HomeMy WebLinkAbout(D2) 2024Sept10 Stonegate CC Update01 (2)City of Port Arthur
Stonegate
Drainage Project
SEPT. 10TH,2024 UPDATE
March 7th – Utility
Locates March 14th –
Contractor
Mobilization March 17, -
Pumping Down
Pond #4
April 03 – Outfall
Ditch Excavation
April 12th, Laying
Outfall Boxes
April 29th – Rain
Impacting
Outfall Ditch
May 24th Outfall Channel
Complete
June – July – 14 Days Rain Delays
August 14th – Pond #4 Excavation
Golf Hill Drive
Oakmont Side
Streets – Utility
Conflicts
August 28th , 2024