HomeMy WebLinkAboutPR 24654: STONEGATE DRAINAGE IMPROVEMENT PROJECT, CHANGE ORDER NO. 4 City of nrt rthur`y_ Texas www.PortArthurTx.gov INTEROFFICE MEMORANDUM Date: November 14, 2025 To: The Honorable Mayor and City Council Through: Ron Burton, CPM, City Manager From: Suhail Kanwar, P.E., M.S., CFM, ENV SP, Director of Public Services/City Engineer RE: PR. No. 24654 — Stonegate Drainage Improvement Project. Change Order No. 4 from Brystar Contracting, Inc. of Beaumont, Texas: Drainage improvements, decreasing the contract by $412,362.05, to a new contract amount of $17,977,620.15. Project No. DR1 PO4. Account No. 307-21-055-8515-00-10-000. Introduction: The intent of this agenda item is to seek City Council's approval for the City Manager to execute Change Order No. 4 with Brystar Contracting, Inc., (Brystar) of Beaumont, Texas, for drainage improvements, decreasing the contract by $412,362.05, to a new contract amount of $17,977,620.15. Project No. DR1PO4. Account No. 307-21-055-8515-00-10-000. Background: Pursuant to Resolution No. 18-231, the City of Port Arthur adopted the 2018 Disaster Recovery and Resiliency Plan (DRRP) for recovery activities following Hurricane Harvey. The City of Port Arthur, as part of the DRRP recovery activities, identified flood and drainage problems within the community of Stonegate. Pursuant to Resolution No. 20-021, Stuart Consulting Group, of Houston, Texas, was approved to provide design specifications and a final bid package for the Stonegate Drainage Improvement Project. Pursuant to Resolution No. 23-561, the City of Port Arthur's City Council approved awarding the Stonegate Drainage Improvement Project to Brystar for the amount of$18,672,548.00. "Remember,we are here to serve the Citizens of Port Arthur" 444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294 Pursuant to Resolution No. 24-060, the City of Port Arthur's City Council gave approval for the City Manager to enter into a professional engineering services contract for construction management and value engineering with Chica&Associates, Inc., (Chica)of Beaumont,Texas for the Stonegate Project. Pursuant to Resolution No. 24-187, approved by Port Arthur City's Council for Change Order No. 1 that addressed City staff, Chica, and Brystar performing value engineering on the project saving a total amount of$1,638,750.00. An additional amount of$686,859.00 was added to the contract for lowering the culvert boxes by one foot(1') at the golf course due to pipeline conflicts and also $101,201.10 was added to the contract for a reinforced concrete liner at the bottom of the ditch due to water table issues. The original contract amount of$18,672,548.00 was reduced by the net of$850,689.90, to the new contract amount of $17,821,858.10. A Field Order was issued for Oakmont Drive to build a conflict box to avoid conflict with Entergy's underground electrical line. An emergency letter dated November 14, 2024, to the City Manager outlined the additional scope of work needed. It was approved and signed with the understanding that a resolution regarding the Field Order would be presented to City Council thereafter. Pursuant to Resolution No. 24-510, approved by Council, Change Order No. 2 was submitted by Brystar Contracting, Inc. (Brystar) of Beaumont, Texas, to resolve an electrical conflict on Oakmont Drive, install an irrigation weir at Pond 3 on the golf course,reroute an existing irrigation line, add HDPE pipe(180 LF), install valves on existing transit lines, paving median to convert to a turning lane, and added 154 calendar days to the original contract completion date of December 24, 2025,to the new contract completion date of May 27, 2026. Also, to include the additional