HomeMy WebLinkAboutPR 24699: POMPEIIAN VILLA, PHASE IV RESTORATION WORK P.R.No. 24699
12/10/2025 AJS /TNR
Memorandum
City of Port Arthur, Texas
Robert A. "Bob"Bowers Civic Center
To: The Honorable Mayor and City Council
Through: Ron Burton, City Manager
From: Adam J Saunders, Civic Center Dir
RE: Proposed Resolution No. P.R. 24699
REQUEST:
At Pompeiian Villa, much repair and maintenance are needed. In June 2025, the Council passed
Res 25-267 for Phase IV restoration work to Pompeiian Villa to Mike Barnett Construction of
Port Neches, Texas. In November 2025, the City Council approved Resolution No. 25-519,
authorizing Change Order No. 01. This change was necessitated by unforeseen delays
encountered during construction, specifically related to the delayed delivery and limited
availability of HVAC mechanical equipment essential for project completion. As a result of these
delays, Change Order No. 01 authorized a 36-calendar-day extension, thereby establishing a new
completion date of December 29, 2025.
Due to the fact that this restoration is subject to approval by the Texas Historical Commission
(THC), many steps are required. A small portion of the exterior wall must be repaired due to
cracks caused by foundation settlement and holes created by the abandonment of electrical
conduits through the exterior walls. THC requires the use of plaster with the same formula as the
original building. Since the plaster on this building has never been analyzed, a sample of the
original plaster must be sent to a lab for analysis. The requested extension of time is based upon
the time needed to analyze the plaster and produce a plaster mixture with the same components
and volumes of the original 1900s plaster. Upon the contractor's receipt of the plaster mixture
from the manufacturer, the contractor can make repairs to the holes created by foundation
settlement and demolition required for the new electrical service. Since there are no prior
analyses of the plaster in Pompeii Villa, analysis is required prior to the placement of new plaster
in the building's façade.
This analysis and manufacturing timeline will add 98 days to the contract. It should be noted
that this does not delay the completion of all other aspects of the Phase IV restoration. Once
other aspects of the restoration are completed, full access to the building will be available. This
delay deals only with a small portion of the exterior. The only contract delay will be the final
payment to close out the project and establish a substantial completion date. Otherwise, there
will be no interruption in the use of the building beyond the current project completion date.
Due to this delay, a change order is requested to add additional days to the Contract Time. The
days to be added would be Change Order #2, totaling ninety-eight days. There is no change to
the cost of the agreement.
ANALYSIS/CONSIDERATION:
P.R.No. 24699
12/10/2025 AJS/TNR
There are numerous repairs needed at the building. Phase IV of repairs and restoration of the
Pompeiian Villa is underway. Change Order#2 to the Phase IV repairs are needed due to delays
in exterior plaster testing.
RECOMMENDATION
A resolution authorizing the City Manager to enter into an agreement with Mike Barnett
Construction of Port Neches, Texas for Change Order#2 to Phase IV repairs and maintenance of
the Pompeiian Villa in the amount of ninety-eight days added to the Contract Time.
BUDGETARY AND FISCAL EFFECT
None
STAFFING EFFECT
None
P.R. No. 24699
12/10/2025 AJS /TNR
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 02 TO THE CONTRACT BETWEEN THE CITY
OF PORT ARTHUR AND MIKE BARNETT CONSTRUCTION OF PORT
NECHES, TEXAS, FOR PHASE IV REPAIRS TO POMPEIIAN VILLA
THAT INCREASES THE CONTRACT TERM BY NINETY-EIGHT DAYS
TO A NEW COMPLETION DATE OF APRIL 6, 2026, AT NO
ADDITIONAL COST.
