INTEROFFICE MEMORANDUM
Date: July 11, 2025
To: The Honorable Mayor and City Council
Through: Ronald Burton, City Manager
From: George Davis, Director of Pleasure Island
RE: P.R. No. 24425 — Acceptance of Close Out Documents Submitted by Florida
Floats, Inc., DBA Bellingham Marine for the Completion of the Pleasure Island
Marina Rehabilitation Project.
Introduction:
The purpose of this agenda item is to request City Council approval of P.R. No. 24425,
authorizing the acceptance of close-out documents submitted by Florida Floats, Inc., doing
business as Bellingham Marine of Jacksonville, Florida, and to approve the release of retainage
in the amount of$59,872.50 for the completed rehabilitation of the Pleasure Island Marina.
Background:
Pursuant to Resolution No. 24-061, the City of Port Arthur entered into a contract with Florida
Floats, Inc., DBA Bellingham Marine of Jacksonville, Florida, for the rehabilitation of the
Pleasure Island Marina, with an original contract amount of $1,382,900.00. Subsequently,
Resolution No. 24-169 authorized Change Order No. 1,reducing the scope of work to align with
budget constraints. This resulted in a decrease of$185,450.00, adjusting the total contract value
to $1,197,450.00.
The rehabilitation work has now been completed to the satisfaction of staff, and the contractor
has submitted all required close-out documentation. Florida Floats, Inc. has also formally
requested the release of the retainage amount of$59,872.50.
Budget Impact:
Funding in the amount of$59,872.50 is available in account number 307-00-000-2050-00-00-000.
Recommendation:
It is recommended that the City Council approve P.R. No. 24425, authorizing the City Manager
to accept the submitted close-out documents and approve the release of retainage in the amount
of$59,872.50 to Florida Floats, Inc., DBA Bellingham Marine of Jacksonville, Florida, for the
successful completion of the Pleasure Island Marina rehabilitation project.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O. Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
P. R. No. 24425
7/11/25 gd
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO ACCEPT THE CLOSE-OUT DOCUMENTS
SUBMITTED BY FLORIDA FLOATS, INC., DBA
BELLINGHAM MARINE OF JACKSONVILLE, FLORIDA,
AND TO APPROVE THE RELEASE OF RETAINAGE IN
THE AMOUNT OF $59,872.50 FOR THE COMPLETION OF
THE PLEASURE ISLAND MARINA REHABILITATION
PROJECT; FUNDING IS AVAILABLE IN ACCOUNT
NUMBER 307-00-000-2050-00-00-000
WHEREAS, pursuant to Resolution No. 24-061, the City of Port Arthur entered into a
contract with Florida Floats, Inc., DBA Bellingham Marine of Jacksonville, Florida, for the
rehabilitation of the Pleasure Island Marina with a projected budgetary impact of$1,382,900.00;
and,
WHEREAS, pursuant to Resolution No. 24-169, Change Order No. 1 was approved to
reduce the scope of work so that the project cost could align with the original amount budgeted,
resulting in a decrease of$185,450.00 to a new total contract amount of$1,197,450.00; and,
WHEREAS, the revised scope of work was reviewed and approved by Arceneaux,
Wilson& Cole, LLC,the construction managers for the project; and,
WHEREAS, Florida Floats, Inc., DBA Bellingham Marine of Jacksonville, Florida has
submitted the Certificate of Substantial Completion dated April 6, 2025 for the work to which
the Certificate applies has been inspected, authorized, and declared to be complete in accordance
with the contract documents (Exhibit "A"); together with the Contractor's Certificate and
Release (Exhibit "B"), the Contractor's Certificate of Warranty (Exhibit "C"), Contractor's
Certificate of Debts Paid (Exhibit "D"), Engineers Certificate of Completion ( Exhibit "E") and
Contractors Certificate of Guarantee(Exhibit"F"); and,
WHEREAS, the retainage for the project, 5% of the work completed and billed,has been
submitted for release by Florida Floats, Inc., DBA Bellingham Marine of Jacksonville, Florida,
in the amount of$59,872.50 (Exhibit"G"); and,
WHEREAS, Florida Floats, Inc., DBA Bellingham Marine of Jacksonville, Florida, has
completed the contracted project to the satisfaction of the Pleasure Island staff (Exhibit "H");
and,
P.R.No.24425
7/11/25 gd
WHEREAS, the City Council finds it appropriate to accept the close-out documentation
and authorize the release of retainage; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR,TEXAS:
Section 1. That the facts and opinions in the preamble are true and correct.
