HomeMy WebLinkAboutPR 24288: SS4 TRANSIT PLANNING STUDY City of Port Arthur
Transit Department
Memorandum
To: Ronald Burton, City Manager
From: Ivan Mitchell, Transit-Fleet Director
Date: July 31, 2025
Subject: P.R. 24288 — SS4 Transit Planning Study
Background:
Port Arthur Transit (PAT) was awarded a 2024 Safe Streets for All (SS4A) planning and
demonstration grant from the Federal Highway Administration (FHWA) to conduct a pedestrian
access to transit plan (the Plan). It is the first-ever look at pedestrian conditions for PAT
customers in City of Port Arthur. The pedestrian safety and quality of access to the transit stop is
as important as the ride itself. PAT is aware that for many transit customers, the walk to a bus
stop needs to be significantly improved. The Plan is PAT's first step to create an action plan that
will qualify for future FHWA, FTA, and TxDOT discretionary grant applications such as
implementation or demonstration grants.
The City's Purchasing Department advertised for qualified vendors in the Port Arthur News on
December 14, 2024, and December 21, 2024, to complete a transit planning study for PAT. The
City received and opened two (2) qualification packages from vendors to complete the transit
planning study. The two (2) packages were submitted from Huitt-Zollars, Inc. and the Solco
Group. After assessing each qualification package for experience, past performance, project
approach, and DBE availability the Solco Group received the highest scoring. Per resolution 25-
086, the City Council authorized the City Manager to enter contract negotiations with the Solco
Group of Port Arthur, Texas to complete PAT's SS4 transit planning study.
Recommendation: It is recommended City Council authorize proposed P.R. 24288. This
resolution would authorize the City Manager to execute a contract with the Solco Group of Port
Arthur, Texas to complete PAT's SS4 transit planning study.
Budgetary/Fiscal Effect: Funding to complete the transit planning study is funded by the FHWA at
80%federal($200,000.00)and 20%local($50,000.00), subject to FY26 budget approval.
P.R. 24288
07/31/2025 IM
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE A CONTRACT WITH THE SOLCO GROUP,
LLC. OF PORT ARTHUR, TEXAS TO COMPLETE PORT
ARTHUR TRANSIT'S (PAT) PEDESTRIAN ACCESS TO
TRANSIT PLANNING STUDY IN THE AMOUNT NOT TO
EXCEED $250,000.00. FUNDING IS AVAILABLE IN
TRANSIT CAPITAL ACCOUNT 401-70-500-5470-00-60-000,
OTHER CONTRACTUAL SERVICES WITH AN 80%
FEDERAL ($200,000.00) AND 20% LOCAL MATCH
($50,000.00), SUBJECT TO FY26 BUDGET APPROVAL.
WHEREAS, Port Arthur Transit("PAT")has been awarded funding from the United
States Department of Transportation, to be administered by the Federal Transit Administration
("FTA"), for the development of a Pedestrian Access to Transit Plan; and
WHEREAS, PAT recognizes that pedestrian safety and the quality of access to transit
stops are as critical to the customer experience as the transit service itself, and that for many
riders, the walk to a bus stop must be significantly improved; and
WHEREAS, the Pedestrian Access to Transit Plan represents PAT's first step toward
creating an actionable framework that will support eligibility for future discretionary grant
applications from the Federal Highway Administration("FHWA"), the FTA, and the Texas
Department of Transportation("TxDOT"), including implementation and demonstration grants;
and
WHEREAS, the City's Purchasing Division published a Request for Qualifications
("RFQ") in the Port Arthur News on December 14, 2024, and December 21, 2024, to solicit
proposals for the completion of the transit planning study; and
WHEREAS, two (2)qualification packages were received and evaluated jointly by the
Purchasing Division and PAT, with scoring results attached hereto as Exhibit"A"; and
WHEREAS,by Resolution No. 25-086, the City Council authorized the City Manager to
negotiate a contract with The Solco Group, LLC, the highest-scoring respondent to the RFQ; and
WHEREAS, the resulting contract between the City of Port Arthur and The Solco
Group, LLC is attached hereto as Exhibit"B".
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR, TEXAS:
THAT, the facts and opinions in the preamble are true and correct.
P.R. 24288
07/31/2025 IM
THAT, the City Manager is hereby authorized to execute a contract with the Solco
Group, LLC. of Port Arthur, Texas, to complete PAT's SS4 transit planning study in the amount
not to exceed $250,000.00, in substantially the same form as "Exhibit"B.
THAT, a copy of the caption of this Resolution be spread upon the minutes of the City
Council.
READ,ADOPTED AND APPROVED this day of August, 2025 at a Regular
Meeting of the City of Port Arthur, Texas by the following vote: AYES:
AYES: Mayor:
Councilmembers:
NOES:
Charlotte M. Moses, Mayor
ATTEST:
Sherri Bellard, City Secretary
P.R. 24288
07/31/2025 IM
APPROVED A • : '.
Roxann Pais Cotroneo, City Attorney
APPROVED FOR ADMINISTRATION: APPROVED AS TO AVAILABILITY
OF FUNDS:
(> 1/t.i2e& /652.4,14
Ronald Burto , CP Lynda Boswell
City Man er Director of Finance
LAAILL e/e -iVetell () %24XCie
Clifton Williams, CPPB Ivan Mi ell
Purchasing Manger Transit-Fleet Director
P.R. 24288
07/31/2025 IM
Exhibit "A"
CITY OF PORT ARTHUR
Request for Qualifications
Professional Services for Transit Planning
Study
December 14, 2024 December 21, 2024
errY ir *
REQUEST FOR QUALIFICA
-
JTICE IS HEREBY GIVEN THAT sealed Ouelificabons.addressed to the City di Port Artntir„
ff..; fff at the Office of the City Secretary,City Hail 4444th Street or P.O.Box 1089,Port'
thur T s T7641 no later than 3:00 PM.,Wed y„January 8,2025 and all'Ogle received
I thereafter be opened and read aloud.on W. Way,January 8,2025 at 3:15 PM},al the City
.941T,70,.(:tarbers,5th Poor,Cat/Hail,Port Arthw.Texas for certain services briefly dies* as: .1
REQUEST FOR QUALIFICATIONS
PROFESSIONAL SERVICES FOR TRANSIT PLANNING STUDY
1
tificasons received after dosing tithe will be returned unopened.
leo of the so:.; .tierts and other Contract Documents are on fie in the Poreeestet9 Office.
With t City of Port Arthur,and are open for public• -* ion without ch..They can also
natridved from the City's website at wew
-City of Port Arthur reserves the right to reject any and all quer- and to waive p L
CM'OF PORT - - TEXAS
•
shallno,. REQUEST FOR P..‘ AUIFICATIONS
eft 2 Article VI Sec.2-262(C)of the City s Code of Ordinance,the City Counbot
VEN THAT sealed ' .s,addressed to the City of Port Arthur.ail
Ward a contract to a company that is in arrears in its obligations to the City.