WHEREAS, in June 2025, the City Council adopted Resolution No. 25-267 approving
an agreement with Mike Barnett Construction of Port Neches, Texas, for Phase IV repairs and
restoration to the Pompeiian Villa in the amount of $415,250.00; and
WHEREAS, in November 2025, the City Council approved Resolution No. 25-519,
authorizing Change Order No. 01. This change was necessitated by unforeseen delays
encountered during construction, specifically related to the delayed delivery and limited
availability of HVAC mechanical equipment essential for project completion. As a result of these
delays, Change Order No. 01 authorized a 36-calendar-day extension, thereby establishing a new
completion date of December 29, 2025; and
WHEREAS, the Phase IV restoration work at the Pompeiian Villa is subject to review
and approval by the Texas Historical Commission (THC), and compliance with THC
requirements is mandatory for the preservation of the historic integrity of the structure; and
WHEREAS, a limited portion of the exterior façade requires repair due to cracks caused
by historic foundation settlement and openings created by the abandonment and removal of
electrical conduits through the exterior walls; and
WHEREAS, the THC requires that all exterior plaster repairs utilize a plaster mixture
consistent in composition, formulation, and appearance with the original early 1900s plaster used
in the construction of the Pompeiian Villa; and
P.R.No. 24699
12/10/2025 AJS /TNR
WHEREAS, because the original plaster composition has never been previously
analyzed, samples of the existing plaster must be extracted and submitted to a laboratory for
testing and analysis in order to determine the appropriate formulation, followed by the
manufacturing of a matching plaster mixture; and
WHEREAS,the time required for laboratory analysis, formulation, and production of the
historically compatible plaster mixture necessitates an extension of the Contract Time; and
WHEREAS, this testing and manufacturing process will require an additional ninety-
eight (98) days, but will not delay or interrupt the completion of the remaining Phase IV
restoration work, nor interfere with the use of the building beyond the current project scope, and
will affect only the final close-out, final payment, and establishment of the substantial
completion date; and
WHEREAS, Mike Barnett Construction of Port Neches, Texas, has submitted Change
Order No. 02 requesting an extension of the Contract Time by ninety-eight (98) calendar days,
establishing a new substantial completion date of April 6, 2026, with no increase in the contract
price; and
WHEREAS, the City Council finds that approval of Change Order No. 02 is in the best
interest of the City and is necessary to ensure compliance with Texas Historical Commission
requirements while preserving the historic character of the Pompeiian Villa.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR,TEXAS:
Section 1. That the facts and opinions in the preamble are true and correct.
Section 2. That The City Manager is hereby authorized and directed to execute
Change Order No. 02 to the contract with Mike Barnett Construction of Port Neches, Texas, for
P.R.No. 24699
12/10/2025 AJS/TNR
Phase IV repairs to the Pompeiian Villa, extending the Contract Time by ninety-eight(98) days to
a new substantial completion date of April 6, 2026, at no additional cost to the City, in
substantially the same form as attached hereto and incorporated herein as Exhibit"A."
Section 3. That a copy of the caption of this Resolution be spread upon the Minutes
of the City Council.
READ, ADOPTED, AND APPROVED, this day of 2026 AD, at a
Regular Meeting of the City Council of the City of Port Arthur, Texas by the following Vote:
AYES: Mayor:
Councilmembers:
NOES:
Charlotte M. Moses, Mayor
ATTEST:
Sherri Bellard, City Secretary
P.R. No. 24699
12/10/2025 AJS /TNR
APPROVED AS TO FORM:
Roxann Pais Cotroneo
City Attorney
APPROVED F: ' AD►� INISTRATION:
&XII*/
Ronald Burton, C'
City Manager
APPROVED AS TO
FUND AVAILABILITY:
Lynda Boswell, M.A., ICMA-CM
Director of Finance
Clifton Williams, CPPB
Purchasing Manager
EXHIBIT "A"
CHANGE ORDER
PROJECT: COPA-Pompeii Villa-Phase IV CHANGE ORDER NO: 002-Days
CONTRACTOR: Mike Barnett Construction DATE: 12.02.2025
1701 Port Neches Ave ARCHITECT'S PROJECT NO.: 22033
Port Neches, Texas 77651 CONTRACT DATE: 06.03.2025
CONTRACT FOR: historical restoration
This Contract is changed as follows:
DI-SCRIP TION t'NII (jlY t \Il S I1l'I. TOTALS
4.1 Our request for 98 additional days is in direct relation to the
approved change order for the Palster repairs. When the
initial request was made for these repairs,we were not aware
of the timeline needed for the testing.We were in the process
of Investigating the possibility that prior test results might be
available thus eliminating the need for further tests.We have
attached a copy of the scheduling provided by Marsh
Waterproofing for the testing and repairs timeline.
Additional days 98
SUBTOTAL $ -
CONTRACTOR'S FEE $ -
TOTAL $ -
GRAND TOTAL $ -
**See attached breakdown
Not valid until signed by the Owner,Architect and Contractor
The original Contingency Sum was $ 30,000.00
Net change by previously authorized Change Orders-Contingency $
l'he Contingnecy Sum prior to this Change Order-Contingency was $ 30,000.00
The Contingency Sum will be decreased by this Change Order-Contingency in the amount of $ 5,821.20
The new Contingency Sum including this Change Order-Contingency will be $ 24,178.80
The original Contract Sum was $ 415,250.00
Net change by previously authorized Change Orders $The Contract Sum prior to this Change Order was $ 415,250.00
The Contract Sum will be increased by this Change Order in the amount of $The new Contract Sum including this Change Order will be $ 415,250.00
The Contract Time will be increased by zero(98)days
"I'he date of Substantial Completion as of the date of this Change Order therefore rincreases to 6-Apr-26
NOTE:The summary does not reflect changes in the Contract Sum or Contract Time which have been authorized by Construction Change Directive.
