Loading...
HomeMy WebLinkAboutPR 24213: APPROVAL OF A DEDUCTIVE CHANGE ORDER FOR THE GENERATOR AT THE OPERATIONS CENTER City of ort rthuir www.PortArthurTx.gov INTEROFFICE MEMORANDUM Date: March 27, 2025 To: The Honorable Mayor and City Council Through: Ronald Burton, CPM, City Manager '� From: Flozelle Roberts, EIT, MEng, MBA, CPM, Director of Public Works RE: P.R. 24213 — Approval of a Deductive Change Order for the Generator at the Operations Center Introduction: This agenda item requests the Council's approval of change order number one to remove the relocation and installation of a City Hall generator with platform and security fencing to the Operations Center. Background: Resolution 24-489 awarded the contract to renovate the Operations Center's interior to Daniels Construction of Beaumont, Texas. The contract also included the alternative bid to move and install a generator from City Hall to the Operations Center. During the construction, staff received a quote for the purchase and installation of a new generator with platform and security fencing significantly less than the bid to move and install the generator at City Hall. Staff, therefore, requests the approval of this deductive change order of$251,871.00 to remove bid alternate number one, Move Generator & Install at Operations Center, from the contract. Staff will present a separate resolution (PR 24242) for purchasing another generator, which recognizes a cost savings of$135,476.00. "Remember,we are here to serve the Citizens of Port Arthur" 444 46 Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294 Budget Impact: The original contract amount was $1,434,548.00. Following the deductive change order for $251,871.00, the new contract amount will be $1,182,677.00. Recommendation: Staff recommends the approval of PR 24213 approving change order number one to remove the relocation and installation of a City Hall generator with platform and security fencing to the Operations Center. "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 PR 24213 03/27/2025 FCR Page 1 of 3 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND DANIELS BUILDING & CONSTRUCTION, INC. OF BEAUMONT, TEXAS, FOR THE REMOVAL OF THE GENERATOR INSTALLATION IN THE OPERATIONS CENTER RENOVATION PROJECT DECREASING THE TOTAL CONTRACT AMOUNT BY $251,871.00 TO A NEW CONTRACT AMOUNT OF $1,182,677.00; ACCOUNT NUMBER 307-21-049-8512-00-10-000, PROJECT NUMBER BU0001- CON. WHEREAS,per Resolution Number 24-489,the City Council awarded a contract for the renovations of the Operations Center, including the relocation of an existing 200kW diesel generator at City Hall to the Operations Center, to Daniels Building & Construction, Inc. of Beaumont, Texas, in the amount of$1,434,548.00; WHEREAS, staff received a quote to install a 150kW generator with a platform and security fencing for a cost savings of$135,476.00 from the accepted bid amount; and, WHEREAS, Daniels Building & Construction, Inc. has submitted deductive Change Order Number One(1)to remove the relocation of a City Hall generator to the Operations Center attached hereto as Exhibit A to the Operations Center Renovation project in the amount of $251,871.00 to a new total of$1,182,677.00; and, NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR,TEXAS: THAT,the facts and opinions in the preamble are true and correct; and, THAT,the City Manager of the City of Port Arthur is hereby authorized and directed to approve deductive Change Order Number One (1) to the contract with Daniels Building & PR 24213 03/27/2025 FCR Page 2 of 3 Construction, Inc. of Beaumont, Texas, in the amount of $251.871.00 to a new total of $1,182,677.00; and, THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ,ADOPTED, AND APPROVED this the day of , A.D. 2025, at a meeting of the City of Port Arthur, Texas, by the following vote: Ayes: Mayor: Councilmembers: Noes: Thurman Bill Bartie Mayor Attest: Sherri Bellard, TRMC City Secretary APPROVED AS TO FORM: Roxann Pais Cotroneo, Esq. City Attorney PR 24213 03/27/2025 FCR Page 3 of 3 APPROVED FOR ADMI ISTRATION: Ronald Burton, CP City Manager .04 / Flo e ' :•erts, I ' Eng, MBA, CPM Director o ' .lic Wo APPROVED AS TO AVAILABILITY OF FUNDS: 0046 Lynda Boswell, ICMA-CM,MA Director of Finance Clifton E. Williams,Jr., CPPB Purchasing Manager P.R.No. 24213 DANIELS D BUILDING & CONSTRUCTION, INC. P.O. BOX 20878 - BEAUMONT, TEXAS 77720-0878 - PHONE (409)838-3006 - FAX(409)838-9006 Attn: Cade Spell Date: 3/19/2025 Long Architecture Project: Port Arthur Operations 755 S. 11th St. STE 255 Proposal Request: No. 8 Beaumont, Tx 77701 Re: To delete the entire Alt. #1 cost Deduct for Demolition of generator pad and roof, Build new generator platform, move and install existing generator .... Deductive total: $ (251,871.00) Subtotal $ (251,871.00) Total this Proposal Request: No. 8 $ (251,871.00) Additional Days: Please indicate your acceptance by signing below. Sincerely, Tony Goss xc: Clayton Ard Jr. Daniels Building & Construction, Inc. xc: Charissa Lewis Accepted by Long Architecture Accepted by City Of Port Arthur Date Date 03/19/2025 / /