'of the CRY Se city Nall 444-4th Street or P.O.Sox 1 pod
iota'than 3:00 t*idesday,January 8,2025 and all bids fart
I"Lot anti - aloud on We. "i ii•ay..January 8,2025 at 3:15 P.M.in the City
Ptirottestig M7, I 7- I loot.City Hell,Port Arthur,Texas for cettaet. briv=
y_earns 7 it as:
REQUEST FOR QUALIFICATIONS
PROFESSIONAL SERVICES FOR TRANSIT* •PINING STUDY
Qualifications received after closing time will be re. ed.
Copies of the Specifications and other Cent .Documents are on file in the Purch f," . Office,
4444th Street,City of Port Arthur,and are open for public inspection without *- They aft
be 1 .*horn the City' website at h or
The-City of Port Arthur reserves die right to reject any and all quatifications and to w
informalities.
Per C or 2ArlicIe Vi Sec. 2-262{C)di the City's Code of Ordnance,the City Council shall riot
award a con a, to a company that is in arrears in its obligations to the City,
« Cr` @ \ 7 zi
k
\ k 7
/
/ ` k `
\ \ 2 /
) - co Z. @
S p
/ _ $ 6 \
/ . . $ 2
?< ƒ $ ®
, _
I 0 \ i
° \
a) ® % 2 % \ \ \ \ \
% & a -
CM
\ \
> \
\ / /
\ A,.
w &
G _ 2 k 2 /
O. Q . ) r
ae
-a
\
k
r)
t�
,
k%, 11
�/ \ � ft .
2X. .'*44ri 2 a� ��� � � \�. `��
P.R. 24288
07/31/2025 IM
Exhibit "B"
STATE OF TEXAS § CITY OF PORT ARTHUR,TEXAS
§ AGREEMENT FOR PROFESSIONAL SERVICES
COUNTY OF JEFFERSON §
This Agreement for Professional Services Agreement is made by and between the City of
Port Arthur,Texas, a Texas home-rule municipality located in Jefferson County,Texas, and Solco
Group, LLC, individually, each a "Party" and collectively, "Parties", acting by and through the
Parties' authorized representatives.
Recitals:
WHEREAS, City desires to engage the services of Professional as an independent
contractor and not as an employee in accordance with the terms and conditions set forth in this
Agreement; and
WHEREAS, Professional desires to render professional services in accordance with the
terms and conditions set forth in this Agreement, engineering, planning, and demonstration grant
from the Federal Highway Administration(FHWA)to conduct a pedestrian access plan.
NOW, THEREFORE, in exchange for the mutual covenants set forth herein and other
valuable consideration, the sufficiency and receipt of which is hereby acknowledged, the Parties
agree as follows:
Article I
Employment of Professional
Professional will perform as an independent contractor for all services under this
Agreement to the prevailing professional standards consistent with the level of care and skill
ordinarily exercised by members of Professional's profession, both public and private, currently
practicing in the same locality under similar conditions including but not limited to the exercise of
reasonable, informed judgments and prompt, timely action. If Professional is representing that it
has special expertise in one or more areas to be utilized in the performance of this Agreement,then
Professional agrees to perform those special expertise services to the appropriate local, regional,
and national professional standards.
Article II
Term
2.1 The term of this Agreement shall begin on the date of execution by all parties, and
the work will begin upon the issuance of the Notice to Proceed by the City and shall remain in
effect for a period of 24 months and may be subject to change upon request and mutual
agreement(s).
2.2 The Professional may terminate this Agreement by giving thirty (30) days' prior
written notice to the City. In the event of such termination by Professional, Professional shall be
entitled to compensation for services satisfactorily completed in accordance with this Agreement
prior to the date of such termination.
2.3 City may terminate this Agreement by giving ten(10) days'prior written notice to
Professional. In the event of such termination by City, Professional shall be entitled to
compensation for services satisfactorily completed in accordance with this Agreement prior to the
date of such termination. Upon receipt of such notice from City, Professional shall immediately
terminate working on,placing orders, or entering into contracts for supplies, assistance, facilities,
or materials in connection with this Agreement and shall proceed to promptly cancel all existing
contracts insofar as they are related to this Agreement.
2.4 Upon notice of termination by Professional or City, Professional shall immediately
surrender all project documents produced by Professional and its subcontractors up to and
including the date on which the termination notice was given.
Article III
Scope of Services
3.1 Professional shall perform the services specifically set forth in Exhibit A, attached
hereto and incorporated herein by reference, entitled"Scope of Services." In case of conflict with
the language of ExhibitA and the provisions of this Agreement, the provisions of this Agreement
shall control. Any additional services require the prior approval of the City Council of the City.
3.2 The Parties acknowledge and agree that any and all opinions provided by
Professional represent the best judgment of Professional.
Article IV
Schedule of Work
4.1 Professional agrees to commence services upon written direction from City and to
complete the tasks set forth in Exhibit A, Scope of Services, in accordance with a work schedule
established by City(the"Schedule"),which is attached hereto and incorporated as Exhibit A.
4.2 In the event Professional's performance of this Agreement is delayed or interfered
with by acts of City or others, Professional may request an extension of time for the performance
of same as hereinafter provided, and City shall determine whether to authorize any increase in fee
or price, or to authorize damages or additional compensation as a consequence of such delays,
within a reasonable time after receipt of Professional's request.
4.3 No allowance of any extension of time, for any cause whatsoever, shall be claimed
or made by Professional, unless Professional shall have made written request upon City for such
extension not later than five(5)business days after the occurrence of the cause serving as the basis
for such extension request, and unless City and Professional have agreed in writing upon the
allowance of such additional time.
Page 2 of 11
City of Port Arthur, Texas
Professional Services Agreement
Article V
Compensation and Method of Payment
5.1 City shall pay Professional for the services specifically as set forth in Exhibit A and
in accordance with the Rate Schedule in an amount not to exceed$ $250,000.00 for said services.
5.2 Each month Professional shall submit to City an invoice supporting the amount for
which payment is sought. Each invoice shall also state the percentage of work completed on the
Project through the end of the then submitted billing period,the total of the current invoice amount,
and a running total balance for the Project to date.
5.3 Within thirty (30) days of receipt of each such monthly invoice, City shall make
monthly payments in the amount shown by Professional's approved monthly invoice and other
documentation submitted.
5.4 Professional shall be solely responsible for the payment of all costs and expenses
related to the services provided pursuant to this Agreement including, but not limited to, travel,
copying and facsimile charges,reproduction charges, and telephone, internet, e-mail, and postage
charges, except as set forth in Exhibit A.
