HomeMy WebLinkAboutPR 24526: CHANGE ORDER NO. 1 WITH MIKE BARNETT CONSTRUCTION, REPAIRS AT THE WEST SIDE CLINIC P.R. No. 24526
09/11/2025 AJS
Memorandum
City of Port Arthur, Texas
Robert A. "Bob"Bowers Civic Center
To: The Honorable Mayor and City Council
Through: Ron Burton, City Manager
From: Adam J Saunders, Civic Center Dir
RE: Proposed Resolution No. 24526
In May 2025, the City Council approved Resolution No. 25-205 for Roof Replacement at the West Side
Clinic. During the removal of the roof, unforeseen concealed circumstances were discovered. In order
to comply with warranty guidelines, the manufacturer's warranty inspector requires these changes. The
current through-wall flashing must be removed and replaced. To accomplish this, 10" of EFIS wall
substrate must be removed at the parapet base. This EFIS must be replaced after installation, new rake
supports must be mounted, and a textured finish must be applied to seal off the flashing. This work will
be Change Order No. 1.
The cost of Change Order No. 1 is $11,790.00. The original cost for this work was $80,648.00. With the
addition of this change order, the total amount for this work increases to $92,438.00. Funding for this
proposed change order will be added to account number 307-21-049-8512-00-10-000, Project No.
BU0022.
Mike Barnett Construction of Port Neches, Texas, has agreed to do the work for $11,790.00 out of
Account No. 307-21-049-8512-00-10-000-, Project No. BU0022.
ANALYSIS/CONSIDERATION:
West Side Clinic needs additional work on the Roof Replacement due to unforeseen circumstances.
Change Order No. 1 will address this additional work.
BUDGETARY AND FISCAL EFFECT
Funds are available in Account No. 307-21-049-8512-00-10-000, Project No.#BU0022.
STAFFING EFFECT
None
RECOMMENDATION
It is recommended that the City Council approve the City Manager to execute Change Order No. 1 to the
contract with Mike Barnett Construction of Port Neches, Texas, for additional repairs at the West Side
Clinic, in the amount of$11,790.00.
P.R. No. 24526
09/11/2025 AJS
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 1 TO THE CONTRACT WITH MIKE BARNETT
CONSTRUCTION OF PORT NECHES, TEXAS, FOR ADDITIONAL REPAIRS
AT THE WEST SIDE CLINIC IN THE AMOUNT OF $11,790.00 TO A NEW
TOTAL OF $92,438.00. FUNDS AVAILABLE IN ACCOUNT NO. 307-21-049-
8512-00-10-000, PROJECT NO. BU0022
WHEREAS, the City Council approved Resolution No. 25-205 in May 2025, authorizing an
agreement with Mike Barnett Construction of Port Neches, Texas, for Roof Replacement at the West
Side Clinic in the amount of$80,648.00; and,
WHEREAS, it has been determined that additional repairs are needed due to unforeseen
circumstances revealed after the demolition of the area in preparation to install a new roof; and,
WHEREAS,to comply with warranty guidelines, the manufacturer's warranty inspector requires
changes: and,
WHEREAS, the necessary changes involve removing and replacing the current through-wall
flashing. To accomplish this, 10" of EFIS wall substrate must be removed at the parapet base. This
EFIS must be replaced after installation, new rake supports must be mounted, and a textured finish must
be applied to seal off the flashing.; and,
WHEREAS, Mike Barnett Construction of Port Neches, Texas, has submitted Change Order
No. 1 for this additional work in the amount of$11,790.00, with an additional five days added to the
work schedule, attached hereto as Exhibit"A"; and,
WHEREAS, the balance of$11,790.00 will be added to the total cost of this project, increasing
the total amount of this work to $92,438.00. Funding for this proposed change order will be added to
account number 307-21-049-8512-00-10-000, Project No. BU0022; and,
WHEREAS, approval of Change Order No. 01 is deemed an appropriate action.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PORT ARTHUR, TEXAS:
THAT,the facts and opinions in the preamble are true and correct.
