INTEROFFICE MEMORANDUM
Date: November 20, 2024
To: The Honorable Mayor and City Council
Through: Ronald Burton, CPM, City Manager
From: Calvin Matthews, P.E., Water Utilities Director
RE: PR No. 24041 —Change Order No. 1 for Atlanta Water Line Improvement
Project
Introduction:
This Agenda Item is to seek the City Council's approval for Change Order No. 1 for the Atlanta
Water Line Improvement Project with Global Drilling Inc. of Winnie, Texas.
Background:
The 16" Atlanta water line from 19th Street to 4th Street is the main water supply line for the
downtown area of Port Arthur. Based on the work orders and the residents' concerns, the water
line condition urgently needs rehabilitation. Arceneaux Wilson & Cole Engineer firm (AWC)
provides professional services to design and construct a 20" water line replacement for the
project.
Resolution No. 24-021 awarded the project to Global Drilling Inc. of Winnie, Texas, for
$2,377,477.00, and Arceneaux Wilson& Cole Engineer firm(AWC) of Port Arthur, Texas, via
Resolution No. 23-464, is the project engineer and construction manager.
The existing 16-inch water line is currently experiencing multiple leaks due to joint separation
and deteriorated pipe material. To avoid further damage to the existing water line during
construction which will result in water services interruptions and to lessen disturbances and
avoid blocking large sections of the road for residents in the area, the City has requested the
Contractor utilize directional drilling trenchless technology to install 4,578 ft of 20-inch water
line. To better accommodate this construction plan,the City has also elected to delete the main
line valves on the 20-inch water line. Arceneaux Wilson& Cole Engineer firm (AWC), along
with City staff, is recommending Change Order No. 1 for the Atlanta Water Line Improvement
project to make the aforementioned changes. Change Order No. 1 is also extending the duration
of the contract time by 90 days to a new total contract time of 270 days.
"Remember,we are here to serve the Citizens of Port Arthur"
City o%
or! rthur
Budget Impact:
The initial contract amount was $2,377.477.00
Change Order No. 1 will increase the contract amount by $234,163.00 to the new total contract
amount of$2,611,640.00.
Funding is available in Capital Improvement Projects Account No. 405-40-000-8516-00-00-
000,Project No. WS0019-CON.
Recommendation:
It is recommended that City Council approve Proposed Resolution No.24041 to approve Change
Order No. 1 for the Atlanta Water Line Improvement project as discussed and/or outlined above.
"Remember,we are here to serve the Citizens of Port Arthur"
PR No. 24041
11/12/24 cm
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE CHANGE ORDER NO. 1 TO THE ATLANTA
WATERLINE IMPROVEMENT PROJECT WITH GLOBAL
DRILLING INC. OF WINNIE, TEXAS, INCREASING THE
CONTRACT AMOUNT BY $234,163.00 TO THE NEW TOTAL
CONTRACT AMOUNT OF $2,611,640.00 WITH EXTENDED
CONTRACT TIME OF 90 DAYS TO THE NEW TOTAL
CONTRACT TIME OF 270 DAYS; FUNDS ARE AVAILABLE IN
CAPITAL IMPROVEMENT PROJECTS ACCOUNT NO. 405-40-
000-8516-00-00-000, PROJECT NO. WS-0019 CON.
WHEREAS, pursuant to Resolution No. 24-021, the Atlanta Water Line Improvement
Project was awarded to Global Drilling Inc. of Winnie, Texas, with a total projected budgetary
amount of$2,377,477.00; and,
WHEREAS, pursuant to Resolution No. 23-464, Arceneaux Wilson& Cole Engineering
Firm (AWC) of Port Arthur, Texas, was hired as Design and Construction Engineer to oversee
the project; and,
WHEREAS, the existing 16-inch water line is currently experiencing multiple leaks due
to joint separation and deteriorated pipe material, and therefore, to avoid further damage to the
existing water line during construction which will result in water services interruptions and to
lessen disturbances to residents in the area, the City has requested the Contractor utilize
directional drilling trenchless technology instead of open trench installation to install, 4,578 ft of
20-inch water line which will also require the removal of main line valves on the 20-inch water
line; and,
WHEREAS, Arceneaux Wilson & Cole Engineering Firm (AWC) proposed Change
Order No. 1 (EXHIBIT"A")to install using directional drilling trenchless technology, increasing
the contract amount by $234,163.00 to the new total contract amount of $2,611,640.00 with
extended contract time of 90 days to the new total contract time of 270 days.
PR No. 24041
11/12/24 cm
Page 2 of 3
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT,the facts and opinions in the preamble are true and correct; and,
THAT, the City Council hereby approves and authorizes the City Manager execute
Change Order No. 1 (EXHIBIT "A") to increase the amount by $234,163.00 to the new total
contract amount of $2,611,640.00 and extending the contract time by 90 days to the new total
contract time of 270 days; and,
THAT, the funding is available in Capital Improvement Projects Account No. 405-40-
000-8516-00-00-000, Project No. WS-0019; and,
THAT, a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ, ADOPTED, AND APPROVED, this day of , 2024, AD,
at a Regular Meeting of the City Council of the City of Port Arthur, Texas by the following
Vote: AYES:
Mayor:
Councilmembers:
NOES:
Thurman Bill Bartie
Mayor
PR No. 24041
11/12/24 cm
Page 3 of 3
ATTEST: APPROVED
Sherri Bellard Roxann Pais Cotroneo
City Secretary City Attorney
APPROV diaOR ADMINISTRATION:
ittopp-
Ronald B7 n, ►e;�
City Mana
alvin Matthews, P.E.
