INTEROFFICE MEMORANDUM
Date: March 6, 2025
To: The Honorable Mayor and City Council
Through: Ron Burton, City Manager
From: George Davis, Director of Pleasure Island
RE: P.R. 24216—Executing change order No. 1 to the contract between the City of
Port Arthur and Geofill Construction, increasing the contract amount by
$28,547.50 to a new contract total of$234,722.50 for the renovation of both
sets of restrooms in Lakefront Park on Pleasure Island
Introduction:
The intent of this Agenda Item is to request the City Council's approval of P. R. No. 24216
authorizing the City Manager to execute change order No. 1 to the contract between the City
of Port Arthur and Geofill Construction of Schertz, Texas, increasing the contract amount by
$28,547.50 to a new contract total of$234,722.50 for the renovation of both sets of restrooms
in Lakefront Park on Pleasure Island.
Background:
Pursuant to Resolution No. 24-188, the City of Port Arthur awarded a contract to Geofill
Construction to renovate both sets of restrooms in Lakefront Park on Pleasure Island. There
were unforeseen damaged areas on both roofs,breakers, plumbing repairs and ADA walkways
required.
Budget Impact:
The funding for this change order is in Account Number 450-00-000-8525-00-00-000 Project
Number PI0007
Recommendation:
It is recommended that the City Council approve P. R.No.24216 authorizing the City Manager
to execute change order No. 1 to the contract between the City of Port Arthur and Geofill
Construction of Schertz,Texas,increasing the contract amount by$28,547.50 to a new contract
total of$234,722.50 for the renovation of both sets of restrooms in Lakefront Park on Pleasure
Island.
"Remember,Ise are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
P. R. #24216
3/6/2025 gd
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN
THE CITY OF PORT ARTHUR AND GEOFILL CONSTRUCTION OF
SCHERTZ, TEXAS, INCREASING THE CONTRACT AMOUNT BY
$28,547.50 TO A NEW CONTRACT TOTAL OF $234,722.50 FOR
THE RENOVATION OF BOTH SETS OF RESTROOMS IN
LAKEFRONT PARK ON PLEASURE ISLAND; FUNDING
AVAILABLE IN ACCOUNT NUMBER 450-00-000-8525-00-00-000
PROJECT NUMBER PI0007
WHEREAS, per Resolution No. 24-188, the City Council awarded a contract to Geofill
Construction to renovate both sets of restrooms in Lakefront Park on Pleasure Island; and,
WHEREAS, there were unforeseen damaged areas on both roofs, breakers, plumbing
repairs and ADA walkways required.; and,
WHEREAS, the unforeseen issues increased the amount by $28,547.50 (attached hereto
as Exhibit"A") for a new contract amount of$234,722.50; and,
WHEREAS, the list of required repairs is (attached hereto as Exhibit`B"); now
therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR,
TEXAS:
Section 1. That the facts and opinions in the preamble are true and correct.
Section 2. That the City Manager of the City of Port Arthur is hereby authorized and
directed to execute, on behalf of the City of Port Arthur, Change Order No. 1, to accept the
required work provided by Geofill Construction, increasing the contract amount by $28,547.50
attached hereto as Exhibit "A" for a new contract amount of $234,722.50 and to accept the
required repairs, in substantially the same form as attached hereto as Exhibit`B".
P. R. #24216
3/6/2025 gd
P. R. #24216
3/6/2025 gd
Section 3. That a copy of the caption of this Resolution be spread upon the Minutes of
the City Council.