The LaBiche hite 1 roup,Inc. Mike Barnett City of Port Arthur
79 1 c 01 1701 Port Neches Ave 3401 Culture Ctr. Dr.
Port ec es,T 7 651 Port Arthur,Texas 77640
By: By: By:
Date: Z Date: '12/525 Date:
PED '4R
A. N. Lae ,i
(_-'1oco � �� m
w 0 _ m n
CC
•
11592 P
4r' OF
Page 1 of 1
MIKE BARNETT
CONSTRUCTION CPR 4 . 1
71,1ng,n S!nty. 1965
1701 Port Neches Ave PROJECT: #22033
Port Neches,Texas 77651 Pompeiian Villa-Phase 4
(409)727-5673 1953 Lakeshore Dr.
Port Arthur,Tx 77641
CHANGE PROPOSAL REQUEST
TO: LaBiche Architectural Group, Inc FROM: Mike Barnett Construction
7999 Gladys Ave Ste 101 1701 Port Neches Ave.
Beaumont,Texas 77707 Port Neches,Texas 77651
Attn: Dohn Labiche Russell Bourgeois
CHANGE PROPOSAL 4.1 DATE: 11/25/25
REFERENCE: Plaster Repairs SCHEDULE IMPACT: 98 DAYS =( DEC29TH THRU APR 6TH)
DESCRIPTION OF CHANGE: ADDITIONAL CONTRACT EXTENSION DUE TO TESTING TIME
Our request for 98 additional days is in direct relation to the approved change order for the Palster repairs.When the
request was made for these repairs,we were not aware of the timeline needed for the testing.We were in the process
Investigating the possibility that prior test results might be available thus eliminating the need for further tests.
We have attached a copy of the scheduling provided by Marsh Waterproofing for the testing and repairs timeline.
DESCRIPTION UNIT QTY UNIT $ TYPE TOTALS
1. Additional 98 days extension to April 6th 2026
Sample testing Dec is`to March is`2026
Repairs upon receipt of test result to 3/31/26
Final paint and re trim/clean up-4/6/26
SUBTOTAL:
CONTRACTOR'S FEE:
SUBTOTAL:
SALES TAX:
CHANGE PROPOSAL GRAND TOTAL:
4
| 3-
4 ,
| \
§ ;^
« ;
! e
/ : j
i yPI
! \
( /
| -\.
\§ '
k //
\
] ,:
A \\f
, w!
|
« |
1 $
2
s «
*
2 3 /l
} *
•
.4. I
! .
q , - § } ) } §
§ � - — . .
ƒ - 9 \ / ) 7
2 q e » \
P,
; \
\ S. i !
CL d ! 7 f t.
}
\ ' < D ° 2
\ «
{ 7 •;
/ ti .9 t. ƒ i } )
ro ) . < \ % ! \ ! !
| j
P.
g SEE
■ X
f rd
,
. .
.
§ XX
13
,• #
1
411
) � « �
!
% �
! m
§ / /
$
0_
2
! 9_d
n
! ,
� \
,
! ; .
§
\
Z
A gl
2 -
��
'
14 ; 0
j t�--
a,
2 2�
t ��t
}
MIKE BARNETT
CONSTRUCTION
CITY OF PORT ARTHUR - POMPEII VILLA PHASE IV
"Foundation leveling and MEP Upgrades"
Updated Job Schedule based upon extension#2
Plaster repairs
City of Port Arthur-POMPEII VILLA 11/25/2025
1953 Lakeshore Dr.
Port Arthur,Texas TX 77640
We at Mike Barnett Construction are providing you with the following UPDATED extended
construction schedule for the project listed. This schedule is based upon the availability of materials
for the HVAC units and the most recent back-order date from the supplier.
This schedule is based upon the current job completion status to date and the pending items until
completion.
This schedule is based upon our request extension time and the materials current delivery and
availability
• Interior chandelier removed by others and repairs by others.
Week 4: Aug 25th to 30th
• HVAC unit 1 trim out.
• First HAVC Unit Install-Phase 1-Complete and commissioned into service.
Week 6: Sept 8th to 13th
• Second HAVC Unit Install-
Week 7: Sept 15th to 20th
• HVAC unit Phase 2 trim out.
