drainage problems within the community of
Port Acres that were in dire need of mitigation and repair. The Port Acres Project was let for bidding.
Pursuant to Resolution No.23-485,the City of Port Arthur's City Council approved awarding the Port
Acres Drainage Improvement Project to the lowest responsible bidder, which was Allco, LLC, of
Beaumont, Texas, for the amount of$34,891,106.81. City staff, Arceneaux, Wilson & Cole (AWC)
of Port Arthur, Texas, and Allco, LLC, of Beaumont, Texas, performed Value Engineering on the
project proposal lowering the contract price by $1,736,424.04 in order to keep it within budget.
Pursuant to Resolution No. 24-032, the City of Port Arthur's City Council approved Change Order
No. 1,that detailed the Value Engineering Breakdown from Allco, LLC,(Allco)of Beaumont,Texas,
that reduced the contract amount of$34,891,106.81 by$1,736,424.04,to the new contract amount of
$33,154,682.77.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
The Port Acres Drainage Improvement Project encountered additional costs due to necessary
relocations of existing infrastructure. These relocations are critical to ensure successful completion
and to avoid conflicts with the proposed drainage improvements. The additional costs for the project
are essential to achieve the project's goals and ensure durability. Given the current workload of City
personnel, outsourcing these tasks is the most feasible and efficient solution. To that end, a Field
Order No. 1 was issued to Allco ensuring that critical work would continue since work stoppage at
this juncture would be impractical, impact safety to the community, and incur excessive costs. Field
Order No. 1 informed the City Manager of the work that was required with the understanding that it
would go to the Port Arthur City Council in the form of Change Order No. 2.
Pursuant to Resolution No. 24-302,Change Order No. 2,approved by Port Arthur's City Council,was
submitted by Allco for the relocation of the sanitary sewer services and sewer main, and the addition
of eighteen (18) calendar days. Change Order No. 2 increased the contract amount by $159,385.00
from$33,154,682.77 to the new contract amount of$33,314,067.77. Additionally, Change Order No.
2 added eighteen (18) calendar days amending the original completion date of June 25, 2025 to the
new completion date of July 13, 2025.
Change Order No. 3 is being submitted by Allco for the installation of a sanitary sewer main on 64th
Street, the addition of fifteen (15) calendar days and the addition of 150 LF of water line relocations
for the amount of$196,037.00.
Change Order No. 3 proposes to increase the contract amount of 33,314,067.77 by $196,037.00 to the
new contract amount of$33,510,104.77. Additionally, Change Order No. 3 proposes to add fifteen
(15) calendar days to the original contract completion date of July 13, 2025, changing it to the new
contract completion date of July 28, 2025.
The cost associated with Change Order No. 3 addresses the elimination of obstructions in the designed
drainage system in Port Acres. The original bid allowed for services to pass through the new drainage
system due to limited finding. However, further investigation by the contractor revealed a greater
number of mains and services in conflict than initially expected. These conflicts could reduce the
project's efficiency and increase future maintenance needs.
Budget Impact:
Funds are available in Drainage System Account No. 307-21-055-8515-00-10-000. Project No.
DR1 P03A.
Recommendation:
It is recommended that the City of Port Arthur's City Council approve PR No. 23877 authorizing the
City Manager to accept Change Order No.3 from Allco,LLC,of Beaumont,Texas,for the installation
of a sanitary sewer main on 64th Street, the addition of fifteen (15) calendar days and the addition of
150 LF of water line relocations for the amount of$196,037.00. Project No. DR1P03A.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
PR No. 23877
8/16/2024 mje
Page 1 of 4
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 3 TO THE CONTRACT BETWEEN THE CITY OF PORT
ARTHUR AND ALLCO, LLC, OF BEAUMONT, TEXAS, FOR THE PORT ACRES
DRAINAGE IMPROVEMENT PROJECT, TO INSTALL SANITARY SEWER
MAIN ON 64TH STREET AND RELOCATE WATERLINES, EXTENDING THE
PROJECT TIME BY FIFTEEN (15) CALENDAR DAYS, AND INCREASING
THE CONTRACT AMOUNT BY $196,037.00 TO A NEW TOTAL OF
$33,314,067.77. FUNDING IS AVAILABLE IN DRAINAGE SYSTEM
ACCOUNT NO. 307-21-055-8515-00-10-000. PROJECT NO. DR1P03A.