READ, ADOPTED AND APPROVED THIS day of , A.D., 2025, at a
Regular Meeting of the City Council of the City of Port Arthur, by the following vote:
AYES:(Mayor)
Councilmembers:
NOES:
Thurman Bill Bartie
Mayor
ATTEST:
Sherri Bellard
City Secretary
APPROVED AS TO FORM:
Roxann Pais Cotroneo
City Attorney
P. R. #24216
3/6/2025 gd
APPROV T MINISTRATION:
Ronald Burt C
City M er
Georg Davis
Director of Pleasure Island
APPROVED AS TO AVAILABILITY OF FUNDS:
few 6c-ilt,LP
Lyn a Boswell
Director of Finance
j-Altzk
Clifton Williams, CPPB
Purchasing Manager
P. R. #24216
3/6/2025 gd
EXHIBIT "A"
CHANGE ORDER NO. 1
ORIGINAL AGREEMENT DATE: April 23, 2024
PROJECT DESCRIPTION: Renovation of both sets of restrooms in Lakefront Park on Pleasure
Island
REQUIRED REPAIRS:
#1: Deduct Original Railing Install
#2: Addition for Louver Removal.
#3: Addition for Decking Install.
#4: Addition for Concrete Walkway Install.
#5: Addition for Concrete Breaking and Repour.
#6: Addition for Railing Install.
#7: Addition for Plumbing and Tankless Water Heater Install.
#8: Addition for Breaker Install.
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT PRICE: $206,175.00
CURRENT CONTRACT PRICE: $206,175.00
The Contract Amount due to this CHANGE ORDER#1 will increase by: $28,547.50
The new CONTRACT AMOUNT including the CHANGE ORDER will be: $234,722.50
ORIGINAL CONTRACT DAYS: 86
NEW CONTRACT DAYS: _235
SIGNED AND AGREED TO on the day of , 2025.
GEOFILL CONSTRUCTION
By:
Print Name:
Title:
SIGNED AND AGREED TO on the day of , 2025.
CITY OF PORT ARTHUR
By:
Ron Burton,
City Manager
P. R. #24216
3/6/2025 gd
EXHIBIT "B"
MOM
GEO ILL
.. construction
Proposal
March 6, 2025
Property Name: Pleasure Island Restrooms
Address: 444 4th St
Port Arthur, TX 77642
Description: Change Order
-Deductive Change Order - (-$10,500.00) - Railings not installed
-Additive Change Order:
1. Louver Removal - Install plywood, install studs to support plywood, cover
in hardi-siding, hardi-trim around, paint all four areas. ($4,680.00
materials and labor)
2. Decking Install - Replace damaged roof decking in unforeseen areas of the
roof, approximately 500-600 sq ft. across both buildings. ($6,222.50
materials and labor)
3. Concrete walkways - Initial walkways were spec'd with 65 linear ft. of
walkway, design change led to 39 additional linear ft. of additional
walkway. ($3,055.00 materials and labor)
4. Concrete breaking repour associated with plumbing - Demo and removed
concrete in the interior of the buildings around toilets, inside of plumbing
chase to free up pipes and AC repour. ($3,445.00 materials and labor)
5. Railing Detail - Install newly designed railings to be secured on to
concrete walkways. ($4,745.00.00 materials and labor)
6. Plumbing Change - Install two new tankless water heaters, 1 per building.
Run associated piping. Demo out existing cast iron piping. Install new
copper piping, Installed new PVC piping. Reconfigured toilet outflow
piping. All work done across two buildings ($14,950.00 materials and
labor)
7. Electrical Charge - Add additional breakers and upgrade breaker sizing.
Wire and run new lines for hot water heaters. ($1,950.00)
Geofill Material Technologies dba Geofill Construction
Mailing Address:P.O.Box1o03,Cibolo,TX 78108
990o Doerr Lane,Schertz,TX78154
210-599-310o Fax: 210-599-3107
Total: $28,547.50
Authorized Signature
Submitted by: Justin Ellington
Bid does not include any hidden or unforeseen issues or damage. Issues
will be addressed upon written consent from management.
No sheetrock repair or paint included in bid unless noted. Repairs not
guaranteed to match existing color, unless otherwise stated.
One year warranty included on workmanship and materials. Warranty does
not cover acts of God. Bid good for (30) days.
I
I
Geofill Material Technologies dba Geofill Construction
Mailing Address:P. O.Box10o3, Cibolo, TX781o8
990o Doerr Lane,Schertz, TX78154
210-599-310o Fax: 210-599-3107