5.5 Nothing contained in this Agreement shall require City to pay for any services that
are unsatisfactory as determined by City or which is not performed in compliance with the terms
of this Agreement, nor shall failure to withhold payment pursuant to the provisions of this section
constitute a waiver of any right, at law or in equity, which City may have if Professional is in
default, including the right to bring legal action for damages or for specific performance of this
Agreement. Waiver of any default under this Agreement shall not be deemed a waiver of any
subsequent default.
Article VI
Devotion of Time,Personnel, and Equipment
6.1 Professional shall devote such time as reasonably necessary for the satisfactory
performance of the services under this Agreement. City reserves the right to revise or expand the
scope of services after due approval by City as City may deem necessary, but in such event City
shall pay Professional compensation for such services at mutually agreed upon charges or rates,(a
copy of the Rate Schedule is attached hereto as Exhibit A),and within the time schedule prescribed
by City, and without decreasing the effectiveness of the performance of services required under
this Agreement. In any event, when Professional is directed to revise or expand the scope of
services under this Agreement, Professional shall provide City a written proposal for the entire
costs involved in performing such additional services. Prior to Professional undertaking any
revised or expanded services as directed by City under this Agreement, City must authorize in
writing the nature and scope of the services and accept the method and amount of compensation
and the time involved in all phases of the Project.
Page 3of11
City of Port Arthur, Texas
Professional Services Agreement
6.2 It is expressly understood and agreed to by Professional that any compensation not
specified in this Agreement may require approval by the City Council of the City of Port Arthur
and may be subject to current budget year limitations.
6.3 To the extent reasonably necessary for Professional to perform the services under
this Agreement, Professional shall be authorized to engage the services of any agents, assistants,
persons, or corporations that Professional may deem proper to aid or assist in the performance of
the services under this Agreement. The cost of such personnel and assistance shall be borne
exclusively by Professional.
6.4 Professional shall furnish the facilities, equipment,telephones, facsimile machines,
email facilities, and personnel necessary to perform the services required under this Agreement
unless otherwise provided herein.
Article VII
Relationship of Parties
7.1 It is understood and agreed by and between the Parties that in satisfying the
conditions 'and requirements of this Agreement, Professional is acting as an independent
contractor, and City assumes no responsibility or liability to any third party in connection with the
services provided by Professional under this Agreement. All services to be performed by
Professional pursuant to this Agreement shall be in the capacity of an independent contractor, and
not as an agent, servant, representative, or employee of City. Professional shall supervise the
performance of its services and shall be entitled to control the manner, means and methods by
which Professional's services are to be performed, subject to the terms of this Agreement. As
such, City shall not train Professional, require Professional to complete regular oral or written
reports, require Professional to devote his full-time services to City, or dictate Professional's
sequence of work or location at which Professional performs Professional's work, except as may
be set forth in Exhibit A.
Article VIII
Insurance
8.1 Before commencing work, Professional shall, at its own expense, procure, pay for
and maintain during the term of this Agreement the following insurance written by companies
approved by the state of Texas and acceptable to City. Professional shall furnish to the City
Manager certificates of insurance executed by the insurer or its authorized agent stating coverages,
limits, expiration dates and compliance with all applicable required provisions. Certificates shall
reference the project/contract number and be addressed as follows:
City of Port Arthur, Texas
Attention: Ron Burton, City Manager
444 4th Street
Port Arthur, Texas 77640-1089
Page 4 of 11
City of Port Arthur, Texas
Professional Services Agreement
A. Commercial General Liability insurance, incltiding, but not limited to
Premises/Operations, Personal & Advertising Injury, Products/Completed Operations,
Independent Contractors and Contractual Liability, with minimum combined single limits
of $500,000 per occurrence, $500,000 Products/Completed Operations Aggregate, and
$500,000 general aggregate. Coverage must be written on an occurrence form. The
General Aggregate shall apply on a per project basis.
B. Workers' Compensation insurance with statutory limits; and Employers'
Liability coverage with minimum limits for bodily injury: 1)by accident, $100,000 each
accident, and 2) by disease, $100,000 per employee with a per policy aggregate of
$500,000.
C. Business Automobile Liability insurance covering owned, hired and non-
owned vehicles, with a minimum combined bodily injury and property damage limit of
$500,000 per occurrence.
D. Professional Liability Insurance to provide coverage against any claim
which the Professional and all professionals engaged or employed by the Professional
become legally obligated to pay as damages arising out of the performance of professional
services caused by error, omission or negligent act with minimum limits of$1,000,000 per
claim, $1,000,000 annual aggregate
NOTE:If the insurance is written on a claims-made form, coverage shall be continuous(by
renewal or extended reporting period) for not less than thirty-six (36) months
following completion of this Agreement and acceptance by City.
8.2 With reference to the foregoing required insurance, Professional shall endorse
applicable insurance policies as follows:
A. A waiver of subrogation in favor of City, its officials, employees, and
officers shall be contained in the Workers' Compensation insurance policy.
B. The City, its officials, employees and officers shall be named as additional
insureds on the Commercial General Liability policy, by using endorsement CG2026 or
broader.
C. All insurance policies shall be endorsed to the effect that City will receive
at least thirty (30) days notice prior to cancellation, non-renewal, termination, or material
change of the policies.
8.3 All insurance shall be purchased from an insurance company that meets a financial
rating of B+or better as assigned by A.M. Best Company or equivalent.
Page 5 of 11
City of Port Arthur, Texas
Professional Services Agreement
Article IX
Right to Inspect Records
9.1 Professional agrees that City shall have access to and the right to examine any
directly pertinent books, documents, papers and records of Professional involving transactions
relating to this Agreement. Professional agrees that City shall have access during normal working
hours to all necessary Professional facilities and shall be provided adequate and appropriate work
space in order to conduct audits in compliance with the provisions of this section. City shall give
Professional reasonable advance notice of intended audits.
9.2 Professional further agrees to include in subcontract(s), if any, a provision that any
subcontractor agrees that City shall have access to and the right to examine any directly pertinent
books, documents, papers and records of such subcontractor involving transactions related to the
subcontract, and further, that City shall have access during normal working hours to all such
subcontractor facilities and shall be provided adequate and appropriate work space, in order to
conduct audits in compliance with the provisions of this section. City shall give any such
subcontractor reasonable advance notice of intended audits.
Article X
Miscellaneous
10.1 Entire Agreement. This Agreement and any and all Exhibits attached hereto
constitutes the sole and only agreement between the Parties and supersedes any prior or
contemporaneous understandings,written agreements or oral agreements between the Parties with
respect to the subject matter of this Agreement.
10.2 Authorization. Each Party represents that it has full capacity and authority to grant
all rights and assume all obligations granted and assumed under this Agreement.
10.3 Assignment. Professional may not assign this Agreement in whole or in part
without the prior written consent of City. In the event of an assignment by Professional to which
the City has consented, the assignee shall agree in writing with the City to personally assume,
perform, and be bound by all the covenants and obligations contained in this Agreement.
