HomeMy WebLinkAboutPR 24441: ATLANTA WATER LINE IMPROVEMENT PROJECT CHANGE ORDER NO. 3 City of or rtlru " INTEROFFICE MEMORANDUM Date: July 15, 2025 To: The Honorable Mayor and City Council Through: Ronald Burton, CPM, City Manager From: Calvin Matthews, P.E., Water Utilities Director RE: PR No. 24441 —Atlanta Water Line Improvement Project Change Order No. 3 Introduction: This Agenda Item is to seek the City Council's approval for Change Order No. 3 for the Atlanta Water Line Improvement Project with Global Drilling Inc. of Winnie, Texas. Background: The 16"Atlanta water line from 19th Street to 4th Street is the main water supply line for the downtown area of Port Arthur. Based on the work orders and the residents' concerns,the water line condition urgently needs rehabilitation. Arceneaux Wilson& Cole Engineer firm(AWC) provided professional services to design and construct a 20"water line replacement for the project. Resolution No. 24-021 awarded the project to Global Drilling Inc. of Winnie, Texas, for $2,377,477.00, and Arceneaux Wilson & Cole Engineer firm (AWC) of Port Arthur, Texas, is the project engineer and construction manager. Resolution No. 24-471 approved Change Order No. 1 to utilize directional drilling trenchless technology to install remaining portions of the new 20-inch water line to better accommodate construction plans. This change order increased the contract amount by $234,163.00 to a new contract amount of$2,611,640.00 and also extended the contract time by 90 days to a new total contract time of 270 days. Resolution No. 25-198 approved Change Order No. 2 to repair a major leak on the 16-inch waterline along Atlanta Avenue, repair a leaking 8-inch sanitary sewer line with bypass pumping, and install tie-ins to address previously unidentified underground utilities, increasing "Remember,we are here to serve the Citizens of Port Arthur" 1' �I I L• the contract amount by $109,900.00 to a new contract amount of$2,721,540.00 and extending the contract time by 90 days to the new total contract time of 360 days. AWC engineer, along with City Staff, is proposing Change Order No. 3 to address the increased installation requirements of six(6)proposed alleyway crossing tie-ins and for the field orders to repair water leaks on existing 2-inch and 6-inch waterlines, which increases the contract amount by $79,510.00 to the new total contract amount of$2,801,050.00. This Change Order also extends the contract time by 45 days for the installation requirements and repairs which prevents the mass water shutoff in the downtown area during the tie-ins installation. Budget Impact: The initial contract amount was $2,377,477.00 Change Order No. 1 increased the contract amount by $234,163.00 to the new contract amount of$2,611,640.00, increasing the change order percentage allowed by 9.8%. Change Order No. 2 increased the contract amount by $109,900.00 to the new contract amount of$2,721,540.00, increasing the change order percentage allowed by 4.6%to a total 14.4%. Change Order No. 3 will increase the contract amount by$79,510.00 to the new contract amount of$2,801,050.00, increasing the change order percentage allowed by 3.3%to a total 17.8%. Funding is available in Capital Improvement Projects Account No. 405-40-000-8516-00-00- 000,Project No.WS0019-CON,contingent upon the approval of budget amendment in Proposed Ordinance No. 7351. Recommendation: It is recommended that City Council approve Proposed Resolution No.24441 to approve Change Order No. 3 for the Atlanta Water Line Improvement project as discussed and/or outlined above. "Remember,we are here to serve the Citizens of Port Arthur" PR No. 24441 7/15/25 cm Page 1 of 4 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 3 TO THE ATLANTA WATERLINE IMPROVEMENT PROJECT WITH GLOBAL DRILLING INC. OF WINNIE, TEXAS, INCREASING THE CONTRACT AMOUNT BY $79,510.00 TO THE NEW TOTAL CONTRACT AMOUNT OF $2,801,050.00 WITH EXTENDED CONTRACT TIME OF 45 DAYS TO A NEW TOTAL CONTRACT TIME OF 405 DAYS; FUNDS ARE AVAILABLE IN CAPITAL IMPROVEMENT PROJECTS ACCOUNT NO. 405-40-000-8516-00- 00-000, PROJECT NO. WS-0019 CON, CONTINGENT UPON THE APPROVAL OF BUDGET AMENDMENT IN PROPOSED ORDINANCE NO. 7351. WHEREAS, pursuant to Resolution No. 24-021, the Atlanta Water Line Improvement Project was awarded to Global Drilling Inc. of Winnie, Texas, with a total projected budgetary amount of$2,377,477.00; and, WHEREAS, pursuant to Resolution No. 23-464, Arceneaux Wilson & Cole Engineering Firm (AWC) of Port Arthur, Texas, was hired as Design and Construction Engineer to oversee the project; and, WHEREAS, pursuant