Loading...
HomeMy WebLinkAboutPR 24304: CHANGE ORDER NO. 1 WITH CONSTRUCTION ZONE OF SOUTHEAST TEXAS CITY of art rthur Texas www.PortArthurTx.gov DEPARTMENT OF DEVELOPMENT SERVICES INTEROFFICE MEMORANDUM Date: March 25, 2025 To: The Honorable Mayor and City Council Through: Ronald "Ron" Burton, CPM, City Manager From: Pamela D. Langford, CPM, Assistant City Manager— Operations/Director of Development Services RE: P.R. NO. 24304 — A proposed resolution authorizing Change Order No. 1 with Construction Zone of Southeast Texas Introduction: To request City Council consideration and approval of Proposed Resolution No. 24304 authorizing the City Manager to execute Change Order No. 1 to the construction contract with Construction Zone of Southeast Texas for the Animal Services Center Building. This Change Order increases the contract amount by $426,585.34, resulting in a revised contract total of$7,791,585.34, and extends the contract time by 214 calendar days. Background: On July 20, 2023, Tolunay-Wong Engineers performed Geotechnical Engineering Construction Materials Testing at the site of the future Animal Services Center to evaluate the condition of the soil and subsurface materials. The testing was conducted to ensure compliance with applicable construction standards and to determine the site's overall suitability for vertical development. As requested by the city, Tolunay-Wong Engineers has continued to monitor construction activities throughout the duration of the project. During a routine inspection on March 27, 2025, a Tolunay-Wong representative determined that the soil in the northeast corner of the construction site was incompetent at a depth of four feet. To comply with environmental and structural engineering standards and to support the construction of the visitors' parking lot, this area must be excavated an additional foot to reach competent material. The excavated area will then need to be backfilled with stabilizer or select fill material before any concrete can be poured. This unexpected soil condition has introduced further delays to the construction schedule. In addition to the geotechnical issue, the contractor encountered several unforeseen site conditions that significantly impacted the project timeline. Most notably, during initial site preparation, a large volume of buried concrete pilings—remnants from the former St. Mary Hospital facility—was discovered. These materials had not been previously identified in the site evaluation and required considerable excavation and removal. As a result, the structural engineering team had to revise the civil design plans to incorporate site stabilization and appropriate backfill to support the future foundation of the Animal Services Facility. This redesign and remediation effort contributed to measurable construction delays. Compounding these issues, progress was also hindered by multiple severe weather events that created unsafe conditions and restricted access to the site. The following list details significant weather occurrences that contributed to work stoppages between April 2024 and April 2025: Documented Inclement Weather Events: • April 28-29, 2024: Heavy rainfall and coastal flooding with wind gusts up to 40 mph; tides rose 2.5 feet above normal. • May 2, 2024: Flash flooding caused by 2-6 inches of rainfall; resulted in road closures and widespread power outages. • May 13, 2024: Severe thunderstorms with wind speeds exceeding 60 mph, large hail, and increased flood risk. • May 16-17, 2024: Regional derecho event with 100 mph winds and multiple tornadoes impacting Southeast Texas. • December 26, 2024: Strong storms with gusts up to 60 mph and 1-inch hail; tornado watch issued. • December 28, 2024: EF-3 tornado passed just south of Port Arthur, causing extensive regional damage and reported injuries. • January 21, 2025: A rare blizzard dropped 4.5 inches of snow—marking the second-highest snowfall ever recorded for the area. These extreme weather events created hazardous working conditions, causing site shutdowns and delaying progress. In addition, March 27, 2025, findings of incompetent soil in the northeast quadrant of the site require further environmental remediation and backfill before the construction of the public parking area can proceed. These steps will involve additional excavation, geotechnical testing, environmental clearance, and material placement to ensure the long-term stability and safety of the structure. Throughout the course of construction, City staff and the contractor have provided several formal updates to the City Council to ensure transparency and accountability. These efforts were particularly responsive to inquiries made by Councilmember Thomas Kinlaw, III, who requested additional discussion and presentations to keep the public informed: • September 17, 2024: A joint presentation by staff and the contractor was delivered to the City Council providing a status update and summary of initial construction challenges. • September 24, 2024: Councilmember Kinlaw requested a follow-up discussion on the project, where the presence and removal of buried concrete pilings were identified as a key factor contributing to early delays. • October 3, 2024: Another update was requested by Councilmember Kinlaw to further address