Loading...
HomeMy WebLinkAboutPR 23969: PORT ACRES DRAINAGE IMPROVEMENT PROJECT CHANGE ORDER NO. 5, ALLOCO 455 CALENDAR DAYS, FUNDING IS NOT IMPACTED City of ort rtlt«r T.rus www.PortArthurTx.gov INTEROFFICE MEMORANDUM Date: April 10,2025 To: The Honorable Mayor and City Council Through: Ron Burton, City Manager From: Pamela D. Langford, Assistant City Manager-Operations/Director of Developmental Services RE: PR No. 23969: Port Acres Drainage Improvement Project—Change Order No. 5: The addition of four hundred fifty-five (455)calendar days to the project changing the original contract completion date of August 12,2025 to the new contract completion date of November 9,2026. Project No. DR1PO3A. Introduction: The intent of this Agenda Item is to seek Port Arthur City Council's approval for the City Manager to execute Change Order No.5 with Allco,LLC,(Allco)of Beaumont,Texas,for the addition of four hundred fifty-five (455)calendar days to the project, changing the original contract completion date of August 12, 2025 to the new contract completion date of November 9, 2026. Project No.DR1P03A. Background: Pursuant to Resolution No. 18-231, the City of Port Arthur adopted the 2018 Disaster Recovery and Resiliency Plan (DRRP) for recovery activities following Hurricane Harvey. The City of Port Arthur, as part of DRRP recovery activities, identified flood and drainage problems within the community of Port Acres that were in dire need of mitigation and repair. The Port Acres Project was let for bidding. Pursuant to Resolution No. 23-485, the City of Port Arthur's City Council approved awarding the Port Acres Drainage Improvement Project to the lowest responsible bidder, which was Allco, LLC, of Beaumont,Texas,for the amount of$34,891,106.81.City staff,Arceneaux,Wilson&Cole(AWC)of Port Arthur,Texas,and Allco,LLC,of Beaumont,Texas,performed Value Engineering on the project proposal, lowering the contract price by$1,736,424.04 in order to keep it within budget. Pursuant to Resolution No. 24-032,the City of Port Arthur's City Council approved Change Order No. 1, that detailed the Value Engineering Breakdown from Allco, LLC, (Allco) of Beaumont, Texas, that reduced the contract amount of $34,891,106.81 by $1,736,424.04, to the new contract amount of $33,154,682.77. "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 S:\Engineering\PUBLIC WORKS\PW-ENGINEERING\C.I.P.PROJECTS\Year Z023\DRAINAGE PROJECTS\Port Acres\Change Orders\Change Order 5\Agenda Memo Port Acres CO 5.doa The Port Acres Drainage Improvement Project encountered additional costs due to necessary relocations of existing infrastructure. These relocations are critical to ensure successful completion and to avoid conflicts with the proposed drainage improvements. The additional costs for the project are essential to achieve the project's goals and ensure durability. Given the current workload of City personnel, outsourcing these tasks is the most feasible and efficient solution. To that end, a Field Order No. 1 was issued to Allco ensuring that critical work would continue since work stoppage at this juncture would be impractical, impact safety to the community, and incur excessive costs. Field Order No. 1 informed the City Manager of the work that was required with the understanding that it would go to the Port Arthur City Council in the form of Change Order No. 2. Pursuant to Resolution No. 24-302, Change Order No. 2, approved by Port Arthur's City Council, was submitted by Allco for the relocation of the sanitary sewer services and sewer main, and the addition of eighteen (18) calendar days. Change Order No. 2 increased the contract amount by $159,385.00 from $33,154,682.77 to the new contract amount of$33,314,067.77. Additionally, Change Order No. 2 added eighteen(18)calendar days amending the original completion date of June 25,2025 to the new completion date of July 13,2025. Pursuant to Resolution No. 24-339, Change Order No. 3, approved by Port Arthur's City Council, was submitted by Allco for the