amount of $315,047.10, modifying the existing contract amount of$17,821,858.10, to the new contract amount of$18,136,905.20. A Field Order, dated May 9, 2025, approved and signed by the City Manager,was issued for the immediate installation of two line stops in the existing main feed water line to prevent a major water outage in the surrounding area for the additional cost of$67,813.00. It was discovered that the selected locations of the line stops were not part of the looped system, resulting in loss of water for the residents of Green Pointe Estates. A line stop was removed and a 6"temporary bypass was installed to supply water to the residents. This resulted in a fourteen day(14) delay and the additional cost of$18,203.00. A change order addressing this action would be presented to City Council as follow up to the Field Order. Pursuant to Resolution No. 25-223, Change Order No. 3 was submitted by Brystar for the 9th Avenue improvements behind the houses of the Greenway Pointe Estates Subdivision that addresses the Field Order's installation of the two 16"water main line stops. It also defined work that will remove and replace an existing sidewalk, install a manhole, install an inlet, install piping, modify an existing conflict box, and install overflow pipes at Ponds#5 and#6. Change Order No. 3 also increased the contract amount of $18,136,905.20 by $253,077.00 to the new contract amount of $18,389,982.20; also, the addition of eighty-nine (89) calendar days, changing the contract completion date of May 27, 2026 to the new date of August 24, 2026. Change Order No. 4 is being submitted by Brystar Contracting, Inc., of Beaumont, Texas, decreasing the contract in the amount of$412,362.05. The deductions are related to quantities not utilized, as listed in the Exhibit A. These additions will provide access roads to the two pump stations that are essential for operating the retention ponds, repair golf cart paths damaged during construction, replace 130LF water line to accommodate the installation of boxes on 9th Avenue, and the removal and replacement of "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 box culverts between the ponds as per the original design. Change Order No. 4 decreases the contract amount of$18,389,982.20 by$412,362.05, to the new contract amount of$17,977,620.15. Budget Impact: Funds are not impacted. Project No. DR1PO4. Account No.: 307-21-055-8515-00-10-000. Recommendation: It is recommended that the City of Port Arthur's City Council approve PR No. 24654 authorizing the City Manager to accept Change Order No.4 from Brystar Contracting Inc.,of Beaumont,Texas.The deductions are related to quantities not utilized, as listed in the Exhibit A; and the additions will provide access roads to the two pump stations that are essential for operating the retention ponds, repair golf cart paths damaged during construction,replace 130LF water line to accommodate the installation of boxes on 9a' Avenue, and the removal and replacement of box culverts between the ponds as per the original design. Project No. DR1PO4. Account No. 307-21-055-8515-00-10-000. "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 PR No. 24654 11/14/2025 RLD Page 1 of 7 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 4 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND BRYSTAR CONTRACTING, INC., OF BEAUMONT, TEXAS, FOR DRAINAGE IMPROVEMENTS DECREASING THE CONTRACT AMOUNT BY $412,362.05, TO A NEW CONTRACT AMOUNT OF $17,977,620.15. ACCOUNT 307-21-055-8515-00-10-000. PROJECT NO. DR1PO4. WHEREAS, pursuant to Resolution No. 18-231, the City of Port Arthur adopted the 2018 Disaster Recovery and Resiliency Plan (DRRP) for recovery activities following Hurricane