10.4 Successors and Assigns. Subject to the provisions regarding assignment, this
Agreement shall be binding on and inure to the benefit of the Parties and their respective heirs,
executors, administrators, legal representatives, successors and assigns.
10.5 Governing Law and Exclusive Venue. The laws of the State of Texas shall govern
this Agreement, and exclusive venue for any legal action concerning this Agreement shall be in a
District Court with appropriate jurisdiction in Jefferson County, Texas. The Parties agree to
submit to the personal and subject matter jurisdiction of said court.
10.6 Amendments. This Agreement may be amended only by the mutual written
agreement of the Parties.
Page 6 of 11
City of Port Arthur, Texas
Professional Services Agreement
g.. n..;
PP-
10.7 Severability. In the event any one or more of the provisions contained in this
Agreement shall for any reason be held to be invalid, illegal, or unenforceable in any respect by a
court of competent jurisdiction, such invalidity, illegality or unenforceability shall not affect any
other provision in this Agreement, and this Agreement shall be construed as if such invalid,illegal,
or unenforceable provision had never been contained in this Agreement.
10.8 Survival of Covenants and Terms. Any of the representations, warranties,
covenants,and obligations of the Parties,as well as any rights and benefits of the Parties,pertaining
to a period of time following the termination of this Agreement shall survive termination,
including,but not limited to, Section 3.3, Article X, and, in particular, Sections 10.13 and 10.14.
10.9 Recitals. The recitals to this Agreement are incorporated herein.
10.10 Notice. Any notice required or permitted to be delivered hereunder may be sent by
first class mail, overnight courier or by confirmed telefax or facsimile to the address specified
below, or to such other Party or address as either Party may designate in writing, and shall be
deemed received three(3) days after delivery set forth herein:
If intended for City:
City of Port Arthur, Texas
444 4th Street
Port Arthur, Texas 77640
Attn: Ron Burton, City Manager
Copy to:
City of Port Arthur, Texas
444 4th Street
Port Arthur, Texas 77640
Attn: Roxann Pais Cotroneo, City Attorney
If intended for Professional:
The Solco Group, LLC
549 4TH Street Suite 209A
Port Arthur Texas 77640
10.11 Counterparts. This Agreement may be executed by the Parties hereto in separate
counterparts, each of which when so executed and delivered shall be deemed an original, but all
such counterparts shall together constitute one and the same instrument. Each counterpart may
consist of any number of copies hereof each signed by less than all, but together signed by all of,
the Parties hereto.
10.12 Exhibits. The exhibits attached hereto are incorporated herein and made a part
hereof for all purposes.
Page 7 of 11
City of Port Arthur, Texas
Professional Services Agreement
10.13 Professional's Liability. Acceptance of the Project Documents by City shall not
constitute nor be deemed a release of the responsibility and liability of Professional,its employees,
associates, agents or subcontractors for the accuracy and competency of their designs, working
drawings, specifications or other documents and work; nor shall such acceptance be deemed an
assumption of responsibility by City for any defect in the Project Documents or other documents
and work prepared by Professional, its employees, associates, agents or sub-consultants.
10.14 Indemnification. PROFESSIONAL AGREES TO INDEMNIFY AND HOLD
HARMLESS CITY FROM AND AGAINST ANY AND ALL LIABILITIES, DAMAGES,
CLAIMS, SUITS,COSTS (INCLUDING COURT COSTS,REASONABLE ATTORNEY'S
FEES AND COSTS OF INVESTIGATION)AND ACTIONS BY REASON OF INJURY TO
OR DEATH OF ANY PERSON OR DAMAGE TO OR LOSS OF PROPERTY TO THE
EXTENT CAUSED BY PROFESSIONAL'S NEGLIGENT PERFORMANCE OF
SERVICES UNDER THIS AGREEMENT OR BY REASON OF ANY ACT OR OMISSION
ON THE PART OF PROFESSIONAL, ITS OFFICERS, DIRECTORS, SERVANTS,
AGENTS, EMPLOYEES, REPRESENTATIVES, CONTRACTORS,
SUBCONTRACTORS, LICENSEES, SUCCESSORS OR PERMITTED ASSIGNS
(EXCEPT WHEN SUCH LIABILITY, CLAIMS, SUITS, COSTS, INJURIES, DEATHS
OR DAMAGES ARISE FROM OR ARE ATTRIBUTED TO THE NEGLIGENCE OF
THE CITY). IF ANY ACTION OR PROCEEDING SHALL BE BROUGHT BY OR
AGAINST CITY IN CONNECTION WITH ANY SUCH LIABILITY OR CLAIM, THE
PROFESSIONAL, ON NOTICE FROM 'CITY, SHALL DEFEND SUCH ACTION OR
PROCEEDINGS AT PROFESSIONAL'S EXPENSE, BY OR THROUGH ATTORNEYS
REASONABLY SATISFACTORY TO CITY. PROFESSIONAL'S OBLIGATIONS
UNDER THIS SECTION SHALL NOT BE LIMITED TO THE LIMITS OF COVERAGE
OF INSURANCE MAINTAINED OR REQUIRED TO BE MAINTAINED BY
PROFESSIONAL UNDER THIS AGREEMENT. IF THIS AGREEMENT IS A
CONTRACT FOR ENGINEERING OR ARCHITECTURAL SERVICES, THEN THIS
SECTION IS LIMITED BY, AND TO BE READ AS BEING IN COMPLIANCE WITH,
THE INDEMNITY SPECIFIED IN § 271.904 OF THE TEXAS LOCAL GOVERNMENT
CODE, AS AMENDED. THIS SECTION SHALL SURVIVE TERMINATION OF THIS
AGREEMENT
10.15 Conflicts of Interests. Professional represents that no official or employee of City
has any direct or indirect pecuniary interest in this Agreement. Any misrepresentation by
Professional under this section shall be grounds for termination of this Agreement and shall be
grounds for recovery of any loss, cost, expense or damage incurred by City as a result of such
misrepresentation.
10.16 Default. If at any time during the term of this Agreement, Professional shall fail to
commence the services in accordance with the provisions of this Agreement or fail to diligently
provide services in an efficient, timely and careful manner and in strict accordance with the
provisions of this Agreement or fail to use an adequate number or quality of personnel to complete
the services or fail to perform any of Professional's obligations under this Agreement, then City
shall have the right, if Professional shall not cure any such default after thirty (30) days written
notice thereof, to terminate this Agreement. Any such act by City shall not be deemed a waiver
Page 8 of 11
City of Port Arthur, Texas
Professional Services Agreement
of any other right or remedy of City. If after exercising any such remedy due to Professional's
nonperformance under this Agreement, the cost to City to complete the services to be performed
under this Agreement is in excess of that part of the contract sum which as not theretofore been
paid to Professional hereunder, Professional shall be liable for and shall reimburse City for such
excess costs.
