OFFICE OF THE CITY MANAGER
INTEROFFICE MEMORANDUM
Date: November 14, 2025
To: The Honorable Mayor and City Council
From: Ronald "Ron" Burton, CPM, City Manager
RE: P.R. NO. 24652 — Proposed Resolution authorizing an Agreement with
Southwestern Bell Telephone Company d/b/a AT&T for Removal and
Disposal of Existing Aerial Communication Cabling and Poles
Introduction:
This agenda item seeks the City Council's approval of Proposed Resolution No.
24652, authorizing the City Manager to execute an agreement between the City of Port
Arthur and Southwestern Bell Telephone Company d/b/a AT&T ("AT&T") for the
removal and disposal of existing aerial communication cabling and poles located within
the City's right-of-way and associated with the Fire Station No. 3 Construction Project
located at 2365 61 St Street.
Background:
The City has identified outdated and inactive aerial communication cabling and
associated poles that must be removed to facilitate ongoing and future improvements
within the public right-of-way. AT&T has provided a Custom Work Agreement outlining
the terms, conditions, and special construction requirements associated with
performing the removals.
The Agreement establishes a special construction cost of $37,401.27, subject to
AT&T's tariff and guidebook provisions and billed on an Actual Cost basis. The
Agreement also addresses customer obligations, potential cost adjustments due to field
conditions, early termination liability, indemnification, and payment requirements.
Budget Impact:
The total estimated cost for the special construction work is $37,401.27. Final billing will
be based on AT&T's actual cost, in accordance with the Agreement.
"Remember,we are here to serve the Citizens of Port Arthur."
P.O. Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
Recommendation:
It is recommended that the City Council approve Proposed Resolution No. 24652,
authorizing the City Manager to execute the Agreement with AT&T in substantially the
same form as attached, along with any related documents necessary to complete the
work.
"Remember,He are here to serve the Citizens of Port Arthur."
P.O. Box 1089 X Port Arthur,Texas 7764 1-1 089 X 409.983.8101 X FAX 409.982.6743
P.R. NO. 24652
11/14/2025 PDL
PAGE 1 OF 4
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE EXECUTION OF AN AGREEMENT
BETWEEN THE CITY OF PORT ARTHUR AND SOUTHWESTERN BELL
TELEPHONE COMPANY d/b/a AT&T FOR THE REMOVAL AND
DISPOSAL OF EXISTING AERIAL COMMUNICATION CABLING AND
POLES IN SUPPORT OF THE NEW CONSTRUCTION PROJECT FOR
FIRE STATION NO. 3, FOR A PROJECTED BUDGETARY AMOUNT OF
$37,401.27; FUNDING AVAILABLE IN CAPITAL FACILITIES ACCOUNT
NO. 307-21-049-8512-00-10-000; PROJECT NO. B00013.CON
WHEREAS, the City of Port Arthur ("City") has identified a need for the removal
and disposal of existing aerial communication cabling and poles located within the
municipal right-of-way adjacent to the Fire Station No. 3 Construction Project located at
2365 61st Port Arthur, Jefferson County, Texas; and
WHEREAS, Southwestern Bell Telephone Company d/b/a AT&T ("AT&T") has
provided a Custom Work Agreement ("Agreement") outlining the terms, conditions, and
special construction requirements necessary to remove and dispose of such aerial
facilities; and
WHEREAS, the Agreement specifies that the work constitutes special construction
and requires the payment of $37,401.27 as consideration for such special construction,
subject to AT&T's tariff and guidebook provisions, actual cost billing practices, and terms
governing changes in scope, field conditions, indemnification, and customer obligations;
and
WHEREAS, the Agreement further provides that pricing is guaranteed for sixty(60)
days from November 24, 2025, requires advance payment before work commences,
obligates the Customer to pay any additional charges resulting from actual cost, changes
in scope, differing field conditions, or unmet customer obligations, and includes additional
P.R. NO. 24652
11/14/2025 PDL
PAGE 2 OF 4
terms relating to early termination, limitation of liability, completion time estimates,
severability, interpretation, governing law, and successors and assigns; and
WHEREAS, the City Council finds it in the best interest of the City of Port Arthur to
enter into the Agreement for the removal and disposal of outdated aerial communication
cabling and poles in order to support ongoing municipal improvements and ensure the
safe and efficient use of public rights-of-way; and
WHEREAS, the Agreement is attached hereto as Exhibit "A", and the City Council
desires to authorize the City Manager to execute the Agreement in substantially the same
form as presented.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR, TEXAS:
THAT, the facts and opinions of the preamble are true and correct.