THAT, the City Council hereby authorizes the City Manager to execute Change Order No. 1 to
the contract with Mike Barnett Construction of Port Neches, Texas, for additional repairs at the West
Side Clinic, in substantially the same form as attached here to Exhibit"A".
THAT the funding for Change Order No. 1 is $11,790.00, bringing the new total to $92,438.00,
funding available in Account No. 307-21-049-8512-00-10-000, Project No. BU0022.
THAT a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ,ADOPTED,AND APPROVED,this day of 2025 AD, at a
Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following Vote:
AYES: Mayor: ,
Councilmembers:
NOES:
Charlotte M. Moses, Mayor
ATTEST:
Sherri Bellard, City Secretary
APPROVED AS TO F •
Roxann Pais Cotroneo
City Attorney
APPR OR ADMINISTRATION:
Ro B
City M r
APPRO D AS TO
UN9AILABILITY:
_ /444E
y a :oswell, .A., ICMA-CM
Director of Finance
1a
Cli o Williams, CPPB
Purchasing Manager
EXHIBIT "A"
MIKE BARNETT
CONSTRUCTION
Change order
Proposal-CPR 1.0
City of Port Arthur 08/29/25
221 Houston Ave
Port Arthur, Texas 77642
Attn: Adam Saunders
Re: Westside Development Clinic
We at Mike Barnett Construction are providing you with this change order proposal for the following scope of
work.
We are submitting this change order proposal due to unforeseen concealed circumstances discovered once the
removal of the roof commenced. The mfg. warranty inspector is requiring these changes to comply with
warranty guidelines.
All the work in this scope of work are additional items that the owner commissioned GC to perform.
All items in this proposal are additional to the original contract amount.
Scope of work:
• To remove 10" EFIS wall substrate at parapet base.
• Remove existing thru-wall flashing.
• To furnish and install New through wall flashing.
• To furnish and install New Rake supports.
• To furnish and install EFIS wall substrate with matching texture finish to seal off the flashing.
Pricing: We are providing this change order with all labor,materials,and equipment for the total amount of:
Eleven thousand seven hundred ninety dollars and .00 cents: $11,790.00 plus all applicable taxes
Labor= $7.075.00 materials =$4,715.00
Mike Barnett Construction: SETX REGION 5 COOP# 20250202/# 20250301
If you accept our proposal please sign below and return via email to rbourgeoismbc( gmail.com /or
lanceusa 11(agmail.com.
Accepted By: Date:
Sincerely,
Russell Bourgeois- Commercial Const. Mgr.
Mike Bamett Construction,Inc., 1701 Port Neches Ave., Port Neches,TX 77651 Phone(409)727-5673 Fax(409)727-2905
MIKE BARNETT
CONSTRUCTION CPR # 1 • 0
Serving The Golden Triangle Since 1965
1701 Port Neches Ave PROJECT: City of Port Arthur
Port Neches,Texas 77651 Westside Clinic
(409) 727-5673 25-205 Roof project.
CHANGE PROPOSAL REQUEST
TO: City of Port Arthur FROM: Mike Barnett Construction
221 Houston Ave. 1701 Port Neches Ave.
Port Arthur,Texas 77642 Port Neches,Texas 77651
Attn: Adam Sanders Russell Bourgeois
CHANGE PROPOSAL#: CPR#1.0 DATE: 09/08/25
REFERENCE: Warranty requirement-Extras SCHEDULE IMPACT: 5 days
DESCRIPTION OF CHANGE:
To remove 10" EFIS wall substrate at the parapet base.
To remove the existing thru-wall flashing.
To furnish and install New thru-wall flashing.
To furnish and install new rate supports.
To furnish and install EFIS wall substrate with matching texture finish to seal off the flashing.
DESCRIPTION UNIT QTY UNIT $ TYPE TOTALS
1 To remove and replace EFIS as needed. $11,790.00
2. To remove and replace new rake supports.
3. To remove and replace thru wall flashing
SUBTOTAL: $ 11,790.00
SUBTOTAL: $ 11,790.00
SALES TAX: $