the construction timeline and weather-related complications. • December 3, 2024: The contractor presented a detailed update on project conditions, weather disruptions, and adjustments to the construction sequence. Additionally, on April 9, 2025, a brief video highlighting visible progress at the Animal Services Center construction site was distributed via email to all City Councilmembers. The video served to provide a visual update on current construction activities and reaffirm the continued advancement of the project despite prior setbacks. These updates, along with routine monitoring and third-party engineering oversight, reflect the City's commitment to transparency and effective communication in managing this critical capital improvement effort. It is not uncommon for large-scale public construction projects to experience delays stemming from unforeseen site conditions, permitting complexities, weather disruptions, or necessary design modifications. In such cases, contract extensions are typically considered to ensure compliance with engineering standards and to allow for the delivery of a safe, high-quality final product. The imposition of liquidated damages contractual penalty for missed deadlines—is generally reserved for cases where the contractor fails to meet revised completion milestones that have already accounted for justified delays. Given the substantiated factors contributing to the current delay—including geotechnical remediation, the removal of legacy materials, and extended weather impacts—it is both reasonable and appropriate to grant a time extension at this phase of construction rather than pursue liquidated damages. As a result of these cumulative delays, the contractor is requesting a 214-calendar-day extension to allow for the continued and compliant construction of the Animal Services Center. This request is submitted in conjunction with Change Order No. 1, which reflects the associated costs of excavation, remediation, and additional site preparation work. Budget Impact: The Port Arthur City Council previously approved a total project budget of $9.65 million for the construction and furnishing of the new Animal Services Center. This funding was made available through the sale of Certificates of Obligation issued by the City in two series: $6.65 million from the 2021 Series and an additional $3 million from the 2023 Series. The original construction contract with Construction Zone of Southeast Texas was awarded in the amount of $7,365,000.00. The proposed Change Order No. 1 would authorize an increase of$426,585.34 to that amount, resulting in a revised contract total of$7,791,585.34. If approved, this change will leave a remaining project budget of $1,858,414.66, which will be used to complete the remaining phases of the project. This includes the purchase and installation of office furniture, specialized equipment, and other apparatus necessary for the operation and functionality of the Animal Services Center. Funds are available in Capital Improvement Project/Buildings Account No. 307-21- 049-8512-00-10-000; Project No. BU0008 to support this change order and continue progress toward the successful completion of the facility. Recommendation: Staff recommend that the City Council approve Proposed Resolution No. 24304 authorizing the City Manager to execute Change Order No. 1 with Construction Zone of Southeast Texas, increasing the total contract amount to $7,791,585.34 and extending the construction period by 214 days. P.R. NO. 24304 04/25/2025 PDL Page 1 of 5 RESOLUTION NO. A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PORT ARTHUR, TEXAS, AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT WITH CONSTRUCTION ZONE OF SOUTHEAST TEXAS FOR THE CONSTRUCTION OF THE ANIMAL SERVICES CENTER BUILDING, INCREASING THE CONTRACT AMOUNT BY $426,585.34 TO A NEW TOTAL OF $7,791,585.34, AND EXTENDING THE CONTRACT TIME BY 214 DAYS; FUNDING AVAILABLE IN CAPITAL IMPROVEMENT PROJECT/BUILDING ACCOUNT NO. 307-13-041-8512-00- 10-000; B00008 PENDING APPROVAL OF BUDGET AMENDMENT PO 7331. WHEREAS, on February 27, 2024, the City Council of the City of Port Arthur approved a contract with Construction Zone of Southeast Texas for the construction of the Animal Services Center Building; and, WHEREAS, Tolunay-Wong Engineers conducted a Geotechnical Engineering Construction Materials Testing on July 20, 2023, and has continued to monitor construction activities at the site; and, WHEREAS, on March 27, 2025, Tolunay-Wong Engineers determined that the soil in the northeast corner of the site was incompetent at a depth of four(4)feet, requiring additional excavation and backfill with stabilizer or select fill material to meet construction standards for the visitors' parking lot; and, WHEREAS, during construction, the contractor encountered several unforeseen conditions, including the removal of pre-existing concrete footings from previous property use, as well as delays caused by multiple severe weather events between April 2024 and April 2025, which have impacted construction activities; and, WHEREAS, the requested Change Order No. 1 will increase the contract amount by $426,585.34 for a revised contract total of $7,791,585.34, and extend the contract time by 214 calendar days; and, P.R. NO. 24304 04/25/2025 PDL Page 2 of 5 WHEREAS, funding for this change order is available in Capital Improvement Project/Buildings Account No. 307-21-049-8512-00-10-000; Project No. B00008 pending approval of Budget Amendment PO 7331. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: Section 1. That the facts and opinions in the preamble are true and correct. Section 2. That the City Council hereby authorizes the City Manager to execute Change Order No. 1 to the contract with Construction Zone of Southeast Texas, increasing the contract amount by $426,585.34 for a revised total of $7,791,585.34 and extending the contract duration by 214 calendar days. Section 3. That a copy of the executed Change Order No. 1 shall be filed in the office of the City Secretary and Development Services Department. Section 4. That this Resolution shall be effective immediately upon its passage. READ, ADOPTED, AND APPROVED on this day of April, A.D., 2025, at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote: AYES: Mayor: Councilmembers: , Noes: Thurman Bill Bartie, Mayor ATTEST: Sherri Bellard, TRMC, City Secretary P.R. NO. 24304 04/25/2025 PDL Page 3 of 5 APPROVED AS TO FORM: Roxann Pais Cotroneo, City Attorney APPROVED F.1.i MIN = RATION: Ronald "Ro Trton, CPM, City Manager APPROVED AS TO AVAILABILITY OF FUNDS: 1)a'() PO ve.,; 646.(ieee -76•2) Ow, (f_,,AIL yn•a Boswell, Finance Director Clifton Williams, CP B, Purchasing Manager P.R. NO. 24304 04/25/2025 PDL Page 4 of 5 Attachment Change Order#1 R CZ PURCHASE ORDER CONSTRUCTIONZONE n OF SOUTH EAST TEXAS WORK ORDER 231 N Twin City Highway,Nederland,TX 77627 111 CHANGE ORDER Phone:(409)729-8989,Fax:(409)729-8987 To: City of Port Arthur BACK CHARGE Owner: City of Port Arthur Project Name: Animal Services Contact: Pamela D. Langford-Purchasing Manager Address: Phone: City/St/Zip: DATE DATE REQ. TERMS CZ JOB NUMBER COST CODE 4/24/2025 QUANTITY DESCRIPTION UNIT PRICE TOTAL PCR# 1 VE Items $ (67,564.00) 2 Site Changes $ - 4 In line sanitizer $ 8,275.00 5 Demo concrete $ 11,167.00 6 Added Hydrant $ 16,828.00 7 ASI#01 $ 15,941.00 9 Gear $ 49,350.00 11 R5 ASI#04 spread footings $ 139,058.00 12 General Conditions for PCR#115R $ 93,447.00 13 Unsuitable Soil at Visitors Parking per report from TWE $ 95,011.00 NOTE: If city adds CO#1 R to the contract,and not use out of contingency use this number 217 Added calendar days April 27,2025,new date November 27,2025 This work order is also subject to the A107 Contract between Construction Zone and City of Port Arthur including AIA 201 General Conditions&Construction Zone Sub total $ 361,513.00 Subcontractor Agreement available at www.cziglobal.com/plan.html 15% $ 54,226.95 Bonds&Ins. 3% $ 10,845.39 Total $ 426,585.34 Original Contract Amount $ 7,365,000.00 Net Change by Previous Change Orders $ - Contract Amount Prior to this Change Order $ 7,365,000.00 This Change Order Amount $ 426,585.34 New Contract Amount including this Change Order $ 7,791,585.34 ACCEPTED BY CUSTOMER SIGNATURE AUTHORIZED CZ REPRESENTITIVE Project Manager TITLE DATE TITLE P.R. NO. 24304 04/25/2025 PDL Page 5 of 5 Attachment OP Tolunay-Wong Engineers,Inc. TOLUNAY WING 2455 W.Cardinal Drive,Suite Beaumont,Texas 77705 ENGINEERS Ph:(409)840-4214 Fax:(409)840-4259 REPORT OF CONSTRUCTION SURVEILLANCE SERVICES PROJECT: P.O. 307-21-049-8512-00-10-000 PAGE 1 OF 1 New Animal Shelter City of Port Arthur PROJECT NO.: 24.21.136 CLIENT: City of Port Arthur REPORTNO.: 164436 Attn: Darlene Thomas-Pierre DATEOFSERVICE: 03/27/2025 P. O. Box 1089 REPORTDATE: 03/28/2025 Port Arthur TX 77641 SERVICES: To monitor daily construction activities by the client/contractor. REPORT OF TESTS On March 27, 2025, TWE representative Michael Hebert reported to the above project site to monitor construction activities as requested by our client. On this date, the Contractor continued excavation for south parking lot. Today's site visit observed this area concluded existing soil in northeast corner to be incompetent at depth of four (4) feet, and additional excavation is required to reach compentent material. Soil was noticably pumping with personnel walking on and the same was witnessed with contractor's equipment. Confirming with geotechnical report, contractor is clear to excavate an additional one (1) foot to reach competent material. Original recommendation was to excavate and install eight (8) inches of stabilized or one (1) foot of select fill below concrete paving for parking lot area. Technician: Michael Hebert, Project Manager TOLUNAY-WONG ENGINEERS, INC. Report Distribution: (1)City of Port Arthur (1)John Polk �(1)Tim Meehan 7- — / -' Michael Hebert Project Manager Our letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced except in full without the 1099MH approval of the testing laboratory. The use of our name must receive our written approval. Our letters and reports apply only to the sample tested and/or inspected,and are not indicative of the quantities of apparently identical or similar products. F M ] o : i h .s o o ao os a4I 1 z U p o m � a' c. m o a . 0 0 0of a - apa o a z w a h 0 0 E- o Ar p - z m O U w..., ' Mil : DIIIIIIIHIHIIIIHhIIII -DIIIIIHIHIIHhIIIIIIII •• !PIuuu FO ,f N 1 qy .. - in" H18 %; a,s m .. 1.7 , 00 w E, lio Fa 0 10 0 , N 3 z Lu ' aoz F. • re Si co W r a p 3A180 53iV