Harvey; and, WHEREAS, the DRRP included mitigation planning and investment in infrastructure to rebuild/repair streets, utilities, public facilities, water, sewer, and drainage in addition to identifying areas in the 100-year flood zone frequently flooded during previous storms or significant rain events; and, WHEREAS, the community of Stonegate was selected as an area that has experienced significant flooding due to rain events, flash flooding and drainage related issues; and, WHEREAS, pursuant to Resolution No. 20-021, Stuart Consulting Group of Houston, Texas, was approved to provide design specifications and a final bid package for the Stonegate area; and, WHEREAS, the Stonegate Drainage Improvement Project was let for bidding under Bid Number P23-069 on September 9, 2023 and September 16, 2023, by the Purchasing Department; and, PR No. 24654 11/14/2025 RLD Page 2 of 7 WHEREAS, three (3) bids were received from Allco, LLC, of Beaumont, Texas; BDS Constructors, LLC, of Vidor, Texas; and Brystar Contracting, Inc., of Beaumont, Texas; and, WHEREAS, bids were opened, and evaluated by the Purchasing Department, the Public Works staff, and Stuart Consulting Group, on Wednesday, October 11, 2023, with Brystar Contracting, Inc., of Beaumont, Texas being the lowest qualified bidder for $18,672,548.00; and, WHEREAS, pursuant to Resolution No. 23-561, the Port Arthur City Council authorized the City Manager to enter into an agreement with Brystar Contracting, Inc., (Brystar) of Beaumont, Texas, for $18,672,548.00 for the Stonegate Drainage Improvement Project; and, WHEREAS, pursuant to Resolution No. 24-060, the Port Arthur City Council authorized the City Manager to enter into a professional engineering services contract for construction management and value engineering with Chica & Associates, Inc., of Beaumont, Texas for the Stonegate Project; and, WHEREAS, pursuant to Resolution No. 24-187, City Council approved Change Order No. 1 where City staff, Chica, and Brystar performed value engineering on the project, saving a total amount of $1,638,750.00. An additional amount of $686,859.00 was added to the contract for lowering the culvert boxes by one foot (1') at the golf course due to pipeline conflicts and also $101,201.10 was added for a reinforced concrete liner at the bottom of the ditch due to water table issues; and, PR No. 24654 11/14/2025 RLD Page 3 of 7 WHEREAS, Change Order No. 1 reduced the original contract amount of $18,672,548.00 by the net of $850,689.90, to the new contract amount of $17,821,858.10; and, WHEREAS, a Field Order was issued for Oakmont Drive that built a conflict box to avoid conflict with Entergy's underground electrical line and an emergency letter dated November 14, 2024, was sent to the City Manager outlining the additional scope of work needed; and, WHEREAS, pursuant to Resolution No. 24-510, approved by Council, Change Order No. 2 was submitted by Brystar Contracting, Inc. of Beaumont, Texas, to resolve an electrical conflict on Oakmont Drive, install an irrigation weir at Pond 3 on the golf course, reroute an existing irrigation line, add HDPE pipe (180 LF), install valves on existing transit lines, paving median to convert to a turning lane, and added 154 calendar days to the original contract completion date of December 24, 2025, to the new contract completion date of May 27, 2026; and, WHEREAS, Change Order No. 2 also modified the existing contract amount of $17,821,858.10 by $315,047.10, to the new contract amount of $18,136,905.20; and, WHEREAS, the emergency letter was approved and signed by the City Manager with the understanding that a resolution regarding the Field Order would be presented to City Council