Section 2. That the City Council hereby authorized the City Manager to hereby
accept the Certificate of Substantial Completion dated April 6, 2025 (Exhibit "A"), together with
the Contractor's Certificate and Release (Exhibit "B"), the Contractor's Certificate of Warranty
(Exhibit "C"), Contractor's Certificate of Debts Paid (Exhibit "D"), Engineers Certificate of
Completion(Exhibit"E") and Contractors Certificate of Guarantee(Exhibit"F").
Section 3. That the City Council hereby authorizes the release of retainage in the
amount of$59,872.50 to Florida Floats, Inc., DBA Bellingham Marine(Exhibit"G").
Section 4. That the City Manager is further authorized to execute the Certificate of
Acceptance (Exhibit "H") onCity behalf of the of Port Arthur for the rehabilitation of the
Pleasure Island Marina..
Section 5. That a copy of the caption of this Resolution be spread upon the Minutes
of the City Council.
READ, ADOPTED AND APPROVED THIS day of , A.D.,
2025, at a Regular Meeting of the City Council of the City of Port Arthur,by the following vote:
AYES: (Mayor)
Councilmembers:
NOES:
Charlotte M. Moses,
Mayor
P.R.No. 24425
7/11/25 gd
ATTEST: APPROVED AS TO FORM:
Sherri Bellard Roxann Pais Cotroneo
City Secretary City Attorney
APPRO l ED •R i I TRATION:
APO"
Rona7`iro ,V7M George Davis,MA, CPM
City Manages• Director of Pleasure Island
APPRO D AS TO THE AVAILABILITY OF FUNDS:
yn yn osw 1, MA, ICMA- M Clifton E. Williams, Jr.,
Director of Finance Purchasing Manager
P.R.No. 24425
7/11/25 gd
EXHIBIT "A"
CERTIFICATE OF SUBSTANTIAL COMPLETION
Purchase Order No.:_24,061 /PLC 481
Project Name: Pleasure Island Marina Repairs
Contractor: Florida Floats, Inc dba Bellingham Marine
Description of Work: Replace and rvair co ncrete floating docks
The work performed under this contract has been reviewed and found to be substantially complete.The
date of substantial completion is hereby established as April 6,2025 .
KNOW ALL MEN BY THESE PRESENTS:
1.) The stage of construction where, in the opinion of the City of Port Arthur, all items of the work necessary
to enable the assets to be utilized without restrictions for the purpose for which the asset was constructed
have been completed; and
2.) All pay items are complete and all necessary testing as required by the Laws and Regulations and/or
Contract Documents have all been completed.
Punch List
All list of items to be completed or corrected, prepared by the CONTRACTOR and verified and amended by the
ENGINEER, is attached hereto.The failure to include any items on such list does not alter the responsibility of
the CONTRACTOR to complete all work in accordance with the contract documents. The CONTRACTOR shall
complete or correct the work on the list of items attached hereto within in 60 days from the above date of
substantial completion.The responsibilities shall be as set out in the Contract Documents or on the attached
hereto. If not specified in and an attachment or in the Contract Documents the CONTRACTOR is responsible for
maintenance, utilities and insurance.