installation of a sanitary sewer main on 64th Street,the addition of fifteen (15) calendar days and the addition of 150 LF of water line relocations for the amount of$196,037.00. Change Order No. 3 also increased the contract amount of$33,314,067.77 by $196,037.00 to the new contract amount of$33,510,104.77. Additionally, Change Order No. 3 added fifteen(15) calendar days to the original contract completion date of July 13,2025, changing it to the new contract completion date of July 28,2025. Pursuant to Resolution No. 24-512, Change Order No. 4, approved by Port Arthur's City Council was submitted by Allco for the relocation of a water lateral and replacing a fire hydrant, adding corrugated pipe, reduction in linear footage of RCB, relocating sanitary sewer service, and the addition of a storm conflict structure,for the amount of$55,790.42,changing the previous contract amount of$33,510,104.77 to the new contract amount of$33,565,895.19. It was necessary to issue a Field Order to perform the work in order to keep the project safe and on schedule. To that end, an Emergency Letter, dated October 25, 2024, was submitted to the City Manager approving the Field Order with the change order subsequently going before Council. Additionally, Change Order No. 4 added fifteen (15) calendar days to accommodate the additional work performed by the Field Order,changing the previous contract completion date of July 28,2025 to the new contract completion date of August 12,2025. Change Order No. 5 is being submitted by Allco,for the addition of four hundred fifty-five(455)calendar days to the project's originally scheduled reduction of days, utility relocation delays,and weather related delays that were beyond control. Under the provisions of the contract Section F—General Conditions,Article 54.Time for Completion and Liquidated Damages-Item"d"(Pages F 21-22)... "The Contract Time will be extended in an amount equal to time lost due to delays beyond the control of the CONTRACTOR if a claim is made therefore as provided and if approved therefore by Engineer. Such delays shall include acts of neglect by the OWNER or others performing additional work, or by acts of God or of the public "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 enemy,fire,floods,epidemics,quarantine restrictions,strikes,labor disputes,sabotage, or freight embargoes." The calculation of 455 calendar days was determined using the Days Lost formula in the contract under Appendix A:Form For Request of Time Extension. Change Order No. 5 proposes to change the original contract completion date of August 12, 2025 to the new contract completion date of November 9,2026. Budget Impact: Funds are not impacted by this request. Project No. DR I PO3A. Recommendation: It is recommended that the City of Port Arthur's City Council approve PR No.23969,authorizing the City Manager to accept Change Order No. 5 from Allco, LLC, of Beaumont, Texas, for the addition of four hundred fifty-five (455) calendar days to the project, changing the original contract completion date of August 12,2025 to the new contract completion date of November 9, 2026. Project No.DR1P03A. "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 PR No. 23969 3/6/2025 mje Page 1 of 5 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 5 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND ALLCO, LLC, OF BEAUMONT, TEXAS, FOR THE PORT ACRES DRAINAGE IMPROVEMENT PROJECT, TO ADD FOUR HUNDRED FIFTY- FIVE (455) CALENDAR DAYS, CHANGING THE ORIGINAL CONTRACT COMPLETION DATE OF AUGUST 12, 2025, TO THE NEW CONTRACT COMPLETION DATE OF NOVEMBER 9, 2026. FUNDING IS NOT IMPACTED. PROJECT NO. DR1P03A. WHEREAS, pursuant to Resolution No. 18-231, the City of Port Arthur (City) adopted the 2018 Disaster Recovery and Resiliency Plan (DRRP) for recovery activities following Hurricane Harvey; and, WHEREAS, the DRRP included mitigation planning and investment in infrastructure to rebuild/repair streets, utilities, public facilities, water, sewer, and drainage; and, WHEREAS, the