to Resolution No. 24-471, Change Order No. 1 was approved to utilize directional drilling trenchless technology to install remaining portions of the new 20-inch water line to better accommodate construction plans increasing the contract amount by $234,163.00 to a new contract amount of$2,611,640.00 and extending the contract time by 90 days to a new contract time of 270 days; and, WHEREAS, pursuant to Resolution No. 25-198, Change Order No. 2 was approved to repair a major leak on the 16-inch waterline along Atlanta Avenue, repair a leaking 8-inch sanitary sewer line with bypass pumping, and install tie-ins to address previously unidentified underground utilities, increasing the contract amount by $109,900.00 to the new total contract PR No. 24441 7/15/25 cm Page 2 of 4 amount of$2,721,540.00 with extended contract time of 90 days to the new total contract time of 360 days; and, WHEREAS, AWC is proposing Change Order No. 3 (EXHIBIT "A") due to the increased requirements for the installation of six (6) proposed alleyway crossing tie-ins that were affected by the further discovery of existing and abandoned underground utilities lines during construction, and additionally, for field orders to repair water leaks on existing 2-inch and 6-inch waterlines, which increases the contract amount by $79,510.00 to the new total contract amount of$2,801,050.00; and, WHEREAS, Change Order No. 3 also proposes a time extension of 45 days to address the aforementioned installation requirements and repairs which increases the total contract completion time to 405 days, and; WHEREAS, the total increased amount in the Change Orders, including the proposed Change Order No. 3, are within the maximum allowed 25% of the original contract amount (Exhibit"B"), as per the Texas Local Government Code Section 252.048(d). NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR,TEXAS: THAT,the facts and opinions in the preamble are true and correct; and, THAT, the City Council hereby approves Change Order No. 3 (EXHIBIT "A") to address the increased installation requirements of six (6) proposed alleyway crossing tie-ins and for the field orders to repair water leaks on existing 2-inch and 6-inch waterlines, increasing the amount by $79,510.00 to the new total contract amount of$2,801,050.00; and, PR No. 24441 7/15/25 cm Page 3 of 4 THAT, the City Council further approves Change Order No. 3 for a time extension of 45 days to the new total contract completion time of 405 days, due to the aforementioned installation requirements and repairs; and, THAT, the funding is available in Capital Improvement Projects Account No. 405-40- 000-8516-00-00-000, Project No. WS-0019, contingent upon the approval of budget amendment in Proposed Ordinance No. 7351; and, THAT, a copy of the caption of this resolution be spread upon the minutes of the City Council. READ, ADOPTED, AND APPROVED, this day of , 2025, AD, at a Regular Meeting of the City Council of the City of Port Arthur, Texas by the following Vote: AYES: Mayor: Councilmembers: • NOES: Charlotte M. Moses Mayor ATTEST: Sherri Bellard City Secretary PR No. 24441 7/15/25 cm Page 4 of 4 APPROVED AS TO FORM: Roxann Pais Cotroneo City Attorney APPRO F ADMINISTRATION: Ronald Burton City Mana Calvin atthews, P.E. Water Utilities Director APPROVED AS TO FUND AVAILABILITY: "YA tgli° y da(Lyn) Boswell, MA, ICMA-CM Finance Director 4/12 - Clifton, E. Williams Jr., CPPB Purchasing Manager EXHIBIT "A" (CHANGE ORDER NO. 3) .V.11klik 411PAIr ARCENEAUX WILSON&COLE engineering I surveying I planning July 15, 2025 Mr. Calvin Matthews, P.E. City of Port Arthur Director of Water Utilities 444 4th Street Port Arthur, Texas 77640 RE.. Proposal For Change Order No. 03 for A TLANTA WATER LINE IMPROVEMENTS AWC Job No. CPA-1160 Mr. Matthews: Attached is Change Order No. 3 for the Atlanta Water Line Improvements project. This change order is to increase the contract amount by $79,510.00 and extend the contract time by 45 calendar days. Due to the high density of both existing and abandoned underground utilities within the alleyway crossings, the Contractor has had to install additional water line length and bend fitting to navigate the proposed water line crossing tie-ins to the existing water line within the alleyway. During the design phase, the Engineer utilized both City resources and topographic survey data to map the existing utilities within the project area. However once in construction, the Contractor found several existing underground lines, both active and abandoned, that were unable to be previously located. Due to the congested area caused by these existing underground lines, six (6) proposed alleyway crossing tie-ins were affected. Also included in this change order are Field Orders in which the City requested the Contractor repair water leaks on existing 2-inch and 6-inch water lines along Atlanta Avenue. The City and Engineer have reviewed the proposed changes and agree they are within the budget and scope as requested. 