INTEROFFICE MEMORANDUM
Date: February 21, 2025
To: The Honorable Mayor and City Council
Through: Ronald Burton, CPM, City Manager
From: Flozelle C. Roberts, EIT, MEng,MBA, CPM, Public Works Director C6(
RE: P.R.24191 —Authorizing the City Manager to purchase a generator from enerac
Industrial Power of Waukesha, Wisconsin.
Introduction:
The intent of this agenda item is to seek the City Council's authorization to purchase a 50 kW
standby generator with installation for the Landfill Division.
Background:
The Public Works Landfill Division is required to stay in compliance with the Texas
Commission on Environmental Quality(TCEQ). The landfill must report all waste disposal to
TCEQ, and it is imperative that all buildings maintain power at all times for this purpose. City
Council approved the purchase of this equipment in the 2024-2025 fiscal year budget's capital
equipment schedule.
Budget Impact:
Generac Industrial Power of Waukesha,Wisconsin,which maintains contract number 092222-
GNR with the Sourcewell Cooperative Purchasing Contract,provided a competitive quote for
a 50 kW standby generator with installation for $47,432.00. The Landfill's Equipment
Account, 403-50-320-8522-00-00-000,will fund the equipment.
Recommendation:
It is recommended that the City of Port Arthur's City Council approve PR 24191 authorizing the
City Manager to purchase a generator with installation for the Public Works Landfill Division
from Generac Industrial Power of Waukesha, Wisconsin, through the Sourcewell Cooperative
Purchasing Contract.
"Remember,we are here to serve the Citizens of Port Arthur"
444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
PR 24191
2/21/2025 JAM
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
PURCHASE A GENERATOR WITH INSTALLATION FROM
GENERAC INDUSTRIAL POWER FOR THE LANDFILL
DIVISION THROUGH THE SOURCEWELL COOPERATIVE
PURCHASING CONTRACT NUMBER 092222-GNR FOR
$47,432.00. FUNDS ARE AVAILABLE IN THE LANDFILL'S
EQUIPMENT ACCOUNT NUMBER 403-50-320-8522-00-00-000.
WHEREAS, the Public Works—Landfill Division is required to stay in compliance with
the Texas Commission on Environmental Quality(TCEQ); and,
WHEREAS,the Landfill's continuous operation is imperative, and lapses in power could
hinder these operations; and,
WHEREAS, the City Council approved the purchase of this equipment in the 2024-2025
fiscal year budget's capital equipment schedule; and,
WHEREAS, Chapter 271 of the Texas Local Government Code allows a city, by
resolution of its governing body, to participate in cooperative purchasing programs as an
alternative to a formal bid process; and,
WHEREAS, per Resolution Number 13-556, the City of Port Arthur is authorized to
participate in cooperative purchasing with JCB Sourcewell (formerly National Joint Powers
Alliance) Cooperative Purchasing Program; and,
WHEREAS,Generac Industrial Power of Waukesha,Wisconsin is a dealer and part of the
Sourcewell Cooperative Purchasing Program under JCB Sourcewell Contract Number 092222-
GNR, and submitted a quote for a generator with installation to provide power to both buildings
at the landfill in the amount of$47,432.00 (attached hereto as Exhibit A).
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR,TEXAS:
THAT,the facts and opinions in the preamble are true and correct; and,
PR 24191
2/21/2025 JAM
Page 2 of 3
THAT,the City Manager of the City of Port Arthur is hereby authorized to purchase a 50
kW standby generator with installation from Generac Industrial Power of Waukesha, Wisconsin,
through the Sourcewell Cooperative Purchasing Contract for$47,432.00; and,
THAT,funding for this purchase is available in the Landfill's Equipment Account Number
403-50-320-8522-00-00-000; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ,ADOPTED AND APPROVED this the day of , A.D.
2025 at a meeting of the City of Port Arthur,Texas,by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Thurman Bill Bartie
Mayor
ATTEST:
Sherri Bellard, TRMC
City Secretary
APPROVED AS TO FORM:
Roxann Pais Cotroneo, Esq.