10.17 Confidential Information. Professional hereby acknowledges and agrees that its
representatives may have access to or otherwise receive information during the furtherance of
Professional's obligations in accordance with this Agreement, which is of a confidential, non-
public or proprietary nature. Professional shall treat any such information received in full
confidence and will not disclose or appropriate such Confidential Information for Professional's
own use or the use of any third party at any time during or subsequent to this Agreement. As used
herein, "Confidential Information"means all oral and written information concerning the City, its
affiliates and subsidiaries, and all oral and written information concerning City or its activities,
that is of a non-public,proprietary or confidential nature including,without limitation,information
pertaining to customer lists, services,methods, processes and operating procedures, together with
all analyses,compilations,studies or other documents,whether prepared by Professional or others,
which contain or otherwise reflect such information. The term "Confidential Information" shall
not include such information that is or becomes generally available to the public other than as a
result of disclosure to Professional, or is required to be disclosed by a governmental authority
under applicable law.
10.18 Remedies. No right or remedy granted or reserved to the Parties is exclusive of
any other right or remedy herein by law or equity provided or permitted;but each right or remedy
shall be cumulative of every other right or remedy given hereunder. No covenant or condition of
this Agreement may be waived without written consent of the Parties. Forbearance or indulgence
by either Party shall not constitute a waiver of any covenant or condition to be performed pursuant
to this Agreement.
10.19 No Third-Party Beneficiary. For purposes of this Agreement, including the
intended operation and effect of this Agreement, the Parties specifically agree and contract that:
(1) this Agreement only affects matters between the Parties to this Agreement, and is in no way
intended by the Parties to benefit or otherwise affect any third person or entity notwithstanding the
fact that such third person or entity may be in contractual relationship with City or Professional or
both;and(2)the terms of this Agreement are not intended to release,either by contract or operation
of law, any third person or entity from obligations owing by them to either City or Professional.
[The Remainder of this Page Intentionally Left Blank]
Page 9 of 11
City of Port Arthur, Texas
Professional Services Agreement
EXECUTED this day of , 2025.
CITY:
CITY OF PORT ARTHUR,TEXAS,
A Texas home-rule municipality,
By:
Ron Burton,City Manager
ATTEST:
Sherri Bellard,City Secretary
APPROVED AS TO FORM:
Roxann Pais Cotroneo, City Attorney
EXECUTED this day of , 2025.
PROFESSIONAL:
The Solco Group, LLC
By:
Print
Title
Page l0 of 11
City of Port Arthur, Texas
Professional Services Agreement
Exhibit A
Scope of Services/ Schedule
Page 11 of 11
City of Port Arthur, Texas
Professional Services Agreement
Ir. j THE SOLCO GROUP, LLC
TRANSPORTATION PLANNING/ENGINEERING/RESEARCH/ADVICE/CONSULTING
Date: July 21, 2025
Mr.Ivan Mitchell
Transit Manager
City of Port Arthur—Transit
344 Proctor Street
Port Arthur,TX 77640
Subject: Proposal for Pedestrian Access to Transit Plan—Safe Streets for All (SS4) 2024 Grant-
TSG Proposal No.: 2024-11-1257B
Dear Mr. Mitchell,
The Solco Group, LLC (TSG) is pleased to submit this formal proposal to the City of Port Arthur
Transit(PAT) to develop a Pedestrian Access to Transit Plan funded by the 2024 Safe Streets
for All (SS4A) Grant Program. This initiative aligns with PAT's goals to improve pedestrian
safety,promote ADA accessibility, and expand equitable access to transit throughout the
community.
Scope of Services
Our team will deliver a comprehensive planning study focused on enhancing pedestrian safety
around PAT's fixed-route transit stops. The effort will include outreach, site assessments,
connectivity evaluations, land use and policy review, and the development of capital
improvement plans. Special attention will be given to high-boarding bus stops,underserved
communities, and individuals with disabilities. Key deliverables will include:
• Draft and final planning studies (publicly available),
• Capital project plans and cost estimates,
• Stakeholder engagement sessions,
• Implementation of timeline and funding strategies.
Methodology
The project will follow a structured 24-month schedule with clearly defined milestones and
monthly progress meetings. Deliverables will be reviewed and approved by the designated City
Project Manager (CPM). Community engagement will be prioritized through outreach and
input from people with disabilities, advocacy groups, and public stakeholders.
THE SOLCO GROUP,LLC 549 4',Street,Suite 209A,Port Arthur, TX 77640
WWW.TheSolcoGrou p.com
TS9
THE SOLCO GROUP, LLC
TRANSPORTATION PLANNING/ENGINEERING/RESEARCH/ADVICE/CONSULTING
Fee Structure
TSG proposes to perform these services in accordance with the hourly fee rates outlined in
the attached TSG Fee Table. We are committed to staying within the $250,000 grant budget
and will provide a detailed breakdown of hours and labor categories upon authorization to
proceed.
TSG is honored to support PAT's commitment to creating a safer and more
accessible Port Arthur.We welcome the opportunity to partner on this meaningful
project. Please don't hesitate to contact us with any questions or for further
clarification.
Sincerely,
Kelvin L. Solco, PE, MBA
Principal The Solco Group, LLC
THE SOLCO GROUP,LLC 549 4'"-Street,Suite 209A,Port Arthur, TX 77640
WWW.TheSolcoGroup.com
APPENDIX A-Fee Table
Planning support
Safe Streets(SS-4)
Planning Efforts
Port Arthur
Contract no.
TSG Number:2024- Principal Project Cad
11-1257B Principal Civil PE Manager Planner Drafter Admin
FEE RATES $ 250.00 $ 195.00 $ 145.00 $ 120.00 $85.00 $ 70.00
SS-4 Kick Off
Meetings and Briefmg 4 4 4 4 2
Data Gathering and
Identification of Road
Segments 2 8 16 8 8
Literature Reviews
and City Documents
Data Collection 8 8 8 8
Formation of PAT
Planning Group for
reviews to include
Public Representation 8 16 36 16 0 8
Evaluation of
Pedestrian Access at
Each Bus Stop
Location 8 16 24 16 0 2
Recommended
Network
Improvements at Each
Bus Stop Location 2 8 24 8 0 2
Focus on Bus Stop
Priority and Key Sites 2 16 16 16 8 1
DRAFT STUDY
available for Public
View 2 40 40 40 8 16
Capital Project
Planning for
Prioritized Projects 2 16 24 24 40 1
Cost Estimates for
next Fiscal Year
Projects 8 8 36 8 0 2
FINAL STUDY
available for Public
View 4 16 40 16 0 4
Implementation Goals
&Objectives for
Long-Term
Investments 4 8 36 8 0 2
Grant applications for
implementation of all
CIP listed in the
planning documents. 4 8 40 24 0 8
Recommended
Network
Improvements
Focus on Bus Stops 4 8 36 8 0 0
Capital Project
Planning 4 8 24 36
Cost Estimates 4 16 16 8 1
Implementation Goals
&Objectives 16 8 8 8 8
Briefings and
Presentations 16 4 4 16 8 36
Administrative
Support 8 8 8 8 48
Sub Total Hours 110 224 440 280 64 149
Sub Total Costs $27,500.00 $43,680.00 $63,800.00 $33,600.00 $5,440.00 $10,430.00
TOTAL LABOR $184,450.00
Printing and
Reproduction $1,200.00
Supplies and
Materials(Posters,
USBs,Brochures) $450.00
Sub-consultant- 1 $35,000.00
Sub-consultants-2 $28,900.00
Contract Budget/
Total $250,000.00
Compensation and Payment Terms
The Client shall pay The Solco Group,LLC ("TSG") for the services described in the attached Exhibit (Fee
Schedule)in an amount not to exceed $250,000.00 for said services.