409 724.7888 3120 Central Mall Drive Port Arthur,TX 77642 Engineering Surveying awceng.com F-16194 10194049 .411c1.114), *Mr This change order will extend the original contract time by 45 calendar days and increase the original contract amount by$79,510.00. We recommend that the City of Port Arthur authorize this change order to the contract as submitted. We have attached Change Order No. 3 which modifies the contract to reflect this change for your consideration and action. Should you have any questions or require additional information, please contact our office. ARCENEAUX WILSON&COLE LLC TEXAS REGISTERED ENGINEERING FIRM F-16194 Keith Zotzky, P. ., FM Vice President of Engineering Services Attached. Change Order#03 A'_ ♦lkiL mimic AriARCENEAUX WILSON&COLE r CHANGE ORDER NO. 3 DATE: July 15, 2025 JOB NO.: CPA-1160 AGREEMENT DATE: May 20, 2024 NAME OF PROJECT: Atlanta Water Line Improvements OWNER: CITY of PORT ARTHUR CONTRACTOR: GLOBAL DRILLING The following changes are hereby made to the CONTRACT DOCUMENTS: BASE BID 1. Remove 20x6 Tee between 17th Street and Gulfway Drive at$8,000/EA. (-$8,000.00) 1.1 Add 20x6 Cross between 17th Street and Gulfway Drive at$8,500/EA. ($8,500.00) 2. Add 20x8 Tee between 11th Street and Thomas Blvd at$8,500/EA. ($8,500.00) 2.1 Add 8" Gate Valve & Box between 11th Street and Thomas Blvd at$3,400/EA. ($3,400.00) 3. Add 20x6 Tee between 11th Street and Thomas Blvd at $8,000/EA. ($8,000.00) 3.1 Add 6" Gate Valve & Box between 11th Street and Thomas Blvd at$2,340/EA. ($2,340.00) ADDITIVE ALTERNATE A BID 1. Remove 20x6 Cross between 5th Street and 6th Street at$8,500/EA. (-$8,500.00) 1.1 Add 20x16 Cross between 5th Street and 6th Street at$15,000/EA. ($15,000.00) 2. Remove three (3) 6" Gate Valve & Box between 5th Street and 6th Street at $2,340/EA. (-$7,020.00) 2.1 Add two (2) 8" Gate Valve & Box between 5th Street and 6th Street at$3,400/EA. ($6,800.00) 3. Add 16" Gate Valve & Box between 5th Street and 6th Street at $18,500/EA. ($18,500.00) 4. Remove 62 LF of 6"Water Line between 5th Street and 6th Street at$60.00/LF. (-$3,720.00) 4.1 Add 62 LF of 8" Water Line between 5th Street and 6th Street at$105.00/LF. ($6,510.00) ADDITIONAL SCOPE ITEMS 1. Field Orders to address leaking 2" and 6" City Water Lines between 6th Street and 7th Street at $3,800/EA. ($7,600.00) 2. Installation of additional water line and bend fittings at 6 alleyway crossing tie-ins at $3,600/EA. ($21,600.00) TOTAL $79,510.00 CHANGE TO CONTRACT PRICE: ORIGINAL CONTRACT PRICE: $2,377,477.00 CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $2,721,540.00 The CONTRACT PRICE due to this CHANGE ORDER will be [increased] by: $79,510.00 The new CONTRACT PRICE, including this CHANGE ORDER, will be $2,801,050.00 1 of 2 __ a I I/V I CHANGE ORDER NO. 3Y Jul 15, 2025 ♦_/� ♦" Job No. CPA-1160 ARCENEAUX WILSON&COLE CHANGE TO CONTRACT TIME: ORIGINAL CONTRACT TIME: 180 Calendar Days CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 270 Calendar Days ORIGINAL DATE OF COMPLETION: February 15, 2025 ADJUSTED DATE OF COMPLETION: August 7, 2025 CONTRACT TIME due to this CHANGE ORDER will be increased by 45 Calendar Days The New DATE OF COMPLETION: September 21, 2025 No other Terms and Conditions of the Contract are changed as a result of this Change Order. Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred by Contractor in his performance of the work covered by the Change Order. RECOMMENDED BY ENGINEER: ACCEPTED BY: ARCENEAUX WILSON & COLE LLC (CONTRACTOR, OFFICER OR OWNER) GLOBAL DRILLING ACCEPTED BY: CITY of PORT ARTHUR 2 of 2 EXHIBIT "B" (Contract Current Status) Contract Current Status Contract Name: Atlanta Waterline Improvement Contractor: Global Drilling Contract#: 24-021 Original Contract Amount: $ 2,377,477.00 Allowed 25%of Contract: $ 594,369.25 Percentage of Percentage Allowed 25%of Amount Contract Amount Original Contract to Date Remaining Original Contract $ 2,377,477.00 $ 594,369.25 Change Order 1 $ 234,163.00 9.8% 9.8% $ 360,206.25 Change Order 2 $ 109,900.00 4.6% 14.5% $ 250,306.25 Change Order 3 $ 79,510.00 3.3% 17.8% $ 170,796.25 Total Change Orders to Date $ 423,573.00 17.8% New Contract Amount $ 2,801,050.00