,7e ve ,'-att Jul 3,2025
Florida Floats, Inc dba Bellingham Marine .,_.,CONTRACTOR NAME SIGNATURE DATE
RECOMMENDED FOR ACCEPTANCE
ENGINEER NAME SIGNATURE DATE
The City of Port Arthur accepts the work as Substantially Complete. City of Port Arthur, Department of Parks and
Recreation.
PROJECT MANAGER SIGNATURE DATE
CITY ENGINEER SIG TURE DATE
G�Qoe, aw,5 7 /25
PLEASURE ISLAND DIRECTOR SIG ATURE DATE
P. R. No. 24425
7/11/25 gd
EXHIBIT "B"
CONTRACTOR'S CERTIFICATE AND RELEASE
FROM: Florida Floats. Inc dba Bellingham Marine
(Name of Contractor)
TO: City of Port Arthur
(Owner)
REFERENCE CONTRACT NO.24-601 /PIC 481
CONTRACT ENTERED INTO THE 1st DAY OF April 2024 BETWEEN THE
CITY OF PORT ARTHUR AND Florida Floats, Inc
OF Jacksonville, FL
FOR THE PROJECT Pleasure Island Marina Repairs
KNOW ALL MEN BY THESE PRESENTS:
1.) The undersigned hereby certifies that there is due from,and payable by,the Owner to the Contractor
under the contract and duly approve Change Orders and modification the balance of
$ 1,197,450.00
2.) The undersigned further certifies that in addition to the amount set forth in Paragraph 1,there are
outstanding and unsettled the following items which he claims are just and due and owing by the Owner
to the Contractor:
a. $59,872.50
b.
c.
d.
(Itemize claims and amounts due,if none,so state)
3.) The undersigned further certifies that all work required under this contract, including work required under
Change Order(s) numbered 2 , has been performed in accordance with the terms thereof, and that
there are no unpaid claims for materials,supplies,or equipment and no claims of laborers or mechanics
for unpaid wages arising out of the performance of this contract,and that the wage rates paid by the
contractor were in conformity with the contract provisions relating to said wage rates.
4.) Except for the amounts stated under Paragraphs 1 and 2 hereof,the undersigned has received from the
Owner all sums of money payable to the undersigned under,or pursuant to,the above-mentioned contract
or any modifications or changes thereof.
5.) That in consideration of the payment of the amount stated in Paragraph 1 hereof,the undersigned does
hereby release the Owner and Operator from any all claims arising under or by virtue of this contract,
except the amount listed in Paragraph 2 hereof due from the owner, provided however,that if any reason
the Owner does not pay the full amount stated in Paragraph 1 hereof,said deduction shall not affect the
validity of this release, but the amount so deducted shall be automatically included under Paragraph 2 as
an amount which the Contractor has not released but will release upon payment thereof. The Contractor
further certifies that upon the payment of the amount listed in Paragraph 2 hereof,and of an amount
which may be deducted from Paragraph 1 hereof,he will release the Owner and Operator from any and
all claims of any nature whatsoever arising out of paid contract modification thereof,and will execute
such further releases or assurances of the Owner and Operator may request.
1
IN WITNESS WHEREOF,the undersigned has signed and sealed this instrument this 3rd day of
July ,2025.
Florida Floats, Inc dba Bellingham Marine
(SEAL} (Contractor)
BY: t7e Bey Tkatt
(Signature)
Jeffrey Pratt/Vice President
(Printed Name/Title of Officer)
Jeffrey Pratt , being first duly sworn on oath,deposes and says, First, that, he/she is the
(Affiant)
Vice President of Florida Floats, Inc dba Bellingham Marine
(Title) (Name of Company)
Second,that he has read the foregoing certificate by him/her subscribed as Contractor's Certificate and Release
(Title)
of City of Port Arthur .
(Name of Company)
Affiant further states that the matters and things stated herein are true.