WHEREAS, pursuant to Resolution No. 18-231, the City of Port Arthur (City) adopted
the 2018 Disaster Recovery and Resiliency Plan (DRRP) for recovery activities following
Hurricane Harvey; and,
WHEREAS, the DRRP included mitigation planning and investment in infrastructure to
rebuild/repair streets, utilities, public facilities, water, sewer, and drainage; and,
WHEREAS, the community of Port Acres was selected as an area that has experienced
significant flooding due to rain events, flash flooding and drainage related issues; and,
WHEREAS, pursuant to Resolution No. 20-023, the engineering firm of Arceneaux,
Wilson, & Cole, LLC (AWC) of Port Arthur, Texas, was approved to provide a master drainage
plan, provide design specifications, and provide construction management services for the Port
Acres Drainage Project; and,
WHEREAS, the Port Acres Drainage Improvement Project was let for bidding with Allco,
LLC, of Beaumont, Texas, being the lowest qualified bidder for $34,891,106.81; and,
WHEREAS, pursuant to Resolution No. 23-485, the City of Port Arthur's City Council
approved awarding the Port Acres Drainage Improvement Project to Allco, LLC, (Allco) of
Beaumont, Texas; and,
PR No. 23877
8/16/2024 mje
Page 2 of 4
WHEREAS, pursuant to Resolution No. 24-032, the City of Port Arthur's City Council
approved Change Order No. 1 for the performance of value engineering by City staff, AWC, and
Allco, LLC, of Beaumont, Texas, decreasing the contract amount of $34,891,106.81 by
$1,736,424.04 to the new contract amount of $33,154,682.77; and,
WHEREAS, pursuant to Resolution No. 24-304, the City of Port Arthur's City Council
approved Change Order No. 2 for the relocation of the sanitary sewer services and sewer main;
and,
WHEREAS, Change Order No. 2 increased the contract amount by $159,385.00 from
$33,154,682.77 to the new contract amount of $33,314,067.77 and added eighteen (18)
calendar days amending the original completion date of June 25, 2025 to the new completion
date of July 13, 2025; and,
WHEREAS, Change Order No. 3 is being submitted by Allco, LLC, of Beaumont, Texas,
for the installation of the sanitary sewer main on 64th Street, the addition of fifteen (15) calendar
days and the addition of 150 LF of water line relocations for the amount of $196,037.00, see
Exhibit A; and,
WHEREAS, Change Order No. 3 proposes to increase the contract amount of
$33,314,067.77 by $196,037.00 to a new contract amount of $33,510,104.77; and,
WHEREAS, Change Order No. 3 proposes to add fifteen (15) calendar days to the original
contract completion date of July 13, 2025 changing it to the new contract completion date of
July 28, 2025; and,
WHEREAS, it was determined after further investigation that there were a significant
number of mains that were in conflict and caused obstructions to the designed drainage system
in Port Acres, Change Order No. 3 addresses the elimination of these obstructions; and,
PR No. 23877
8/16/2024 mje
Page 3 of 4
WHEREAS, approval of PR No. 23877 for Change Order No. 3 is herein deemed an
appropriate action; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, Change Order No. 3 is herein approved and the City Manager is hereby authorized
to execute said Change Order No. 3 to the contract between the City of Port Arthur and Allco,
LLC, of Beaumont, Texas; and,
THAT, Change Order No. 3 increases the contract amount of $33,314,067.77 by
$196,037.00 to the new contract amount of $33,510,104.77; and,
THAT, Change Order No. 3 adds fifteen (15) calendar days to the original contract
completion date of July 13, 2025 changing it to the new contract completion date of July 28,
2025; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council,
READ, ADOPTED AND APPROVED this the day of , A.D. 2024,
at a meeting of the City of Port Arthur, Texas by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
PR No. 23877
8/16/2024 mje
Page 4 of 4
Thurman Bill Bartle
Mayor
ATTEST:
Sherri Bellard
City Secretary
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION:
Roxann Pais Cotroneo, Esquire Ron Burton
City Attorney City Manager
APPROVED AS FOR AVAILABILITY OF
FUNDS:
32-/Jei
Lyn a (Lyn) Boswell, MA, ICMA-CM
Director of Finance
John Cannatella, PE
City Engineer
LOA.
Clifton Williams, CPPB
Purchasing Manager
EXHIBIT A
r.
CITY OF PORT ARTHUR
Public Works Engineering
DATE: AUGUST 16,2024
PROJECT: PORT ACRES DRAINAGE IMPROVEMENT PROJECT
OWNER: CITY OF PORT ARTHUR
CONTRACTOR: ALLCO,LLC OF BEAUMONT,TEXAS
CHANGE ORDER NO.: 3
THE FOLLOWING CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE HEREBY MADE:
Adjust the Estimated Quantities to reflect the Actual Quantities used in the completion of the project:
Item Description Unit Original Unit Price Original Amount Total Added New Amount
Quantity
1 64th Street
-Installation of sanitary sewer main LF $ 160,037.00
2 7126-0002-Water Line Relocations LF 20 $ 240.00 $ 4,800.00 150 $ 36,000.00
TOTAL CHANGE ORDER $ 196,037.00
ORIGINAL CONTRACT AMOUNT $33,314,067.77 NEW CONTRACT $33,510,104.77
AMOUNT
ORIGINAL CONTRACT AMOUNT:I$ 34,891,106.81 I
TOTAL AMOUNT OF CHANGE ORDER NO.1: S (1,736,424.04)
TOTAL AMOUNT OF CHANGE ORDER NO.2: $ 159,385.00
TOTAL AMOUNT OF CHANGE ORDER NO.3: $ 196,037.00
PERCENT OF CHANGE ORDER NO.1: -4.98%
PERCENT OF CHANGE ORDER NO.2: 0.46%
PERCENT OF CHANGE ORDER NO.3: 0.56%
TOTAL PERCENT OF CHANGE ORDERS NOS.1,2&3: -3.96%
NEW CONTRACT AMOUNT: $ 33,510,104.77
CONTRACT COMPLETION DATE:I July 28,2025
FIFTEEN(15)CALENDAR DAYS HAVE BEEN ADDED TO CHANGE ORDER NO.3
PAREPARED BY: APPROVED BY:
M.Jennifer Edwards,BAAS,MPA;CIP Manager John Cannatella,PE,City Engineer
APPROVED BY: APPROVED BY:
Brandon Harrison,ALLCO,LLC. Marc Ochoa,Senior Project Manager,AWC
APPROVED BY: APPROVED BY:
Dr.Hani Tohme,PE,Consultant Clifton Williams,CPPB,Purchasing Manager
APPROVED BY:
Ron Burton,City Manager
S:\Engineering\PUBLIC WORKS\PW-ENGINEERING\C.I.P.PROJECTS\Year 2023\DRAINAGE PROJECTS\Port Acres\Change Orders\Change Order 3\Port Acres CO 3