thereafter; and, WHEREAS, a Field Order, dated May 9, 2025, approved and signed by the City Manager, was issued for the immediate installation of two line stops in the existing main feed water line to prevent a major water outage in the surrounding area for the additional PR No. 24654 11/14/2025 RLD Page 4 of 7 cost of $67,813.00. It was also discovered that the selected locations of the line stops were not part of the looped system, resulting in the loss of water for the residents of Green Pointe Estates. A line stop was removed and a 6" temporary bypass was installed to supply water to the residents, resulting in a fourteen-day (14) delay and the additional cost of $18,203.00; and, WHEREAS, pursuant to Resolution No. 25-223 for Change Order No. 3, approved by the City of Port Arthur's Council, was submitted by Brystar for 9th Avenue improvements behind the houses of the Greenway Pointe Estates Subdivision that addresses the Field Order's installation of the two 16" water main line stops and defined work to remove and replace an existing sidewalk, install a manhole, install an inlet, install piping, modify an existing conflict box, and install overflow pipes at Ponds #5 and #6; and, WHEREAS, Change Order No. 3 also increased the contract amount of $18,136,905.20 by $253,077.00 to the new contract amount of $18,389,982.20 and the addition of eighty-nine (89) calendar days, changing the contract completion date of May 27, 2026 to the new date of August 24, 2026; and, WHEREAS, approval of PR No. 24654 authorizing the City Manager to execute Change Order No. 4 with Brystar Contracting, Inc. of Beaumont, Texas, decreasing the contract in the amount of $412,362.05. The deductions are related to quantities not utilized, as listed in the Exhibit A; and the additions will provide access roads to the two pump stations that are essential for operating the retention ponds, repair golf cart paths damaged during construction, replace 130LF water line to accommodate the installation of boxes on 9th Avenue, and the removal and replacement of box culverts between the PR No.24654 11/14/2025 RLD Page 5 of 7 ponds as per the original design is herein deemed an appropriate action, see Exhibit A; now, therefore; WHEREAS, Change Order No. 4 decreases the contract amount of $18,389,982.20 by $412,362.05, to the new contract amount of $17,977,620.15; and, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR, TEXAS: THAT, the facts and opinions in the preamble are true and correct; and, THAT, the City Manager of the City of Port Arthur is hereby authorized to execute Change Order No. 4 with Brystar Contracting, Inc. of Beaumont, Texas, decreasing the contract amount by $412,362.05. The deductions are related to quantities not utilized, as listed in the Exhibit A; and the additions will provide access roads to the two pump stations that are essential for operating the retention ponds, repair golf cart paths damaged during construction, replace 130LF water line to accommodate the installation of boxes on 9th Avenue, and the removal and replacement of box culverts between the ponds as per the original design; and, THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED this the day of , A.D., 2025, at a of the City Council of the City of Port Arthur, Texas, by the following vote: Ayes: Mayor: Councilmembers: PR No. 24654 11/14/2025 RLD Page 6 of 7 Noes: PR No. 24654 11/14/2025 RLD Page 7 of 7 Charlotte M. Moses Mayor ATTEST: Sherri Bellard City Secretary APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION: r —0 44/ Roxann Pais Cotroneo, Esquire Ron Burton, CPM (q�� behalf. o P) City Attorney City Manager APPROVED AS TO AVALIABILITY OF FUNDS: l� 1 Cy (_. y'- Lynda "Lyn" Boswell, M.A., ICMA-CM Director of Finance \//1. -01,4 /141i1V V' Suhail Kanwar, PE Director of Public Services/City Engineer kkPCliftonilliams, CPPB Purchasing Manager EXHIBIT A CITY OF PORN.111SR Nor m murOp .B.101.1 PV61I1527I.AroN2114 CI DA IIt oPnMt.sNTNUN CONTRACTOR -I RMVSTAR CONTRACNCA INC. TN.0011 61.41015 CHANGES IN...,P.A.ANINOR SPNCIFICATIONS AR.11ERNNI NI NON,NANG.0.1.12 NO,4 ANN..C01.04 QRAv15NA to reflect r61.iarml5uo03144 used lo roe eem.em0 e0190 project: Nmn No Wean.MN.,per Nem0elmpmn Unh ONtlnelOuemM USOPM. 