Water Utilities Director
APPROVED AS TO FUND AVAILABILITY:
Lynda(Lyn) Boswell, MA, ICMA- M
Finance Director
/; L[JL
Clifto , E. Williams Jr., CPPB
Purchasing Manager
EXHIBIT "A"
(CHANGE ORDER NO. 1)
.11111k
.11110
.. ARCENEA
UX WILSON&COLE
engineering I surveying I olonrnng
November 14, 2024
Mr. Calvin Matthews, P.E.
City of Port Arthur
Director of Water Utilities
444 4th Street
Port Arthur, Texas 77640
RE: Proposal For Change Order No. 01 for
A TLANTA WATER LINE IMPROVEMENTS
AWC Job No. CPA-1160
Mr. Matthews:
Attached is Change Order No. 1 for the Atlanta Water Line Improvements project.
This change order is to increase the contract amount by $234,163.00 and extend
the original contract time by 90 calendar days.
The City has requested the Contractor utilize the directional drilling trenchless
technology to install the entirety of the project's base bid and additive alternate
bid 20-inch water line along Atlanta Avenue. This is due to the condition of the
existing 20-inch water line and the potential of an open trench construction
inflicting further damage to the existing pipe. The existing 16-inch water line is
currently experiencing multiple leaks due to joint separation and deteriorated
pipe material. Doing this allows the Contractor to maintain the ability for vehicular
travel along Atlanta Avenue, without having to shut down large sections of
roadway for the water line construction. Utilizing directional drilling also allows
for the 20-inch water line to be constructed with minimal impedance on the
adjacent homeowner's compared to what would be experienced with open
trench installation. In order to maximize the directional drilling process, the City
has also elected to delete main line valves on the 20-inch water line. This allows
for longer sections of 20-inch water line to be installed within a single directional
409.724.7888
3120 Central Mall Drive
Port Arthur,TX 77642 Engineering Surveying
awceng.com F-16194 10194049
st,
drill pipe pull. The Contractor has also experienced a longer than normal lead time
for the manufacturing of the remaining 20-inch gate valves in the project. The
City and Engineer have reviewed the proposed changes and agree it is within the
budget and scope as requested.
This change order will extend the original contract time by 90 calendar days and
increase the original contract amount by $234,163.00. We recommend that the
City of Port Arthur authorize this change order to the contract as submitted. We
have attached Change Order No. 1 which modifies the contract to reflect this
change for your consideration and action.
Should you have any questions or require additional information, please contact
our office.
ARCENEAUX WILSON&COLELLC
TEXAS REGISTERED ENGI EER/NG FIRM F-16194
Keith Zotzky, P.E., C
Vice President of Engineering Services
Attached.
Change Order#01
I
ARCENEAUX WILSON&COLE
CHANGE ORDER NO. 1
DATE: November 13, 2024 JOB NO.: CPA-1160
AGREEMENT DATE: May 20, 2024
NAME OF PROJECT: Atlanta Water Line Improvements
OWNER: CITY of PORT ARTHUR
CONTRACTOR: GLOBAL DRILLING
The following changes are hereby made to the CONTRACT DOCUMENTS:
4. Deduct 143 LF 20" HDPE DR11 (DIPS) in Steel Casing at $590/LF. ($84,370.00)
5. Add 2,800 LF 20" HDPE DR11 (DIPS) Trenchless Installation at $250/LF. ($700,000.00)
6. Deduct 2,657 LF 20" HDPE DR11 (DIPS) Installation in Trench at $121/LF. ($321,497.00)
13. Deduct 10 EA 20" Gate Valve & Box at $20,000/EA. ($200,000.00)
Al. Add 1,778 LF 20" HDPE DR11 (DIPS) Trenchless Installation at $260/LF. ($462,280.00)
A2. Deduct 1,778 LF 20" HDPE DR11 (DIPS) Installation in Trench at $125/LF. ($222,250.00)
A8. Deduct 5 EA 20" Gate Valve & Box at $20,000/EA. ($100,000.00)
TOTAL $234,163.00
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $2,377,477.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $2,377,477.00
The CONTRACT PRICE due to this CHANGE ORDER will be [increased]
by: $234,163.00
The new CONTRACT PRICE, including this CHANGE ORDER, will be $2,611,640.00
4
4
4
4
1 of 2
0
M CHANGE ORDER NO. 1
♦_ awc November 13, 2024
trjrJob No. CPA-1160
ARCENEAUX WILSON&COLE
engineering!surveying planr^
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 180 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 0 Calendar Days
CURRENT DATE OF COMPLETION: November 17, 2024
CONTRACT TIME due to this CHANGE ORDER will be increased by 90 Calendar Days
The New DATE OF COMPLETION: February 15, 2025
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred
by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCENEAUX V SON.& COLE LLC (CONTRACTOR, OFFICER OR OWNER)
GLOBAL DRILLING
ACCEPTED BY:
CITY of PORT ARTHUR
I
I
2of2