community of Port Acres was selected as an area that has experienced significant flooding due to rain events, flash flooding and drainage related issues; and, WHEREAS, pursuant to Resolution No. 20-023, the engineering firm of Arceneaux, Wilson & Cole, LLC (AWC) of Port Arthur, Texas, was approved to provide a master drainage plan, provide design specifications, and provide construction management services for the Port Acres Drainage Project; and, WHEREAS, the Port Acres Drainage Improvement Project was let for bidding with Allco, LLC, of Beaumont, Texas, being the lowest qualified bidder for $34,891,106.81; and, WHEREAS, pursuant to Resolution No. 23-485, the City of Port Arthur's City Council approved awarding the Port Acres Drainage Improvement Project to Allco, LLC, (Allco) of Beaumont, Texas; and, S,\L n;veering,P Ubu:..vOkt s\Ph-t NGINEittiN ',.L .YkUECTS\Year 2023\DRAINAGE PROJECTS\Port Aaer\Change Orders\Change Order 5\PR 23969 Pat Acres CO 5.doa PR No.23969 3/6/2025 mje Page 2 of 5 WHEREAS, pursuant to Resolution No. 24-032, the City of Port Arthur's City Council approved Change Order No. 1 for the performance of value engineering by City staff, AWC, and Allco, LLC, of Beaumont, Texas, decreasing the contract amount of $34,891,106.81 by $1,736,424.04 to the new contract amount of $33,154,682.77; and, WHEREAS, pursuant to Resolution No. 24-302, the City of Port Arthur's City Council approved Change Order No. 2 for the relocation of the sanitary sewer services and sewer main; increased the contract amount by $159,385.00 from $33,154,682.77 to the new contract amount of $33,314,067.77 and added eighteen (18) calendar days amending the original completion date of June 25, 2025 to the new completion date of July 13, 2025; and, WHEREAS, pursuant to Resolution No. 24-339, Change Order No. 3, approved by Port Arthur's City Council, was submitted by Allco, LLC, for the installation of a sanitary sewer main on 64th Street, the addition of fifteen (15) calendar days and the addition of 150 LF of water line relocations for the amount of $196,037.00; and, WHEREAS, Change Order No. 3 also increased the contract amount of $33,314,067.77 by $196,037.00 to the new contract amount of $33,510,104.77 and added fifteen (15) calendar days to the original contract completion date of July 13, 2025, changing it to the new contract completion date of July 28, 2025; and, WHEREAS, pursuant to Resolution No. 24-512, Change Order No. 4, approved by Port Arthur's City Council, was submitted by Allco, LLC, of Beaumont, Texas, for the relocation of a water lateral and replacing a fire hydrant, adding corrugated pipe, reduction in linear footage of RCB, relocating a sanitary sewer service, and the addition of a storm conflict structure, for the amount of $55,790.42 changing the previous contract amount of $33,510,104.77 to the new contract amount of $33,565,895.19; and, PR No. 23969 3/6/2025 mje Page 3 of 5 WHEREAS, a Field Order was issued addressing revisions to the drainage project to keep the project safe and on schedule; and, WHEREAS, an Emergency Letter dated October 25, 2024, addressing the Field Order was prepared, submitted to, and approved by the City Manager with the change order subsequently going before Council; and, WHEREAS, the Port Acres Drainage Improvement Project, to date, has encountered several delays due to the relocation of essential utilities, including water, sewer, gas, and existing industrial pipelines along with adverse weather conditions that have severely impacted progress, see Exhibit A; and, WHEREAS, an extension of time is necessary to address delays to ensure that the drainage improvements are completed effectively to benefit the residents of Port Acres and the City of Port Arthur, as a whole; and, WHEREAS, under the provisions of the contract Section F — General Conditions, Article 54. Time for Completion and Liquidated Damages-Item "d" (Pages F 21-22), extension of time in an amount equal to time lost due to delays beyond the control of the