THAT, the City Council hereby approves the Agreement between the City of Port
Arthur and Southwestern Bell Telephone Company d/b/a AT&T for the removal and
disposal of existing aerial communication cabling and poles in support of the new
construction project for Fire Station No. 3, for a projected budgetary amount of
$37,401.27. Funding available in Capital Facilities Account No: 307-21-049-8512-00-10-
000; Project No. B00013.CON
THAT, the City Manager is hereby authorized to execute the Agreement in
substantially the same form as delineated in Exhibit "A".
THAT, a copy of the caption of this resolution be spread upon the minutes of the
City Council.
P.R. NO. 24652
11/14/2025 PDL
PAGE 3 OF 4
READ, ADOPTED, AND APPROVED this day of December 2025, at a
meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor:
Council members:
Noes:
Charlotte M. Moses, Mayor
ATTEST:
Sherri Bellard, TRMC, City Secretary
APPROVED AS •
Roxann Pais Cotroneo, City Attorney
APPROVED OR • DM 1ST •TION:
_.1
Ronald "Ron B . , CPM, City Manager
APPROVED AS TO THE AVAILABILITY OF FUNDING:
Lynda Boswell, .A., ICMA-CM Clifton illiams, CPPB,
Director of Finance Purchasing Manager
P.R. NO. 24652
11/14/2025 PDL
PAGE 4 OF 4
EXHIBIT "A"
1 5
AT&T
LETTER OF AGREEMENT FOR CUSTOM WORK
ESTIMATE OF ACTUAL COST
11/24/2025
Customer Name:CITY OF PORT ARTHUR
Billing Address:444 4TH STREET,PORT ARTHUR,TX 77640
Contact Name:PAMELA LANGFORD
Contact Email:PAMELA.LANGFORD@PORTARTHURTX.GOV
Contact Phone Number:(409)983-8296
Project Number:A05B9Z8
Work Order ID:CWO-44731
Site Location:2365 61ST ST,PORT ARTHUR,TX 77640
AT&T has received a request from you to perform the following work:
REMOVE EXISTING AERIAL COMMUNICATIONS CABLES AT F 2365 61ST ST.IN PORT ACRES,TEXAS.
CABLES WILL BE BURIED IN CONFLICT AREA AND POLES WHERE TELEPHONE ATTACHMENTS EXIST
WILL BE REMOVED ALONG WITH ASSOCIATED HARDWARE.ADDITIONAL CHARGES MAY APPLY IF
UNFORSEEN FIELD CONDITIONS ARE ENCOUNTERED THAT MAY REQUIRE ALTERNATIVE SOLUTIONS
TO CABLE REROUTING.
Estimated Actual Cost Quote
Engineering Labor $9,760.15
Construction Labor $10,501.61
Contractor Expense $14,999.55
Material Expense $2,639.96
Miscellaneous Expense $0.00
Subtotal $37,901.27
Less Credit/Payments $500.00
Total Balance Due $37,401.27
An advance payment based on the estimated cost of the special construction charges is required
before work can begin. At the completion of the project, an additional payment may be required if
costs exceed the estimated amount.A refund will be issued if actual costs are less than the estimated
amount.
This signed agreement and advance payment$37,401.27 must be received at the AT&T address shown
below before AT&T will proceed with any work.
This quote is only valid for 60 days from the date of this letter.