Jeffrey ?/-att
Jeffrey Pratt
(Affiant)
Subscribed and sworn to before me this 3rd day of July , 2025
My commission expires 3/20/2027 1)101cry
"a' rak
7
NOTARY State of Florida
2
P. R. No. 24425
7/11/25 gd
EXHIBIT "C"
CONTRACTOR'S CERTIFICATE OF WARRANTY
FROM: FLORIDA FLOATS, INC DBA BELLINGHAM MARINE
(Name of Contractor)
TO: CITY OF PORT ARTHUR
(Owner)
REFERENCE CONTRACT NO.: 24-061/PIC 481
CONTRACT ENTERED INTO THE 1ST__DAY OF APRIL 2024 BETWEEN THE
CITY OF PORT ARTHUR_ AND FLORIDA FLOATS, INC.
OF JACKSONVILLE. FL
FOR THE PROJECT _PLEASURE ISLAND MARINA REPAIR
KNOW ALL MEN BY THESE PRESENTS:
1.) FLORIDA FLOATS,INC does hereby guarantee all of the work done under the
(Name of Contractor)
above referenced contract to be free from faulty materials in every particular, and free from improper
workmanship, and against injury from proper and usual wear; and agrees to replace or re-execute without
cost to the Owner and Operator such work as may be found to be improper or imperfect, and to make
good all damage caused to other work or materials due to such required replacement or re-execution.
2.) This guarantee shall cover a period of one(1)year from the date of acceptance of all work under this
contract by Owner, as evidenced by the Contractor's Certificate of Completion.
3.) This Certificate is given in connection with the final payment under the contract between the Owner and
FLORIDA FLOATS, INC ,and with the knowledge that it will be relied upon in
(Name of Contractor)
Making such payment and that such payment would not be made except upon the truth of the matter
contained in this affidavit.
IN WITNESS WHEREOF,the undersigned has signed and sealed this instrument this 3RD day of
JULY ,2025.
FLORIDA FLOATS, INC
{SEAL} (Contractor)
e I'e Tratt
(Signature)
JEFFREY PRATT/VICE PRESIDENT
(Printed Name/Title of Officer)
1-Warranty
JEFFREY PRATT , being first duly sworn on oath,deposes and says, First,that, he/she is the
(Affiant)
VICE PRESIDENT of FLORIDA FLOATS INC DBA BELLINGHAM MARINE ,
(Title) (Name of Company)
Second,that he/she has read the foregoing certificate by him/her subscribed as CONTRACTOR'S
CERTIFICATE OF WARRANTY
(Title)
of CITY OF PORT ARTHUR .
(Name of Company)
Affiant further states that the matters and things stated herein are true.
,7e f1-ey ?ma
(Affiant)
Subscribed and sworn to before me this 3RD day of JULY ,2025.
My commission expires 3/20/2027
eanyPi*
Ida
.._:: camwIM37S98T
t,plm 27
NOTARY STATE OF FLORIDA
2-Warranty
P. R. No. 24425
7/11/25 gd
EXHIBIT "D"
CONTRACTOR'S CERTIFICATE OF DEBTS PAID
PROJECT: Pleasure Island Marina Repairs
LOCATION: Port Arthur,Texas
OWNER: City of Port Arthur
STATE OF TEXAS;
COUNTY OF JEFFERSON;
The undersigned hereby certifies that, except as listed below, payment has been made in full and all
obligations have otherwise been satisfied for all materials and equipment furnished for all work, labor,
and services preformed and for all known indebtedness and claims against the Contractor for damages
arising in any manner in connection with the performance of the Contract referenced above for which
the Owner's property might in a way be held responsible or encumbered.