Contractor is recognized; and, WHEREAS, Change Order No. 5, is being submitted by Allco, LLC, of Beaumont, Texas, to add four hundred fifty-five (455) calendar days to the original contract completion date of August 12, 2025 changing it to the new contract completion date of November 9, 2026, using the Days Lost formula under Appendix A: Request for Time Extension, see Exhibit B; and, WHEREAS, approval of PR No. 23969 for Change Order No. 5 is herein deemed an appropriate action; now, therefore, 5:\Engineering\PUBLIC WORKS\PW-ENGINEERING\C.I.P.PROJECTS\Year 2023\DRAINAGE PROJECTS\Port Acres\Change Orders\Change Order 5\PR 23969 Port Acres CO 5.dorx PR No. 23969 3/6/2025 mje Page 4 of 5 BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the facts and opinions in the preamble are true and correct; and, THAT, Change Order No. 5 is herein approved and the City Manager is hereby authorized to execute said Change Order No. 5 to the contract between the City of Port Arthur and Allco, LLC, of Beaumont, Texas; and, THAT, Change Order No. 5 adds four hundred fifty-five (455) calendar days to the original contract completion date of August 12, 2025 changing it to the new contract completion date of November 9, 2026; and, THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED this the day of , A.D. 2025, at a meeting of the City of Port Arthur, Texas by the following vote: Ayes: Mayor: Councilmembers: Noes: Thurman Bill Bartie ATTEST: Mayor Sherri Bellard City Secretary PR No. 23969 3/6/2025 mje Page 5 of 5 APPROVED AS TO FORM: APPROVE OR DMINISTRATION: Roxann Pais Cotroneo, Esquire Ron Burton, City Attorney City Ma er APPROVED AS FOR AVAILABILITY OF FUNDS: 014-) Lynda (Lyn) Boswell, MA, ICMA-CM Director of Finance John n tella, PE City En eer (1114112, r,D Clifton Williams, CPPB Purchasing Manager S:\Engineering\PUBLIC WORKS\PW-ENGINEERING\C.I.P.PROJECTS\Year 2023\DRAINAGE PROJECTS\Port Acres\Change Orders\Change Order 5\PR 23969 Port Acres CO 5.docx EXHIBIT A elm MMARCENEAUX WILSON&COLE engineering I surveying I planning MEMORANDUM Date: February 11, 2025 To: City of Port Arthur From: Marc A. Ochoa, PE / Senior Project Manager Project: Port Acres Subdivision Drainage Improvements Subject: Request for Time Extension Purpose: This memo is to formally request an extension of 455 calendar days for the Port Acres Drainage Improvement project.The extension is necessary due to unforeseen delays and additional work required to complete the project as detailed below. Original Schedule Reduction: As previously agreed,the contractor accepted an accelerated schedule with the understanding that an extension would be granted upon demonstrating substantial progress.The original schedule was reduced by 180 calendar days before the contract was awarded. However, multiple unforeseen delays have significantly impacted on the project timeline, necessitating this request for an extension. Utility Relocation Delays: During construction, the contractor has encountered several delays due to the relocation of essential utilities,including water, sewer, gas,and existing industrial pipelines.These delays have accounted for an estimated 30 calendar days. Weather-related Delays: Additionally, adverse weather conditions have severely hindered progress.To date,the contractor has been unable to work for a total of 124 calendar days due to weather-related conditions. 409 724.7888 3120 Central Mall Drive Port Arthur,TX 77642 Engineering Surveying amrceng.tom F-16194 10194049 lox invc ,4111,1" The following table provides a breakdown of the weather-related delays per month from March 2024 to January 2025: Month Weather Delay Days March 2024 0 April2024 22 May 2024 35 June 2024 7 July 2024 20 August 2024 8 September 2024 0 October 2024 8 November 2024 1 December 2024 8 January 2025 15 Estimated Future Delays: These delays currently account for an additional 11 months to the project. Based on an observed average of 11 weather-related delay days per month, it is estimated that an additional 121 calendar