• Second HAVC Unit Install-Phase 2-Complete and commissioned into service.
• Interior patch repairs begin if needed.
Week 9: Sept 29th to Oct 4th
• Third HAVC Unit demolition and Install-Phase 3 (Side 3)-begins
• Foundational leveling on Phase2 - Drill and Pour under ream piers
• Interior patch repairs as needed.
Week 11: Oct 13th to Oct 17t''
• ALL HAVC INTERIOR UNITS ARE BACKORDERED UNTIL 11/5/2025
• Interior chandelier removed by others and sent out for repairs.
• All foundation under ream piers drilled.
• Pouring Under ream piers
• Electrical interior trim 85%Completed
Mike Barnett Construction,Inc.,1701 Port Neches Ave.,Port Neches,TX 77661 Phone(409)727-5673 Fax(409)727-2906
MIKE BARNETT
CONSTRUCTION
• All Underneath wood sill structural repairs are completed
• Fire Alarm Installation 90%completed
• All Plumbing aspects are completed.
Week 12: Oct 20"to Oct 25`h
• Electrical service set to begin and home run tie ins
• Fire Alarm finalized this week.
• Interior patch repairs pending RFI regarding HVAC grills
• New conduit for fountain
• Foundation pier pour finalize and blocks and shims installed.
Week 13: Oct 27th to Nov l".
• Foundation soil debris and clean up
• Foundation leveling finalize
• Electrical service trimmed out completely
• Set HVAC electrical disconnects
• Set HVAC EXTEIROR condenser units.
Week 14:November 3'd to 8`h
• Electrical connection to all exterior HVAC condenser units finalized
• Spray Foam Underneath begins
• Complete all electrical trim out and service transfer.
• Begin Preliminary HVAC Ductwork installation based upon Grills verification
Week 15:Nov 10`h to 15`h
• Spray foam continues.
• Preliminary HVAC Ductwork installation-continues
• Interior wall repairs at Grill opening
• Interior HVAC units' arrival due this week.
Week 16:Nov 17 to 22"d
• Finalize Interior wall repairs
• Installation of unit 1-1
• Electrical connection for 1-1 completed
• Reinstall Chandiler
Week 17:Nov 24`h to 29th (Thanksgiving week)
• Interior wall repairs
• Installation of unit 1-3 installed
Week 18: Dec ls`to 6th (PLASTER REPAIRS Contract extension Begins)
• Finalize Interior wall repairs
• Installation of unit 1-2 installed
• Electrical connection for 1-3 and 1-2 completed
Mike Barnett Construction,Inc.,1701 Port Neches Ave.,Port Neches,TX 77651 Phone(409)727-5673 Fax(409)727-2905
MIKE BARNETT
CONSTRUCTION
• Plaster samples to be acquired this week.
Week 18: Dec 8th to 13th
• Complete All HVAC installations
• Attic Insulation begins
• Start Copulation of Close out documents.
• Third party Mortar Analysis Shipping—TESTING time frame begins
Week 18: Dec 15th to 20`h
• Attic installation completed
• HVAC Factory start up and Air balance-based upon availability
• Develop Punchlist
• Begin punch list repairs.—Excluding Plaster repairs/paint touch up/final clean up
• Start the project clean up.
• Finalize project clean up.-INITIAL
• Remove all temporary and construction equipment.
• Third party testing company closed for holidays( 12/19 to 1/5)
Week 18: Dec 22nd to 27th(Christmas holiday)
• Finalize project clean up.Making it ready for upcoming plaster repairs
• Finalize Close out documents.—MOVE to end of Project time line
Week 18: Dec 29th to Jan 3rd 2026
• Third party testing company closed for holidays( 12/19 to 1/5)
• ALL OTHER ASPECTS OF THE PROJECT WILL BE COMPLETED EVEN HVAC TRIM
OUT AS POSSIBLE.ALL OTHER REPAIRS WILL BE COMPLETED SO THE BUILDING
CAN BE TURNED BACK OVER TO THE CITY UNTIL SUCH TIME AS PLASTER REPAIRS
CAN BE DONE
DEC 29TH TO MARCH 1ST 2026-Waiting for the test results of the samples.
March 1"to March 31"-Plaster repairs By Marsh Waterproofing
April Pt—April 6th—Painting touch ups/Cleanup/HVAC Re trim out.
This schedule extension is due to the testing of plaster materials availability and the delays that are connected to
the completion of the project.
We appreciate your review of this matter.
Sincerely,
Russell Bourgeois.