Exceptions:_RetainaRe only ($59,872.50)
Contractor: Florida Floats, Inc dba Bellingham Marine/Jacksonville, FL
t7efYei -att
Signature:
Printed Name: Jeffrey Pratt, Vice President
Date: July 3, 2025
Subscribed and sworn to before me this 3rd day of July , 2025
My commission expires: 3/20/2027
MARCEY NESTER
Nolan,Public
Rite of Florida
••-• . cmmlm437s9a7
Ecru 3/ignon
NOTARY State of Florida
P.R.No. 24425
7/11/25 gd
EXHIBIT "E"
ENGINEER'S CERTIFICATE OF COMPLETION
Project: Pleasure Island Marina Repair
Date of Issuance: April 16th, 2025
Owner(s): City of Port Arthur
Owner's Project Number: PIC 481
Engineer: Arceneaux Wilson& Cole LLC
Contractor: FLORIDA FLOATS, INC DBA BELLINGHAM MARINE
This Engineer's Certificate of Completion applies to all Work under the Contract Documents or
to the following specified parts thereof:
To: City of Port Arthur
(OWNER)
And To:
(ENGINEER)
The Work to which this Certificate applies has been inspected by authorized representatives of
Owner, Contractor and Engineer, and that Work is hereby declared to be complete in accordance
with the Contract Documents on
April 16th 2025
DATE OF COMPLETION
Executed by Engineer on _�.,�����
iMCP•• OF •rF 4t1
JOE M.WILSON,JR. 0
I.I to�i.t c206 to•_iv o'
1%%VI. ENS.NG,•
07/17/2025
P. R.No. 24425
7/11/25 gd
EXHIBIT "F"
CONTRACTOR'S CERTIFICATE OF GUARANTEE
FROM: FLORIDA FLOATS, INC DBA BELLINGHAM MARINE
TO: CITY OF PORT ARTHUR
FOR: PLEASURE ISLAND MARINA REPAIRS
REFERENCE CONTRACT NO. 24-061 / PIC 481 ENTERED INTO THE 1ST
DAY OF APRIL 2024 , BETWEEN THE CITY OF PORT ARTHUR
AND FLORIDA FLOATS, INC
(CONTRACTOR)
OF JACKSONVILLE, FL
(CITY/STATE)
FOR: PLEASURE ISLAND MARINA REPAIR
(PROJECT)
KNOW ALL MEN BY THESE PRESENTS:
1. FLORIDA FLOATS, INC does hereby guarantee all of the work done under the
above referenced contract to be free from faulty materials in every particular, and free
improper workmanship, and against injury from proper and usual wear; and agrees to
replace or re-execute without cost to the Owner and Operator such work as may be found
to be improper or imperfect, and to make good all damage caused to other work or
materials, due to such require replacement or re-execution.
2. This guarantee shall cover a period of one (1)year from the date of acceptance of all work
under this Contract, as evidenced by the Engineer's Certificate of Completion.
IN WITNESS THEREOF, the undersigned has signed and sealed this instrument this the
3RD day of JULY , 2025.
FLORIDA FLOATS, INC
(COMPANY NAME)
,7ef!e matt
Jeffrey ran(Jul 202510 08 EDT)
(OWNER,SIGNATURE/TITLE)
Jeffrey Pratt,Vice President
(PRINT)
SUBSCRIBED AND SWORN to before me this 15th day of JULY
2025 .
My commission expires 3/20/2027
(DATE)
w�wsr�s►ea
Y NomrvPDblIc
-y _ Cute01 Fb,M
COmTfHH375987
Eepirea 3/20/202'
(NOTARY PUBLIC)
)1
P.R.No. 24425
7/11/25 gd
EXHIBIT "G"
4)
r
0 7
c
0
ai c a) m a)
-0a).00Nc �.c o o .
a) � o o 4_ o 0
3 @ 3L a ov U Tas
oca y a,00 . ..
