HomeMy WebLinkAbout(P2) 2025 Water Utilities Infrastructure Rehabilitation Update- council workshop re2 (2)Water Utilities Budget and Infrastructure Update
JANUARY 28, 2025
Adopted 2024 Capital Improvements Budget5-year Program
Project Name 2024 Adopted Budget 2025 2026 2027 2028 Project Total Cost
Lift Stations Rehab $1,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $9,000,000
Sabine Pass Coll Sys $500,000 $500,000 $500,000 $500,000 $500,000 $2,500,000
El Vista Force Manin $2,200,000 $1,100,000 $3,300,000
Sabine Pass Waste Water Treatment Plant $394,000 $394,000
46th Street Force Main $1,500,000 $1,500,000
Collection Systems Rehab $1,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $9,000,000
Install Parallel 36" Trunk Trans Line $19,000,000 $19,000,000
Elevated Storage Tank Rehab $1,000,000 $1,500,000 $1,000,000 $1,000,000 $4,500,000
Water Line Improvement/Replacements TWDB $5,000,000 $5,000,000 $2,000,000 $3,000,000 $15,000,000
Main WWTP Improvement CO $1,700,000 $1,700,000
Lead and Copper Phase I $500,000 $1,700,000 $2,200,000
Water Purification Plant Electrical Impr $1,000,000 $1,000,000
Atlanta Water Line Replacement $1,500,000 $2,000,000 $3,500,000
Fire Hydrant Replacement $500,000 $500,000 $500,000 $500,000 $500,000 $2,500,000
TOTAL $8,094,000 $18,400,000 $12,600,000 $27,000,000 $9,000,000 $75,094,000
Funding Source 2024 Adopted Budget 2025 2026 2027 2028 Project Total Funding
General Revenue -Cash $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $10,000,000
Bonds $5,594,000 $15,900,000 $10,100,000 $24,500,000 $6,500,000 $62,594,000
CDBG
FEMA/HMPG Grant
Other Grant $500,000 $500,000 $500,000 $500,000 $500,000 $2,500,000
PAEDC
Other Funding Source1
Total $8,094,000 $18,400,000 $12,600,000 $27,000,000 $9,000,000 $75,094,000
Proposed 2025 Capital Improvements Budget5-year Program
Project Name 2025 Utility
Request
2026 2027 2028 2029 FY 25-29
Project
Cost
Elevated Storage Tank Rehabilitation $2,000,000 $4,000,000 $4,000,000 $4,000,000 $4,000,000 $18,000,000
Force Main Replacement $3,700,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $11,700,000
Lift Stations $2,000,000 $4,000,000 $4,000,000 $4,000,000 $4,000,000 $18,700,000
Waste Water Treatment Plant Construction $1,500,000 $2,000,000 $1,000,000 $2,000,000 $2,000,000 $10,680,842
Collections System Rehab $3,000,000 $3,000,000 $2,000,000 $5,000,000 $4,000,000 $17,101,200
Sabine Pass Collection System $500,000 $500,000 $500,000 $500,000 $500,000 $2,500,000
Lead and Copper Inventory $700,000 $700,000
Distribution System Rehab $8,850,000 $10,000,000 $12,000,000 $12,000,000 $12,000,000 $53,200,000
El Vista Force Main Phase II $1,100,000 $1,100,000
Fire Hydrant Replacement-City Wide $500,000 $1,000,000 $500,000 $500,000 $500,000 $2,500,000
Other Equipment (Pipefitting) & Projects $1,250,000 $2,400,000 $8,817,958
Water Purification Plant Improvement $1,000,000 $1,000,000 $1,000,000
Water/Sewer Replacement in Street Projects $5,000,000 $3,000,000 $1,000,000 $4,000,000
TOTAL $30,000,000 $ 30,000,000 $ 30,000,000 $ 30,000,000 $ 30,000,000 $ 150,000,000
Funding Source 2026 2027 2028 2029 FY 25-29
Project
Cost
General Revenue - Cash
Bonds (GO's, CO's, Revenue)$30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $150,000,000
Grants $0
(1)Other Grant- ARPA
EDC Street Maintenance
(2)Other Funding Source
TOTAL $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $150,000,000
Approved 2025 Capital Improvements Budget
Project Name 2025
Elevated Storage Tank Rehabilitation
Force Main Replacement
Lift Stations
Waste Water Treatment Plant Construction
Collections System Rehab
Sabine Pass Collection System
Lead and Copper Inventory
Distribution System Rehab
El Vista Force Main Phase II
Fire Hydrant Replacement-City Wide
Other Equipment (Pipefitting) & Projects
Water Purification Plant Improvement
Water/Sewer Replacement in Street Projects
Non-Designated (405-40-000-85XX-00-00-000)$1,045,600
TOTAL $1,045,600
Funding Source
General Revenue -Cash $1,045,600
Bonds (GO's, CO's, Revenue)
Grants
(1)Other Grant-ARPA
EDC Street Maintenance
(2)Other Funding Source
TOTAL $1,045,600
FY 2025 Proposed Rate Increases and Council Actions
Proposed Ordinance Rate Proposed Council Meeting Date Motion
PO#7278 8.5% for $30 million CIPs 9/10/2024 Fail
PO#7280 7.5% for $25 million CIPs 9/17/2024 Fail
PO#7281 7.0% for residential and
8.5% for commercial
$25 million CIPs
9/17/2024 Fail
PO#7288 Reconsidering PO#7281 10/22/2024 Fail
FY 25 Financial Status of Utility Departmentas of the numbers ending in December
Projected end-of-year deficit: approx. $3 million (Not considering emergencies)
FY 25 Major Projects Approved and Funded
Sabine Pass Pipe Bursting IV paid by ARPA Interest Revenue.