Each month,TSG shall submit to the City of Port Arthur an invoice supporting the payment amount being
requested. Each invoice shall include:
1. The percentage of work completed on the project through the end of the current billing period.
2. The total of the current invoice amount.
3. A running total of all payments billed to date for the project.
Within thirty(30)calendar days of receipt of each monthly invoice,the Client shall remit payment in the
amount shown on the TSG-approved invoice, together with any supporting documentation submitted by
TSG.
11W10111
PORT ARTHUR TRANSIT (PAT) PEDESTRIAN ACCESS TO TRANSIT PLANNING STUDY
Port Arthur Transit SCOPE OF WORK
SCOPE FOR PEDESTRIAN ACCESS TO TRANSIT PLAN—Safe Streets for All(SS4A)2024 Grant
INTRODUCTION
The Solco Group,LLC(TSG)is pleased to submit this proposal to assist the City of Port Arthur Transit(PAT)in enhancing
pedestrian safety at existing transit stops through ADA compliance and transit accessibility improvements,as part of a
planning study supported by a 2024 SS4A grant. Our approach combines technical expertise, stakeholder engagement, and
a commitment to inclusive mobility for all community members, especially those with visual disabilities and diverse mobility
needs.
OUTREACH
PAT,in collaboration with local community organizations,will conduct broad outreach to gather input from transit users.A
diverse review committee—comprising advocacy group representatives, transit riders, seniors,people with disabilities, and
city staff—will guide the planning process,shaping outreach efforts,criteria for focus area selection,and the identification
of potential projects.
CONNECTIVITY IMPROVEMENTS
Connectivity improvements will be prioritized by evaluating continuous pedestrian routes that link neighborhoods,transit
stops,and key community anchors.Engineering and planning services will identify pedestrian-only zones in high-traffic
areas,assess safety gaps in the pedestrian network,and address issues such as high-traffic intersections and inadequate
lighting.
The plan will generate a prioritized list of infrastructure improvements designed to boost mobility and enhance quality of
life,making Port Arthur's public spaces safer and more accessible.These improvements may include upgraded sidewalks
and crossings,advanced signals,intersection redesigns,traffic calming measures,and enhanced lighting and visibility.
LAND USE PLANNING AND POLICY ANALYSIS
Land use planning and policy analysis will support the creation of a comprehensive network of sidewalks,pathways,and
bike lanes within mixed-use developments,ensuring that all areas are accessible and walkable.Both short-temp"quick win"
strategies and long-term solutions requiring significant investment and innovation will be outlined. The adoption of smart
technologies,such as real-time transit apps and crowd-sourced data platforms,will further support these efforts.
A framework for ongoing maintenance will be established to ensure that pedestrian infrastructure remains in good repair and
that issues such as debris or hazards are promptly addressed. The results will include a phased implementation plan and
timeline,guiding the roll-out of recommendations over the next five years and identifying funding opportunities through
federal grants,local budgets,and private partnerships.
METHODOLOGY
The plan's methodology ensures a thorough examination of all aspects related to safe pedestrian access to PAT's fixed-route
system,delivering actionable recommendations to foster livable,connected neighborhoods in Port Arthur.Key components
include extensive data collection,site assessments,and a focused analysis to identify connectivity gaps between
neighborhoods,transit hubs,and major destinations,improving safe and efficient public transportation access citywide.
PAT Pedestrian Access to Transit Plan —SS4 2024 I Page 1
PORT ARTHUR TRANSIT (PAT) PEDESTRIAN ACCESS TO TRANSIT PLANNING STUDY
SCOPE OF WORK
TASK DETAILS
The planning effort will culminate in preliminary designs and capital project planning focused on improving pedestrian
access to transit.These efforts will be supported by clear implementation goals and objectives that guide PAT's future
investments.The following tasks ofthe plan are described as follows:
Tasks Description
Data Gathering and Identification of Road At least ten road segments in the PAT service area selected
Segments based on high bus ridership and pedestrian improvement
needs.
Formation of PAT Planning Group for Planning participation and outreach goals and process
reviews to include Public Representation
Evaluation of Pedestrian Access at Each Assessment of pedestrian access to PAT bus stops,including
Bus Stop Location an origin/destination review for further improvement
opportunities.
Recommended Network Improvements at Suggestions for enhancements such as sidewalks, crosswalks,
Each Bus Stop Location and curb extensions to facilitate safer access to transit.
Focus on Bus Stop Priority Targeting stops with high boarding counts and safety
concerns for preliminary design development.
DRAFT STUDY available for Public View Draft of the Planning Study for review and comment—30-day
comment period minimum online, social media, etc.
Capital Project Planning for Prioritized Preparation and planning of capital projects aimed at
Projects improving pedestrian access in priority areas.
Cost Estimates for the next Fiscal Year Provision of estimated costs for the selected pedestrian
Projects infrastructure improvements.
FINAL STUDY available for Public View All comments and updates from Planning Group updated,
presentation to City Council—30-day comment period
minimum, online, social media, etc.
Implementation Goals&Objectives for Definition of clear goals and objectives to direct PAT capital
Long-Term Investments investments in the coming years.
Grant applications for implementation of Apply for relevant federal, state, or city grants to fund each
all CIP listed in the planning documents. prioritized project in the final study.
SS4A Planning Study Goals and Framework
The purpose of the SS4A grant-funded planning study is to establish measurable tasks and generate actionable
items that stem directly from the planning effort. The following table outlines the key tasks of the pedestrian
access improvement initiative, each aligned with specific, measurable goals to ensure focused progress and
accountability.
By defining clear objectives for network enhancements, bus stop upgrades, capital project planning, and cost
estimation, the initiative offers a structured framework to guide future investments and effectively monitor
implementation outcomes.