y YL a) �oN ..L...0 c O Q C a
0 co
Y p L a) j• j,E 7 N C w c a) cs. in a) E ..:
S ( t o E 0 0 T Ln 0 > _ c N m
c 3 0 o U TEa N N a) c o `�v o p co
c)O Q 0 t6 ay a O p 2 .0 To N C W N OS - C
'-- -- "_'d -O fV w L� m - ao 0
a o o(6 to c o mu) ui ,°i N 0 a) U
-
U 4- aJ . oo o T a) a) N C U
N .(n
c----- ooscc°il5i Ua co3rnE m^ LLU UJ +• Y
w • 1—w OO o = a `
ui m doa0 Saar — oa)
o .0 c a) ai .NY mpo o a? I- v c
a) QEac 0 ygg H oN C. 0 U0 ,_
{ o
O d o i 2 0 ate) a)U •O o o D C N
o T . Q. L � a) °« a)w Ea) a)
CO o NLO a° : 11.!.. Q .o N,.:L..•LL a�iw O E O
%N N 0 0 3 O c) $W o 3 ! a) o O
0 0 a) oO E 1 0 __ O Ewa uv m €
N N w o O O O a) LL z a) c c 1"' c C c
O � Y ... Y-" O N W O aD 0 co) N (0
co U O L � � E N H' a C O O u U o a 7 O
..+ 3 ` • 'd O O U co N Q N. O) o w
o .. a) U a) N C.0 c 0 00 c m C 4..,
•� Z ,$ N 4= C OL '- L_ .n M LL O a w.c-2 O) V L C N o
co C a) CO O co O ih 1-U o-c•N 4_ c O w, N
p c o O O ' '0 U C E _c a) o i o Eft e O O L 'C
d v i) U L O N a) N .V p 'p_ W > p)O C (ts TO E C -p 0
U •n O C "6 U C T N a) U ..,, N a) T W C N E C
p n y o o C a) O O o N o r @ LL ° a� ' c0 c9
c Q a a` c) a) cU a3 H o (ai; •� � 8wc.,- a '' U c
0-+ ` C .a N a c U LL .O co W e .x00 W m 0
a) a) c ,� < o _ W� 0)0 >, o no �C o a)
.� C t6 0 >' @ ' N '. 42 O_ E Z O N p c0 ) N N .1 0 U U
Ce o `o E o • Z m U Z m E u aac) O roc •'• `� c'aj
L `� O t6 y O T m 7 O T Z p a) 2 o C T L o
c H .E o a.NL U m cncoZ � W e 0Qw.0) a -0 W CO HO a
.'
2
I--
C
O 0 0 0 O O O O O co0 0
Z 0 0 0 O co O c0 c[) 0 U) O co co o
O O co0 0 0 O O 0 f- (N.) O N O U)
W N 0 into V Efl S. N. N. fA C 0 0 6
to
E vOi 0) -a- CO co co O
d M O O) ,- in oi
U) c U7 U)
M CO CO
a O Of} d9 Efl E9 Efl ffl cfl
A/ N W
Y. st
`
O „ > o O O O 0
O O O
W d y d w 0 O O O O C
a`o t N O O c Efl to Efl
LL t 4F! lfl O
Q )y 0 c a CO
0 LL a
LL z Q '
O C co
1- _
P. E a) x
w � o a s Eco
�) CO
V — , o
13 �-- cS 2 M J 3 a`) o Y LO N C FO N
a)
wL U a U) o o 15
C a) o 0 as Q o
Q 0) a) Q `° a, mEt a)
s ° E E c :? cn m a- o w o a) 2 a) c
r W _ o) o as v a) g cc !•_ 0 o z d 2 y c
Z ¢ c a) a) o 1 .c m m a a) m o 0 s D v O . L
O_ O L O as U 0 a m ns T H a�i O C m a) V CO O a) •c o a T
l C J
r— x0 Q LL "La ~ w C a) j w CO ca D 7 E O E I L °-y m
a p o r V co0 to
L U c cn E cL rn 0 0 ai as 9 a x co F- cC O a�'i E �>' o)
U CU U 0 N r1' o (0 f6 N p)N O c
J U n W `o c? c U �° U C o0 0 0 W W CD ti aci c r,'o_ a .c
LL a) a) .-. C 'Es @ o o � TO ` a) i N o> Q 0
0. C coj Z c a) O O N O 0 7 N a as Z
Q. O c O ac O Z U H W' a H• J U co U CO S F TS c E° Z
Q H ci 0 0 Q o - N M 4 U) co N- ao 01 0
0000
0o O o 0 0
c 0 0 0 0 c
c
— 'm
'.,
a)
cG
0 0 0 0 0
N to to) O O O 0
4-+ O s O O O O 0
O cv N N V Vr r.
