Loading...
HomeMy WebLinkAbout(D2) 2024Sept10 Stonegate CC Update01City of Port Arthur Stonegate Drainage Project Sept. 10th,2024 update 1 2 March 7th – Utility Locates March 14th – Contractor Mobilization March 17, - Pumping Down Pond #4 3 April 03 – Outfall Ditch Excavation 4 April 12th, Laying Outfall Boxes April 29th – Rain Impacting Outfall Ditch 5 May 24th Outfall Channel Complete 6 June – July – 14 Days Rain Delays 7 August 14th – Pond #4 Excavation 8 Golf Hill Drive Oakmont Side Streets – Utility Conflicts August 28th , 2024 9 10