days of rain-related delays should be anticipated and accounted for in the project timeline. Total Breakdown: The following table provides a breakdown of the additional days requested: Category Additional Days Original Schedule Reduction 180 Utility Relocation Delays 30 Weather Delays to Date 124 Estimated Future Weather Delays 121 Total Additional Days 455 Revised Schedule Completion: The current contract completion date is August 12, 2025.With the addition of 449 calendar days due to the outlined delays,the revised completion date would be November 9, 2026. This extension is necessary to ensure the successful and high-quality completion of the Atm T+If Port Acres Drainage Improvement Project while mitigating the impact of uncontrollable factors on the construction schedule. Conclusion: Given these circumstances,we respectfully request that the City of Port Arthur grant a time extension to allow for the successful completion of the project without compromising quality or safety.This extension is necessary to address delays beyond the contractor's control and to ensure that the drainage improvements are completed effectively to benefit the residents of Port Acres.The contractor remains committed to accelerating the schedule whenever possible. We appreciate your consideration of this request and look forward to your prompt response. Please do not hesitate to reach out if further information or discussion is required. Sincerely, 77. 1eVele2%&-- Marc A. Ochoa, PE Senior Project Manager EXHIBIT B CITY OF PORT ARTHUR Public Works Engineering DATE: MARCH 6,2025 PROJECT: PORT ACRES DRAINAGE IMPROVEMENT PROJECT OWNER: CITY OF PORT ARTHUR CONTRACTOR: ALLCO,LLC OF BEAUMONT,TEXAS CHANGE ORDER NO.: 5 THE FOLLOWING CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE HEREBY MADE: Adjust the Estimated Quantities to reflect the Actual Quantities used in the completion of the project: Original Item Description Unit Quantity Unit Price Original Amount Total Added New Amount 1 ADDITION OF FOUR HUNDRED FIFTY-FIVE(455)CALENDAR DAYS NO FUNDS ARE IMPACTED TOTAL CHANGE ORDER $ - PREVIOUS CONTRACT AMOUNT $33,510,104.77 NEW CONTRACT $33,565,895.19 AMOUNT ORIGINAL CONTRACT AMOUNT: $ 34,891,106.81 TOTAL AMOUNT OF CHANGE ORDER NO.1: S i 2,736,424.04j TOTAL AMOUNT OF CHANGE ORDER NO.2: $ 159,385.00 TOTAL AMOUNT OF CHANGE ORDER NO.3: $ 196,037.00 TOTAL AMOUNT OF CHANGE ORDER NO.4: $ 55,790.42 PERCENT OF CHANGE ORDER NO.1: -a.98%C PERCENT OF CHANGE ORDER NO.2: 0.46% PERCENT OF CHANGE ORDER NO.3: 0.56% PERCENT OF CHANGE ORDER NO.4: 0.16% PERCENT OF CHANGE ORDER NO.5: 0.00% TOTAL PERCENT OF CHANGE ORDERS NOS.1,2,3,4&5: -3.80` NEW CONTRACT AMOUNT: 33 5.5.- .19 CONTRACT COMPLETION DATE:WI=r 9 2026 FOUR HUNDRED FIFTY-FIVE(455)CAL DAR DAYS HAVE BEEN ADDED TO CHANGE ORDER • • PAREPARED BY: - I APPROVED BY: d qi M.Jennifer dwards,1 ,S,MPA;CIP Manager Jr hn Cannatella,PE,City Engineer APPROVED BY: APPROVED BY: Brandon Harrison,ALLCO,LLC. Marc Ochoa,Senior Project Manager,AWC APPROVED BY: APPROVED BY: Dr.Hani Tohme,PE,Consultant Clifton Williams,CPPB,Purchasing Manager APPROVED BY: Ron Burton,City Manager S:\Engineering\PUBLIC WORKS\PW-ENGINEERING\C.I.P.PROJECTS\Year 2023\DRAINAGE PROJECTS\Port Acres\Change Orders\Change Order 5\Port Acres CO 5 11, REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES CITY OF PORT ARTHUR DATE: , 20 MONTH OF: , 20 CITY of PORT ARTHUR,TEXAS PUBLIC WORKS DEPARTMENT P.O.BOX 1089 CITY of PORT ARTHUR,TEXAS 77641-1089 ATTENTION: Engineering Division Gentlemen: We request extension of completion time on our Contract due to the days of work lost as specified(list dates actually lost: do not include days not normally worked such as Saturdays, Sundays,or holidays): Dates Lost: Days Lost( )/ 5 x 7= Calendar Days Requested Reasons for Request: Contractor By: Approved for extension of calendar days. Disapproved. Date: , 20 CITY OF CITY OF PORT ARTHUR,TEXAS BY: City Manager Distribution by City Original:Public Works Engineering Cc: Engineer Contractor CPA Federally Funded