) °o o LL U
N CIf0
Lc O O m
O 4., H 0 0 0 0 0
000
Z 0 O
0 0
C U 0 06 0
• CO o 0 0000
C.) C0
= V
Q a 0000 0
0000 0
Q � O to tr) O 0
II G`1 I; LL to I-- I` to N
CIS O t9 + N N Cr) C' LO
C7 c a y CI w to cD to I;
E 00 ovc°Oom � ����k m
O co co~ is \A\
* .Cr
.? 1k1
%Q`?-' • � � •till LU
0000 % • Z oy. NO 0
o o o 0 i/n..• O � 0.01 a cV 0
U. 4 0 1-1 o �O. `\ J �IiWZu.Z� CN
• nMI ° 01� W
z �c„ o
0000
o tv 0000• 0
U) `w t(a
LU as
03 Q. d - C
CD m '-
a
co
co U o o 0 0 0
'c
co ` 7 C O to to O 46
o
O O O LC) I"- r tf) N
a d a W N N CO et
C .- V + tf) CO tr) ti
a.Z. Tr CO LC) CO
N E av
o <
> z U.
COas
E co
N O O O O O 00
n) aa) 0 to trio o
▪ M 3 7 N N M •d� to
�'
o U a) to co to n
O .c , t > CO u) a) O)
CA '0 ` vt In O (O
c t0 �O
C N N ..
'FIs co c c 2 c.
O a .0
W aci � 2a) U 0
W
I a co 7
co � > a
n `o .� 22 o a)0
ocl 0 a c U
Z c � s
o » � c O cn
f0 `) uN -ow@
0 co
t'
Q N U 0 �M ;- Q
C) L. tD -aU p c_.) c a) ca @ _ c
'vctvc a a a CO c) Q) O c
ZcCa7 0
—
0 CC S 0
9
O O E c- NM0
Z O O V U o Q Z
O. c CZ et) >
0
<0 D
P. R. No. 24425
7/11/25 gd
EXHIBIT "H"
CITY OF PORT ARTHUR, TEXAS
PLEASURE ISLAND DEPARTMENT
CERTIFICATE OF ACCEPTANCE FOR
Rehabilitation of the Pleasure Island Marina
To: Florida Floats, Inc., DBA Bellingham Marine
This document is to certify that the City of Port Arthur, Texas accepts the completion of the
rehabilitation of the Pleasure Island Marina, based on the recommendation of the City of Port
Arthur's Pleasure Island Department and receipt of the Certificate of Completion, Contractor's
Affidavit of All Debts Paid, Contractor's Certificate of Release, Contractor's Certificate of
Warranty executed by Florida Floats, Inc., DBA Bellingham Marine of Jacksonville, Florida.
Ron Burton, CPM
City Manager
Sherri Bellard
City Secretary
CERTIFICATE OF COMPLETION
Date: July 11, 2025
Project: Rehabilitation of the Pleasure Island Marina; Release of Retainage
To: All Concerned
I HEREBY CERTIFY THAT this project was completed on April 6, 2025 and that the work
was under periodic inspection during construction by an engineer and City staff. To the best of
my knowledge, the project was constructed substantially in accordance with the plans and
specifications.
Submitt by:
Georg Davis, CPM
Director of Pleasure Island
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294