PAT Pedestrian Access to Transit Plan—SS4 2024 I Page 2
PORT ARTHUR TRANSIT (PAT) PEDESTRIAN ACCESS TO TRANSIT PLANNING STUDY
SCOPE OF WORK
Tasks Measurable Goal
Recommended Network Improvements Increase the number of accessible pedestrian pathways and
reduce the number of pedestrian incidents by 20%within two
years.
Focus on Bus Stops Enhance safety features at 100%of high-boarding bus stops
identified as priority locations within the first project phase.
Capital Project Planning Complete capital improvement plans for all priority zones by
the end of the fiscal year.
Cost Estimates Provide cost estimates with a variance of less than 10%from
final project expenditures.
Implementation Goals & Objectives Align 90%of PAT capital investments with defined access
and safety objectives over the next three years.
ESTIMATED PROJECT SCHEDULE
Month Task Milestone/Deliverable
1 Project Initiation,Team Kick-off, Begin Monthly Project launch: Initial progress
Progress Meetings meeting held
1-2 Identify Priority Zones and High-Boarding Bus List of priority locations finalized
Stops
2-3 Stakeholder Engagement Sessions (Initial) Input from community and
advocacy groups
3-6 Network Assessment: Evaluate pedestrian Assessment report: Baseline
pathways and bus stop safety incident data collected
4-8 Develop Capital Improvement Plans for Priority Draft improvement plans for all
Zones priority zones
6-10 Estimate Costs for Proposed Improvements Cost estimates completed
(variance <10%)
7-14 Design and Engineering of Pedestrian Pathways Designs finalized for
and Bus Stop Upgrades implementation
9, 16 Stakeholder Engagement Sessions(Design Stakeholder feedback
Review & Implementation Feedback) incorporated
11-20 Implementation of Pedestrian Pathway Increased pathway accessibility:
Improvements progress tracked monthly
11-18 Enhance Safety Features at High-Boarding Bus 100%of priority bus stops
Stops upgraded
12, 18, 24 Monthly Progress Review and Reporting Milestone reports: Schedule
adjustments as needed
20-22 Finalize Capital Project Completion and Cost All improvement plans executed;
Reconciliation cost evaluation
21-23 Final Stakeholder Engagement&Community Feedback on outcomes and
Feedback Sessions outstanding issues
24 Project Wrap-up,Outcome Analysis,Final Achievement of 20% pedestrian
Reporting incident reduction and 90%PAT
capital alignment verified
PAT Pedestrian Access to Transit Plan —SS4 2024 I Page 3
PORT ARTHUR TRANSIT (PAT) PEDESTRIAN ACCESS TO TRANSIT PLANNING STUDY
SCOPE OF WORK
• Monthly Progress Meetings for Planning Group: Initiated Month 1 and held regularly to monitor
milestones.
• Stakeholder Engagement Sessions: Scheduled at major project phases for community and advocacy
group input.
Project Oversight and Collaboration
All deliverables will be monitored for timely completion, and the project team will work collaboratively to
ensure that each milestone is achieved according to the established schedule.
Project Management and Communication
TSG will coordinate closely with Port Arthur Transit staff, providing regular progress updates and
maintaining responsive communication throughout the duration of the project. Engagement efforts will be
planned to maximize input from individuals with disabilities, local law enforcement, and community
advocates, ensuring that a broad range of perspectives inform the planning process.
Conclusion
TSG is committed to delivering high-quality, inclusive, and actionable transit solutions for the City of Port
Arthur. We welcome the opportunity to collaborate and invite any questions or requests for clarification
regarding this proposal.
PAT Pedestrian Access to Transit Plan—SS4 2024 I Page 4
IS
- THE SOLCO GROUP, LLC
TRANSPORTATION PLANNING/ENGINEERING/RESEARCH/ADVICE/CONSULTING
THE SOLCO GROUP,LLC TRANSPORTATION PROFESSIONAL SERVICES/
CONSULTING AGREEMENT
THE SOLCO GROUP LLC appreciates the opportunity to collaborate with you and
provide professional advice regarding your specific project. To ensure a mutual
understanding, we have set forth the following pertinent information about our services.
THE SOLCO GROUP, LLC (hereafter referred to as TSG), and the City of Port Arthur,
Texas (PATX) and/or the Port Arthur Transit Department (PAT) (CLIENT(s))
acknowledge and agree to the following.
1. CLIENT CONTACT -The CLIENT is free to contact TSG to discuss the specific
project immediately after the execution of this agreement.
2. TO BE PROVIDED BY THE SOLCO GROUP, LLC — TSG agrees to provide
the following:
a. The services of all professional and technical personnel required for the
performance of the services described under Scope of Work.
b. Up to three physical copies and one electronic file copy of the construction
plans and specifications for the project.
c. Project consultation throughout the project from initiation to project
closeout.
3. ACCESSIBILITY - The CLIENT acknowledges all work performed by TSG or
affiliates will occur within the standard business hours of 7:00 AM to 7:00 PM
Monday through Saturday. TSG has limited accessibility on Sundays and if
required, will need to be scheduled in advance. If scheduling conflicts occur on
any day of the week TSG will return the CLIENT's phone calls as soon as
possible and attend meetings as soon as mutual schedules permit.
4. TO BE PROVIDED BY PORT ARTHUR TEXAS (PATX) (CLIENT) — The
CLIENT agrees to provide the following:
a. All available pertinent information that it may have in its possession or to
which it may have access.
b. A representative to whom the Engineer will report and from whom
Engineer shall receive instruction and authorization.
c. Right of access to all properties as required during the execution of the
work.
d. All necessary resident engineering services.
THE SOLCO GROUP,LLC 549 4",Street,Suite 209A,Port Arthur, TX 77640
WWW.TheSolcoGroup.com
461
- THE SOLCO GROUP, LLC
TRANSPORTATION PLANNING/ENGINEERING/RESEARCH/ADVICE/CONSULTING
e. Services of an independent testing laboratory to perform all materials
testing necessary for control of the project during the construction phase.
f. Documentation and property description information work necessary for
easement or property boundaries description.
5. TIME OF PERFORMANCE -The services of The Solco Group, LLC are to
commence upon the signing of the contract.
a. The estimated project duration for the design services is approximately
thirty business days for design, subject to change upon the CLIENT
request or mutual agreement(s).
b. The final contract plans and documents will be available and ready per the
agreed project schedule.
6. OWNERSHIP OF DOCUMENTS - All drawings, specifications, records,
photographs, videos, and other project related documents prepared by TSG, its
employees, subcontractors, and agents in the performance of this Agreement shall
be the property of PATX. These items will be delivered to the CLIENT upon the
completion and/or termination of this Agreement. TSG reserves the right to retain
copies of documents, photographs, and other records for filing purposes, TSG
archives, and for historical reference.
