Loading...
HomeMy WebLinkAboutPR 23976: CHANGE ORDER NO. 1 FOR 36" WATERLINE AERIAL CROSSING COATING City of url INTEROFFICE MEMORANDUM Date: October 8, 2024 To: The Honorable Mayor and City Council Through: Ronald Burton, CPM, City Manager From: Calvin Matthews, P.E., Water Utilities Director RE: PR No. 23976—Change Order No. 1 for 36" Waterline Aerial Crossing Coating Introduction: This Agenda Item is to seek the City Council's approval for Change Order No. 1 for the 36" Waterline Aerial Crossing Project with Blastco Texas Inc. of Channelview, Texas. Background: The two 36-inch Waterlines along Savannah Avenue & Main "D" Canal Alligator Bayou and Savannah Avenue & and Main Outfall Canal were constructed in 2004. The Aerial Crossing parts are corroded and are in urgent need of rehabilitation. Resolution No. 24-203 awarded the project to Blastco Texas Inc. of Channelview, Texas for $336,520.00,and Schaumburg&Polk,Inc. Engineering Firm of Beaumont,Texas is the project engineer and construction manager. During construction, the existing air release valve (ARV) tap on the 36" waterline along Savannah Ave was found to be extremely corroded and in bad condition posing a health and safety concern in ensuring proper delivery of water to residents in the area. Schaumburg&Polk Engineering Firm along with City staff is recommending Change Order No. 1 to remove and replace the existing ARV tap on the 36"waterline along Savannah Ave, including new tapping saddle with a 6" flanged spool, gate valve, and ARV. Change Order No. 1 is also requesting to extend the contract time by 28 days to the new total contract time of 178 days,to accommodate for material delivery and installation. "Remember,we are here to serve the Citizens of Port Arthur" Cih'of rt rthrt Budget Impact: Initial contract amount was $336,520.00 Change Order No. 1 will increase the contract amount by $9,393.12 to the new total contract amount of$345,913.12. Funding is available in Capital Improvement Projects Account No. 405-40-000-8516-00-00- 000,Project No. WS0013-CON. Recommendation: It is recommended that City Council approve Proposed Resolution No.23976 to approve Change Order No. 1 for the 36" Waterline Aerial Crossing Coating project as discussed and/or outlined above. "Remember,we are here to serve the Citizens of Port Arthur" PR No. 23976 10/8/24 cm Page 1 of 3 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 TO THE 36" WATERLINE AERIAL CROSSING COATING PROJECT WITH BLASTCO TEXAS INC. OF CHANNELVIEW, TEXAS, INCREASING THE CONTRACT AMOUNT BY $9,393.12 TO THE NEW TOTAL CONTRACT AMOUNT OF $345,913.12 AND A TIME EXTENSION OF 28 DAYS TO A NEW TOTAL CONTRACT TIME OF 178 DAYS; FUNDS ARE AVAILABLE IN CAPITAL IMPROVEMENT PROJECTS ACCOUNT NO. 405-40-000-8516-00-00-000, PROJECT NO.WS-0013 CON. WHEREAS, pursuant to Resolution 24-203, the 36" Waterline Aerial Coating Project was awarded to Blastco Texas Inc. of Channelview, Texas with a total projected budgetary amount of$336,520.00; and, WHEREAS, Schaumburg & Polk, Inc. Engineering Firm of Beaumont, Texas was hired as Construction Engineer to oversee the project; and, WHEREAS, during construction, the existing air released valve (ARV) tap on the 36" waterline along Savannah Ave was found to be extremely corroded and in bad condition posing a health and safety concern in ensuring proper delivery of water to residents in the area; and, WHEREAS, Schaumburg & Polk, Inc. Engineering Firm proposed Change Order No. 1 (EXHIBIT "A") to remove and replace the existing ARV tap on the 36" waterline along Savannah Ave, including new tapping saddle with a 6" flanged spool, gate valve, and ARV increasing the contract amount by $9,393.12 to the new total contract amount of$345,913.12; and, WHEREAS, Schaumburg & Polk, Inc. has also requested an extension of the contract time by an additional 28 days, bringing the total contract duration to 178 days, to accommodate for material delivery and installation; and PR No. 23976 10/8/24 cm Page 2 of 3 NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT,the facts and opinions in the preamble are true and correct; and, THAT, the City Council hereby approves Change Order No. 1 (EXHIBIT "A") to increase the amount by $9,393.12 to the new total contract amount of$345,913.12 and extending the contract time by 28 days to the new total contract time of 178 days; and, THAT, the funding is available in Capital Improvement Projects Account No. 405-40- 000-8516-00-00-000, Project No. WS-0013; and, THAT, a copy of the caption of this resolution be spread upon the minutes of the City Council. READ, ADOPTED, AND APPROVED, this day of , 2024, AD, at a Regular Meeting of the City Council of the City of Port Arthur, Texas by the following Vote: AYES: Mayor: Councilmembers: • NOES: Thurman Bill Bartie Mayor ATTEST: APPROVED ST:11'0RM: Sherri Bellard Roxann Pais Cotroneo City Secretary City Attorney PR No. 23976 10/8/24 cm Page 3 of 3 APPROVED FOR ADMINISTRATION: Ronald o City Manager 6,/ Calvin Matthews, P.E. Water Utilities Director APPRO ED AS TO FUND AVAILABILITY: 11-1CC &C"6-4-4 LY nda'Boswe Finance Director I . ;'/1) LULL Clifto Williams, CPPB Purchasing Manager EXHIBIT "A" (CHANGE ORDER NO. 1) APPROVAL OF CONTRACT CHANGE CHANGE ORDER No.One(1) DATE: October 8,2024 PROJECT: City of Port Athur Waterline Aerial Crossing Coating P24-031 OWNER: City of Port Athur,Texas 444 4th Street Port Arthur,Texas 77640 CONTRACTOR: Blastco Texas 16201 Wood Drive Channelview,Texas 77530 TO THE OWNER: Approval of the following contract change is requested. Reason for Change: to remove and replace the existing 6"ARV including removing the existing 6"tap on the existing 36"water line ORIGINAL CONTRACT AMOUNT: $ 336,520.00 THIS CHANGE ORDER 4 Miscellaneous -Replacement of the existing ARV at the Main Outfall Cannal,DELETE 1 ALLOW @$25,000.00 $ (25,000.00) 13 Remove and replace the existing 36"tap,including new tapping saddle with a 6"flanged spool,gate valve,and ARV,ADD 1LS @$34,393.12 $ 34,393.12 TOTAL AMOUNT OF THIS CHANGE ORDER: $ 9,393.12 TOTAL REVISED CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER: $ 345,913.12 CONTRACT TIME Original Contract Time: 150 calendar days Additional time for material delivery and installation 28 calendar days Revised Contract Time per this Change Order 178 calendar days CONDITION OF CHANGE: "Contractor acknowledges and agrees that the adjustments in contract price and contract time stipulated in this Change Order represents full compensation for all increases and decreases in the cost of,and the time required to perform the entire work under the Contract arising directly or indirectly from this Change Order and all previous Change Orders. Acceptance of this waiver constitutes an agreement between Owner and Contractor that the Change Order represents an all inclusive,mutually agreed upon adjustment to the Contract,and that Contractor will waive all rights to file a claim on this Change Order after it is properly executed." Rect7I de Approved by: Accepted by: Avid-fie leon SchPolk, nc. City of Port Arthur Blastco Texas Eng Owner Contractor Datr Date: Date: 10/0 8/2 4 Page 1 of 1