Hwy 365 Force Main Replacement proposed to be funded by the General Fund as an agenda item at this council meeting.
FY 25 Emergency Memo
Date Scope Summery Cost
10/07/2024 8” Sewer line by Railroad and Thomas Blv $154,400.00
10/15/2024 42” Sewer line at 3835 Gulfway $247,611.66
11/27/2024 WTP Filter Leak and Valve repair $50,000.00
12/9/2024 WTP 600 Amp Breaker to Train 3 and 4 $50,000.00
12/17/2024 Generator at Gulf Pump Station $25,444.34
12/13/2024 Manhole collapsed 3000 61st Street $50,000.00
1/3/2025 Sewer cleaning and replacing the manhole at the Library $100,000.00
1/23/2025 12” Water line repair in Sabine Pass $20,000.00
Total $697,456.00
FY 25 Customer Calls for Service
From October 1, 2024 to January 23, 2025
Water Service Calls: 678
Sewer Service Calls:1506
Water Billing/Meter Service Work Orders: 24,604
Water Line Replacement ProjectsPriority 1
MANDATED BY THE U.S. ARMY CORPS OF ENGINEERS
36” SAVANNAH WATER LINE SUPPLIES DOWNTOWN, PLEASURE ISLAND, SABINE PASS AREA
City of Port Arthur Utilities Projects Total Cost Estimate
Project Description Priority 1 Priority 2 Estimated Cost
Sanitary Sewer Lift Stations Rehab Projects $ 19,524,000.00 $ 37,800,000.00 $ 57,324,000.00
Sanitary Sewer Pipe Replacement Projects $ 13,824,221.00 $ 250,471,340.00 $ 264,295,561.00
Water Line Replacement Projects $ 57,968,382.00 $ 470,035,230.00 $ 528,003,612.00
Water Towers Rehab Projects $ 1,658,300.00 $ 7,535,660.00 $ 9,193,960.00
Water Purification Plant and Gulf Pump
Station Projects $ 11,390,210.00 $ 5,100,000.00 $ 16,490,210.00
WasteWater Treatment Plants Projects $ 1,200,000.00 $ 32,500,000.00 $ 33,700,000.00
Fire Hydrants Replacement Projects $ 550,000.00 $ 14,850,000.00 $ 15,400,000.00
Total $ 106,115,113.00 $ 818,292,230.00 $ 924,407,343.00
Future expansion needs $ 258,903,873
Total with Future expansion needs $ 1,183,311,216.00
Sources of Funding
Sources of Funding –Grants Application from 2023 to present
Not Approved
TDEM Hazard Mitigation Grant Program-Critical Lift Stations $7,045,576.00
USFWS Wildland Fire Management -Fire Hydrant $2,341,350.00
FEMA/TDEM Severe Winter Storm Hazzard Mitigation –Fire Hydrant Study $2,341,350.00
TWDB DWSRF Water Line Replacement $190,111,639.00
TWDB DWSRF Lead and Copper $4,806,260.00
Total $206,646,175.00
Pending
EPA HARC Community Change Grants-Lift Station $20,000,000.00
EPA HARC Community Change Grants-Sewer Pipe Rehab $20,000,000.00
TWDB DWSRF Lead and Copper $4,806,260.00
Total $44,806,260.00
Re-apply 2025
TWDB DWSRF Water Line Replacement (low Interest loan)$190,111,639.00
Potential Sources of Funding –Meter Replacement Program
Project Bid Documents are completed
Under Legal Review
Sources of Funding for Capital Project –Certificates of Obligation
Notes:
•These rate increases do not include Operation Rate Increases and Inflation
•The Rate Increases are estimated based on $37 Million current annual revenue
Spending Rate
Yearly
Number of Years to
complete
Annual Water Rate Increase
(Percent)
Estimated Completion
year
$50 Million/year 17.9 8.7 %2042
$40 Million/year 22.4 7 %2046
$30 Million/year 29.9 5.2 %2054
$20 Million/year 44.8 3.6 %2069
$10 Million/year 89.6 1.8%2114
17.9 22.4 29.9 44.8 89.6
2042 2046 2054
2069
2114
2000
2020
2040
2060
2080
2100
2120
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
100.0
$50 Million/year $40 Million/year $30 Million/year $20 Million/year $10 Million/year Estimeated Completion YearNumber of YearsSpending Rate
Utility Projects vs Water/Sewer Rate Increase
Estimated Timeline
Number of Years Estimated Completion Date
5.2%
3.6%
8.7%7%
Not
Recommended
Summary
The 2025 utilities fund doesn’t have any funding for the Major Planned Capital Improvement Projects.
At the End of the year 2025, the budget projection is a deficit of $3 million.
Any emergency work for the Utilities Department for the 2025 budget will have to be funded from the General Fund as of January 2025.
The Attorney General’s consent order is expected to be filed before the end of the 2025 budget year.
The General Fund can not subsidize the Utilities Enterprise Fund.
The Utilities Enterprise Fund will not be able to repay the General Fund any of the money borrowed during the 2025 budget year.
QUESTIONS?