City Attorney
PR 24191
2/21/2025 JAM
Page 3 of 3
APPROVED i A I MINIS RATION:
Ronald Burton, CP
City Manager
loze le C oberts, E Eng, A, CPM
Director f Public W
APPROVED AS TO THE AVAILABILITY OF FUNDS:
tudiZet4
Clifton E. illiams,Jr., CP143
Purchasing Manager
C ie3)
Lyn Boswell, CMA-CM, MA
Director of Finance
PR#24191
Exhibit
A
GENERACa Sourcewell
ENCHGY S1S'EMS -'--- ------"'- '-'"'
* INDUSTRIAL Awarded Contract
I Con,ract tt 092222-GNR
February 27,2025 RV2
City of Port Arthur Public Works Department
Brad Brown
Drainage Superintendent
Brad.brownPportarthurtx.gov-409-549-0738
Jorge A. Morales
Landfill Environmental Operations Manager
Jorge.morales( portarthurtx.gov -409-736-1383
Reference: CITY OF PORT ARTHUR LANDFILL SD50
Clarifications
• Undetermined flood zone requirements-EST taking exception/not included in scope
• Concrete pad size= 11'L X 5'W x 2' deep
• Generator will cover the 2 small buildings on site as discussed during site walkthrough
Project details&narrative:
• Partnership to execute a turnkey solution with A&A for(1) 50kw diesel&(1)ATS
• A&A is responsible for system sizing and equipment selection based on site walkthrough
• Project will follow Sourcewell guidelines under contract#092222-GNR for equipment
• Customer Sourcewell Member ID#61648
• Generac Gencoonect#20957502/dp
• Turnkey package price only, prices listed below are not intended for individual sale
Quantity 1 -Generac Industrial diesel-4-cylinder 3.3L engineStationary Emergency-Standby rated
• 50 kW Rating,wired for 120/240 VAC single phase, 60 Hz
• Permanent Magnet Excitation
• UL2200/ EPA Certified-SCAQMD Certified
• Standard Weather Protective Enclosure,Steel
• Power Zone 410 Digital Control Panel for Single Generators
• Primary MLCB, 80%rated thermal-magnetic, 200 Amp
• Battery Charger, 10 Amp, NFPA 110 compliant, installed
• 110 AH,925 CCA Group 31 Battery,with rack, installed
• Block heater STD 1500W
• 120V GFCI and 240V Outlet
• 24" 132 Gallon Double-Wall UL142 Basetank(no fuel included/provided by EndUser)
1 of 4
• Std set of 3 Manuals
• Standard 2-Year Limited Warranty
• Freight to site -offloading by A&A
• Basic Start up(after installation is complete)
Quantity 1 -TX Series Automatic Transfer Switch
• 200 Amp, 2 pole, 120/240 VAC single phase,60 Hz,with 2-Wire Start Circuit
• 3 Owner's Manuals
• Controller and Circuit Breaker Covers, Padlockable, Black
• NEMA 3R Enclosure w/Enclosure Heater
• Service Entrance Rated
• In Phase Only Transfer
• Standard two year basic warranty
Quantity 1 — Istallation&Services (Item#2 below)
• Freight to Site&std start up by EST(after install is complete and fueled)
• Customer Training(during the scheduled startup)
• Warranty registration
• Product offloading and setting
• Installation Servcies byA&A—Josh Marceaux
o Scope incldues /200A service increase as discussed durign site visit
• house keeping pad concrete size= 11'L X5'W x 2' deep
• Requried project trenching
• Labor/manpower
• Installation materials(pipe,wire and misc)
• Permits
• Misc. Materials required for install and commision of above described
equipemnt. EST provided (1)50kW Industrial Generac generator and (1)
200amp transfer switch.
Sourcewell;•
Awarded Contract
Contract#092222 GNR
Sourcewell Project Pricing:
Item #1 Generac Equipment SD50 & 200AATS $27,717.00
Item #2 Site Services &A&A Installation $19,715.00
Project total investment for the above equipment $47,432.00
(Not including any applicable tax)
Installation Exclusions:Aluminum Conduit, Generator,ATS,gas meter upgrades
and any unforeseen problem with existing circuitry.
2 of 4
Notes
Estimated Delivery:Generator—after approved submittals and written release for production.
Prices valid for 30 days from above date
Terms/Start Up/Delivery:
Generac Dealer Startup included (for Generator)—Inspection for warranty and building load
transfer test during normal business hours(8AM—5PM).This includes one roundtrip within 150
miles of the Generac dealer's facility during normal business hours; additional mileage and/or
testing can be quoted separately.Additional trips required due to incomplete site preparation will
be invoiced to the customer at the dealer's prevailing service rate.
Clarifications and Exceptions:
1. Offloading and placement of the generator is not included and is the responsibility of the
purchaser.
2. EST suppliers and installation vendors will be paid when paid from the City
3. Diesel to be provided by City of Port Arthur)
4. Any unforeseen problems with existing site or electrical circuitry that affect the
completion, change is scope of supply and/or projects cost will be invoiced to the
End User
5. A&A takes responsibility for sizing the system and turnkey solution.Any errors or emissions
in the scope of supply or materials will be the responsibility of A&A
6. This proposal is based on specification of drawings.
7. Generator installation services are not included and are the responsibility of the purchaser.
This includes all related mechanical piping(exhaust or fuel systems),electrical conduit and
electrical wiring.
8. Generator preventative maintenance services are not included and are the responsibility of
the purchaser.
9. NETA acceptance testing, harmonic content testing,insulation resistance testing, infrared
scanning and/or ground fault testing are not included in this proposal.Standard factory
testing and standard on-site testing at unity power factor are included.
10. Coordination study,3rd party site testing, protective relay calibration,settings, etc. are not
included in this proposal.
11. Fuel is not included in this proposal unless specifically listed above. Diesel fuel is required
for startup and testing of generator and will be the responsibility of the purchaser.
12. All permitting, including Air Quality Management District(AQMD or APCD),will be the
responsibility of the purchaser.
13. Installation of exhaust silencer(if removed for shipping)shall be the responsibility of the
installing contractor.
14. Breaker and automatic transfer switch lugs are provided per the factory offerings and
submittal information per UL2200 and UL1008 approvals. Projects that require lug changes
will be done by others at their expense.
3 of 4
15. Proposal does not include federal, state,or local sales, use, property,TERP,or excise taxes.
In lieu of such taxes,the purchaser must provide the seller a tax exemption certificate
acceptable to the proper taxing authorities prior to the order being processed
16. Lead times listed in this proposal are an estimate of current factory production schedules
and should be verified at time of order release.
Lead time: 10- 13 Weeks+Installation time
Terms and Conditions
Net 30 days, subject to review and approval by our Credit Dept. Payment obligations are not
dependent or contingent upon the manner in which purchaser may receive payment from others.
No retainage against this order will be permitted unless agreed to ahead of time.Warranty is invalid
without factory start up.
Start up will be done during normal business hours.Additional charges will be applied to start ups
requested on weekends or off normal business hours.
Sincerely,
Chris Johnson
Regional Sales Manager—Industrial Sales
(713)-416-9500
Chris.johnsonPenergysystems.com
Acceptance of Quote
Prior to ordering equipment or services, please sign and return as a confirmation of the above terms
and conditions.