2 5
AT&T
CUSTOM WORK AGREEMENT
Project Number:A05B9Z8
Work Order ID:CWO-44731
This Custom Work Agreement ("Agreement") is entered into by and between CITY OF PORT ARTHUR
(Customer).And SOUTHWESTERN BELL TELEPHONE COMPANY(hereafter"AT&T") and hereby agree
to following terms and conditions:
1 Tariffs/Guidebooks. This Agreement is subject to and controlled by the provisions of AT&T's
tariffs/guidebooks as applicable and all such revisions to said documents as may be made from
time to time.
2 Special Construction. This Agreement is for the special construction as further described on
page 1,attached hereto, and incorporated herein by this reference ("Special Construction"). As
consideration for the Special Construction, Customer shall pay to AT&T $37,401.27. Advance
payment based on estimated cost is required before work will begin. Payment in full for the
remaining balance exceeding the advance payment based on actual costs is required within
thirty days after AT&T issues an invoice to the Customer for the Special Construction charges.
3 Price Quote. The price is guaranteed for 60 days from 11/24/2025. If the charges are not
accepted within 60 days the request will be canceled and a new request will need to be placed.
The second estimate may be higher than the price that was originally quoted.
4 Early Termination. Should Customer terminate or cancel this Agreement prior to the
completion of construction, Customer shall remain liable for the Special Construction Charges.
Customer acknowledges and agrees AT&T shall incur substantial up-front costs in connection
with its performance under this Agreement and that damages in the event of such early
termination or cancellation are not readily ascertainable and that in such event of early
termination payment of the Special Construction Charges is reasonable. Customer further
acknowledges and agrees that it hereby waives any right to contest such payment of the
Special Construction Charges for any reason,including, but not limited to reasonableness of the
charges,quality of the work,or timeliness of the work.
5 Limitation of Liability. AT&T's maximum liability arising in,out of or in any way connected to this
Agreement shall be as set forth in the tariffs and/or guidebooks, as applicable, and in no event
shall exceed Special Construction Charges paid by Customer to AT&T.
3 5
AT&T
6 Changes in Scope of Work. The parties recognize that this is an 'Actual Cost'contract. "Actual
Cost" means that Customer will be provided with a final bill after the completion of all work and
agrees to pay that final bill. The final bill will be calculated based on AT&T's billing practices and
work performed,which Customer agrees to accept.Customer understands and agrees that the
final bill for the Actual Cost may exceed the preliminary cost estimate that has been provided
for this work.Consequently,AT&T is not required to provide the Customer with prior notice that
the Actual Cost has exceeded the preliminary cost estimate prior to providing the final bill.
Further, if the Customer initiates changes in the scope of the work after AT&T has provided the
preliminary cost estimate or after executing this contract, the above cost estimate and this
contract are null and void. A new cost estimate must be provided based on the new scope of
work and a new contract entered. Additionally, if the contractor bid exceeds the estimated
contractor costs the applicant will be responsible for additional costs and a change order will be
issued for customer approval.Work will not commence until signed change order and additional
payment has been received.
7 Changes Due to Field Conditions. In the event there exists any conditions in the field that differ
from those that existed at the time AT&T provided the quote or from the time the Customer
executes the contract, AT&T shall bill and Customer shall pay any additional cost. Field
conditions that may alter the cost associated with this work include, but are not limited to,
conditions that exist below the surface of the ground and could not have been anticipated at
the time of the price quote, above ground barriers, Acts of God affecting the progress or
sequencing of the work, labor disputes and other conditions or circumstances that AT&T could
not have reasonably anticipated at the time the cost estimate was provided. Differing field
conditions are but one example of why the Actual Cost may exceed the preliminary cost
estimate. Further, items that Customer has agreed to provide in connection with the Special
Construction work, such as (but not limited to) providing conduit and/or handholes, must be
suitable to AT&T's purposes. If these items are not suitable or AT&T is forced to acquire or
provide them, it will result in increased costs that Customer agrees to pay.
8 Customer Obligations. Customer agrees to provide appropriate easements and/or rights of
way, as determined by AT&T, to AT&T for its lines and any facilities necessary for the Special
Construction work. Further, Customer agrees to provide and place suitable conduit and
handholes for AT&T's use in the Special Construction work. Should Customer not provide these
items, Customer understands and agrees that it will result in increased costs above the
estimate provided,which Customer agrees to pay.