7. COMMUNICATIONS - All communication and information between the
CLIENT and TSG are considered privileged and confidential if desired and
requested. TSG will provide disclosure to others only when authorized by the
CLIENT in writing. CLIENT authorization may be needed when TSG needs to
assign work to its affiliates. However, TSG may use the name, logo, or
authorized image of the CLIENT in TSG marketing materials.
8. PAYMENTS AND COMPENSATION - Payments to TSG shall be made
promptly and shall not be contingent upon funding anticipated by the CLIENT.
9. The CLIENT understands that TSG will invoice immediately upon the execution
of this agreement, and then monthly, or more frequently if requested. The
CLIENT understands the TSG invoice terms are due upon receipt. All fees shall
be paid promptly. Invoices will be faxed or sent by e-mail unless the original is
requested. Once TSG submits an invoice for services provided, Port Arthur Transit
and the City of Port Arthur agree to pay such invoices within thirty(30) days after the
date of the applicable invoice. Any balance outstanding for more than thirty (30)
days of the invoice shall be deemed delinquent and subject to delinquent payment
fees,penalty fees, and/or interest charges.
THE SOLCO GROUP,LLC 549 4",Street,Suite 209A,Port Arthur, TX 77640
WWW.T h eSo I co G ro u p.co m
Ala-
THE SOLCO GROUP, LLC
TRANSPORTATION PLANNING/ENGINEERING/RESEARCH/ADVICE/CONSULTING
i. Port Arthur Transit (PAT) and/or the City of Port Arthur (PATX) will
compensate The Solco Group, LLC for all work and services described in
the Scope of Services. The CLIENT also agrees to the following:
ii. The scope and cost of said services will be reviewed and approved by Port
Arthur Transit and/or the Port Arthur City Council prior to any
authorization to proceed.
10. This cost shall constitute complete compensation for all direct labor, payroll
burden, general and administrative overhead, profit, travel, equipment, and
materials necessary to complete the tasks as set forth in the Scope of Work.
11. METHOD OF PAYMENT—The CLIENT is responsible for payment for services
rendered as stipulated in this agreement. All payment to The Solco Group, LLC
for services under this Scope of Work will be made monthly based on the
percentage of work completed during the preceding month and will, in every case,
be supported by a suitable invoice.
12. BRANDING AND IMAGES - The CLIENT acknowledges the use of"The Solco
Group, LLC" name, branding, and images in any manner is not authorized unless
this signed agreement is returned to TSG, subject to privacy laws. The CLIENT
will also allow The Solco Group, LLC to use the Port Arthur Transit and City of
Port Arthur name, branding, logos, or similar images for use in developing the
project plans and specifications and for TSG marketing purposes.
13. TERMINATION - If, through circumstances of unforeseen cause, TSG fails to
fulfill in a timely and proper manner the obligations under this Agreement, the
City of Port Arthur shall thereupon have the right to terminate this Contract by
giving written notice to the Engineer of such termination and specifying the
effective date thereof, at least ten (10) days before the effective date of such
termination. In such event, all finished or unfinished documents, data, studies,
surveys, drawings, maps, models, photographs, and reports prepared by TSG
under this Contract shall become the property of TSG and TSG shall be entitled to
receive just and equitable compensation for any work satisfactorily completed
hereunder. The City of Port Arthur may terminate this Agreement at any time by
giving at least thirty (30) days' notice in writing to the TSG. If the Agreement is
terminated by the City of Port Arthur as provided herein, then TSG will be paid
for the time provided and expenses incurred up to the actual termination date.
14. CHANGES - The CLIENT may, from time to time, request changes in the scope
of the services of TSG to be performed hereunder. Such changes, including any
increase or decrease in the amount of the TSG's compensation, which are
mutually agreed upon by and between the City and the TSG, shall be incorporated
in written amendments to this Agreement.
THE SOLCO GROUP,LLC 549 4` Street,Suite 209A,Port Arthur, TX 77640
WWW.TheSolcoGroup.com
I .- THE SOLCO GROUP, LLC
TRANSPORTATION PLANNING/ENGINEERING/RESEARCH/ADVICE/CONSULTING
15. STANDARD ARBITRATION AGREEMENT - Any dispute, controversy or
claim arising out of or relating in any way to Agreement including without
limitation any dispute concerning the design, construction, validity, interpretation,
enforceability, or breach of the agreement, shall be exclusively resolved by
binding arbitration upon a Party's submission of the dispute to arbitration. In the
event of a dispute, controversy or claim arising out of or relating in any way to the
Agreement, the complaining Party shall notify the other Party in writing thereof.
Within thirty (30) days of such notice, both Parties shall meet at an agreed
location to attempt to resolve the dispute in good faith.
16. CIVIL RIGHTS ACT OF 1964 - Under Title VI of the Civil Rights Act of 1964,
no person shall, on the grounds of race, color, or national origin,be excluded from
participation in, be denied the benefits of, or be subjected to discrimination under
any program or activity receiving Federal fmancial assistance.
17. INSURANCE—The Solco Group, LLC will maintain the following insurance
coverage for the duration of this project.
a. Commercial General Liability of$1,000,000 each occurrence and
b. $2,000,000 aggregate
c. Professional Liability(Errors and Omissions)of$1,000,000 each occurrence
and$1,000,000 aggregate.
18. SPECIAL CONDITIONS (if applicable):
THE SOLCO GROUP,LLC 549 4',Street,Suite 209A,Port Arthur, TX 77640
WWW.TheSotcoGroup.com
.,, THE SOLCO GROUP, LLC
TRANSPORTATION PLANNING/ENGINEERING/RESEARCH/ADVICE/CONSULTING
Anticipated Start Date: Upon issuance of notice-to-proceed
This agreement is acceptable to The Solco Group, LLC, as indicated by the authorized
representative signature(s) below:
(TSG Representative) Print Name: Kelvin L. Solco, P.E., MBA
(TSG Representative) Signature:
(TSG Representative) Title: President/ CEO
(Attest for TSG):
THE SOLCO GROUP,LLC 549 4',Street,Suite 209A,Port Arthur, TX 77640
WWW.Th eSol co Gro u p.co m
TN THE SOLCO GROUP, LLC
TRANSPORTATION PLANNING/ENGINEERING/RESEARCH/ADVICE/CONSULTING
ACCEPTANCE - If this contract meets with the approval of the Port Arthur Transit (PAT)
and/or the City of Port Arthur (PATX), please indicate CLIENT acceptance by signing this
proposal and returning one signed copy to The Solco Group, LLC PO Box 22001 Beaumont,
Texas 77720.
Agreed to this day of , 2025.
By(Client):
(Client) Print Name:
(Client) Signature:
(Client) Title:
(Attest for Client):
Thank you for allowing us to serve you.
THE SOLCO GROUP,LLC 549 4'"•Street,Suite 209A,Port Arthur, TX 77640