0Nn6.1400um New Wan. New680005 $1Srwp1 OR 104..115.1116101414.441.403 $014M004 +0 564003:ON(POn0s1 Cr 00.000 525.00 61260.000.00 l?tle 51.115m.00 (5160u6.00i 60 REMOVE CON,IPA0I Sr 1710D 51200 5205,200.00 15.726 S160711.00 1$16,e55.001 ID 6EM060c0NCI5,505w641 5. 1,oEo 530.00 331000.00 890.16 $26,Rem If6ss6ml 9D REMOVE 6R0014C1 CON0(0004455000 0A1071 13 300 53000 69,010.00 166 06.980.00 156.400001 130 REMONC SilialPCI if 0,000 51000 $u,000.00 4c61 565,39620 51,290.00 1E0 CONC PIANO10'1 5v s,GDD 397.00 SH3,1W.00 3104 SOS9579m ($165,611001 170 CONC CURO(11 II) 1F 9,000 510.00 590..DO 5,19e. 551,10m 1535mam1 160 00101.20 Sv 950 $106.00 611I.60000 3t1 $116,61.00 30.0001 REx0ASE1NEw e.R51116•) ST 1000 53000 SGm.lp0.00 19,510.03 $5.,3561 IS17,605.101 200 OANIN.0RA1z0 LIME(1Cu01411 rah 325 5380.30 555,500.00 INS1 $63/Mm 1$11622001 110 UME TRTISUBGRADEI(6'1 w 13000 5600 $19a00 CO 11553 565,31500 IS?60i0O 0 RC Par 0601 t1 MO 5000.00 5156,..00 634 5117,60000 35,600.001 030 6155E140161 11 e00 561000 5105,0030.00 341 5311,070.00 1531330m1 500 SANITARY PIPE(PVC1101.1 (I 120 5630.00 651,000.00 60 425110040 320800.00 SOS 0071001144E NPE 1,0(4101 LI 65 567000 54355000 50 533400.00 1610050.001 520 METAL V GUARD FENCE 11 EAM 100 511000 S IL.00 0 Sem (511,0mm1 560 .000O5053EE5 PLAPw11(ae•1 0R 1 525m0.00 325,00.00 0 Sam 1515,000m1 975 1TN POINTING 10 10,000 63e00 $380.000,00 0 $0.m IS 31,000.0) 5l a01(m WATER MITER BOX CA 13 5650.a0 613050.00 0 $0.00 (SBA50m) S. REM AREL MAILBOX Ea 0 51500.10 51000000 0 $s,000A0 IS,...) 600 ADAww951T1'PE 51 EA 5 50,mD.00 $15,0..00 u 51160010 (530D0.001 610 Ts.NCR SA,En 595TEM5 O 01. 51m $1631.00 7,69 $1551m IS830001 610 BARRICADES.510N5.AND TRAFFIC CONTROL MO 16 51,e00.00 640500 co SO $56m000 511200400 690 O0N500e0 7617 000 0 24,000 53.00 511,000.00 2334 51,00320 I0609911601 700 RIP RAPISTONE COMMONI(0600(10WI TON 695 $12500 596,8)20D 35377 $483211i 114,6.53.901 COI 10.960A PDX CULSSRTS LS 1 591A1.00 59,145.06 0 $Om (291e.01 CO2/n1m ls0 CONE 0111ANE1110'1 Sv 1,5. $100 CO 5160,..00 761 $176,100m 51010,0 CO2/item190 R.0AS5111 w 0045116.1 Se Sao 530.00 S 11,I100.00 D 50m 151e600.e01 CO2/neml 3 e0850090250(60 X 0r0 a 120 $1100.00 15020D0.00 l $101,100.00 32.00. CO3/Item11 10 RB0SE INF.ea55116.1 56 530.00 $10000 6 0 $am IS sl CO3/nem060 RC PEI36m1 LI 1. 5.0.00 535,eoo.00 0 Sum 152.00. CO6 POND 0502ER1LOw(6DON00EW FLAP 03351 I0 1 510031 OD 52O5100 0 50.00 1520351101 CO3 POND R60NE5FCOW(1R0 LP 50PC VPRPSGATEI 15 1 $36,031.00 536,031.00 0 Sum 153611.051 NEN CART/ORMI PAIN 10 PUMP 5TA1I0N 112'04050'MNNRI L5 5441.100.00 $00n 1 $4A1,100.00 ' $41,20O00 Ntx ROCK ROAD TO PUMP STATION Ls 5103,0i3.00 50.00 i 5103,e23.00 51.023.00 sr. AVE TOPU4PSTATw11ul0LrcE/uus6 W7 01 5'wTLICBRII9 1NL., 5320.060.00 $O.DO 5129060m $1n.1.00 316. NNE 10 5146.100.00 5000 1 3166,1m00 $1u,600.00 REvanlRl a.D.mNnRCCr.EA Nu0w41s Rni RE6IAc0 5000.54 LINE CROSSING 9rN Avr is 536.195.00 $O.W 1 $34nsm f36.zf5m 50310r45 65,776,134600 55,361A53.95 5412061.05 UPON.CONTRACT CO..i .1-3 lz.zu ouxrDEDUCTml 1 1 i001..509.15 ()RIG.At.CONTRACT AMOUNT,.S NCT um.11m 10 ...NI Or TINS ClIANOR O F..NOa 5 1411062.. r1RCENTOr TM1SCMkNCr.OROCR NO.0 1,57150.PN 0.10.6 FINAL CO...CT A610501':5 14.677611.15