HomeMy WebLinkAbout(D2) 2024Sept10 Stonegate CC Update01City of Port Arthur Stonegate Drainage Project
Sept. 10th,2024 update
1
2
March 7th – Utility Locates
March 14th – Contractor Mobilization
March 17, - Pumping Down Pond #4
3
April 03 – Outfall Ditch Excavation
4
April 12th, Laying Outfall Boxes
April 29th – Rain Impacting Outfall Ditch
5
May 24th Outfall Channel Complete
6
June – July – 14 Days Rain Delays
7
August 14th – Pond #4 Excavation
8
Golf Hill Drive Oakmont Side Streets – Utility Conflicts
August 28th , 2024
9
10