9 Time to Complete. Any representation by AT&T, its contractors, or employees that the project
will be complete by a certain date or certain time period is strictly an estimate and not binding.
All estimated completion dates are subject to changing conditions in the field, changes in the
scope of the work,relocation of existing utilities not within AT&T's control,Acts of God,weather
delays, labor disputes, contractor disputes, pandemics and other conditions or circumstances
could not reasonably anticipate at the time of the estimate.
4 5
AT&T
10 Indemnification and Hold Harmless. Both parties, its agents, servants, and employees hereby
agree to indemnify and hold harmless each other, and its employees, agents and contractors,
from and against any and all claims, costs, expenses,judgments or actions for damage to
property or injury or death to persons, and/or arising from or relating to the work that is the
subject of this agreement, to the extent any such claims are caused by the negligent acts or
omissions of both parties, its agents,servants,or employees.
11 Miscellaneous.
A. Counterparts. This Agreement may be executed in one or more counterparts,each of which
when so executed shall be deemed to be an original, but all of which when taken together
shall constitute one and the same instrument.
B. Effect of Waiver. No consent or waiver, express or implied shall be deemed a consent to or
waiver of any other breach of the same or any other covenant,condition,or duty.
C. Headings. The headings, captions, and arrangements used in this Agreement are for
convenience only and shall not affect the interpretation of this Agreement.
D. Interpretation. The parties agree that this Agreement shall not be interpreted in favor or
against either any party. The parties further agree that they entered into this Agreement
after conferring with legal counsel, or after having a reasonable opportunity to confer with
legal counsel.
E. Applicable Law. This Agreement shall be governed and interpreted in accordance with the
laws of the state that the work site location is located without regard to that state conflict
of law principles.
F. Attorneys' Fees. If either party materially breaches this Agreement and should the non-
breaching party seek to enforce it rights through legal action, the prevailing party shall
recover from the other party all costs and expenses incurred, including, but not limited to,
reasonable attorneys'fees.
G. Authority. The signatories to this Agreement represent and warrant that they are duly
authorized to execute this Agreement.
H. No Precedent. Except for the matters resolved and released herein, this Agreement is of no
value and shall not be considered precedent for resolving any dispute that may arise in the
future.
I. Severability. Any provision of this Agreement held by a court of competent jurisdiction to be
invalid or unenforceable shall not impair or invalidate the remainder of this Agreement and
the effect thereof shall be confined to the provision so held to be invalid or unenforceable.
J. Successors and Assigns. This Agreement is binding upon and shall inure to the benefit of the
parties and their respective successors and assigns.
12 Final Agreement. THIS AGREEMENT REPRESENTS THE ENTIRE AND FINAL EXPRESSION OF THE
PARTIES WITH RESPECT TO THE SUBJECT MATTER HEREOF. EXCEPT AS PROVIDED HEREIN,THIS
AGREEMENT MAY NOT BE CONTRADICTED BY EVIDENCE OF PRIOR, CONTEMPORANEOUS OR
SUBSEQUENT ORAL AGREEMENTS OF THE PARTIES; THERE ARE NO UNWRITTEN ORAL
AGREEMENTS BETWEEN THE PARTIES.
Page 5 of 5
AT&T
IN WITNESS WHEREOF,the parties hereto have caused this Agreement to be executed by their duly
authorized representative on the dates set below.This quote is only valid for 60 days from the date of
this letter.
Project Number:A05B9Z8
Work Order ID:CWO-44731
Date Quote Expires:01/24/2026
AT&T Design Engineer: RAY HILLIN
AT&T Engineer Email:RH0424@att.com
Please send check payable to AT&T CWO along with signed agreement to:
14575 PRESIDIO SQUARE BLVD,FLOOR 1,ROOM 111, HOUSTON,TX 77083
Signature:
Email: pamela.langford@portarthurtx.gov
Title:
Company:
Signature:
Email: db7217@att.com
Title:
Company: