Date: March 4, 2026
To: The Honorable Mayor and City Council
Through: Ron Burton, CPM, City Manager
From: Suhail Kanwar, P.E., M.S., CFM, Director of Public Services/City Engineer
RE: PR No. 24826: Request for Approval of Amendment No. 1 — Redbird Street Rehabilitation
Project — Green Avenue to Jefferson Drive. Project No. ST5106.CON Street Capital Account
No. 307-21-053-8517-00-10-000. PaveCon, LTD, of Houston, Texas
Introduction:
The intent of this memorandum is to request City Council's approval of Amendment No. 1 to the construction agreement
with PaveCon, LTD, of Houston, Texas (PaveCon), for the Redbird Street Rehabilitation Project — Green Avenue to
Jefferson Drive,for a 100-calendar-day time extension.
Background:
Due to the large number of streets needing repair, Purchasing has sought additional ways to bring in more
contractors to repair them. Purchasing found PaveCon as a contractor on the BuyBoard Cooperative Contract
for road repair. Purchasing and Engineering met with the PaveCon representative and requested a quote for the
rehabilitation of Redbird Street - Green Avenue to Jefferson Drive. PaveCon also met with Water Utilities
{ regarding utility work needed on Redbird Street, Green Avenue, and Jefferson Drive. PaveCon submitted a quote
of$678,349.66 for this work.
Pursuant to Resolution No.25-3654,the City Council awarded the construction contract to PaveCon for a contract amount
of$678,349.66 for the rehabilitation of Redbird Street—Green Avenue to Jefferson Drive,extending from Sabine Avenue
to Neches Avenue, at either end of the street.
Amendment No. 1 is being submitted by PaveCon for a 100-calendar-day extension due to the unknown condition of the
existing sewer line,in the event the sewer line needs to be replaced. It is assumed that approximately 650 LF of existing
sewer line and 10 sewer taps will need to be replaced between Wignall Avenue and Jefferson Drive. These changes have
no impact on the contract price.
Budget Impact:
Project No. ST5106.CON Street Capital Account No. 307-21-053-8517-00-10-000.
Recommendation:
It is recommended that the City of Port Arthur's City Council approve PR No. 24826 for Amendment No. 1 to the
construction agreement with PaveCon,the Redbird Street Rehabilitation Project—Green Avenue to Jefferson Drive, for
a 100-calendar-day time extension. Project No. ST5106.CON.
"Remember,we are here to serve the Citizens of Port Arthur"
444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
CAUsers\trotibi_ch\AppData\Local\Microsoft\Olk\Attachments\ooa-d7e954fa-90ac-4575-8ab5-16073aacf6dc\3d4b54b7c9e6b26fcea331b11daaecOf0269cf4d8a6e0362b18bc665081d3aa9\Agenda
M emo_PaveCon_CO 1.docx
PR 24826
03/04/2026 RLD
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE AMENDMENT NO. 1 TO THE CONSTRUCTION
CONTRACT WITH PAVECON, LTD., OF HOUSTON, TEXAS,
FOR THE REDBIRD STREET REHABILITATION PROJECT
FROM GREEN AVENUE TO JEFFERSON DRIVE; PROVIDING
FOR A (100) CALENDAR DAY TIME EXTENSION; PROVIDING
FOR FUNDING FROM STREET CAPITAL ACCOUNT NO. 307-
21-053-8517-00-10-000, PROJECT NO. ST5106.CON
WHEREAS, the Engineering Department of the City of Port Arthur conducts periodic roadway
condition assessments and reviews historical maintenance data to identify streets requiring
reconstruction, remediation, or rehabilitation; and
WHEREAS,based upon such assessments, Redbird Street between Green Avenue and Jefferson
Drive was identified as requiring rehabilitation and was recommended for inclusion in the City's street
improvement program; and
WHEREAS, due to the significant number of streets in need of repair, the Purchasing Division
explored additional procurement methods to increase contractor participation and expedite street
rehabilitation projects, including the use of cooperative purchasing programs; and
WHEREAS, the Purchasing, Utilities, and Engineering Departments jointly identified PaveCon,
Ltd., of Houston, Texas, as a qualified contractor through the BuyBoard Cooperative Purchasing
Program; and
WHEREAS, the City provided PaveCon, Ltd. with a bid table, project layout, and the City of
Port Arthur's applicable standards and specifications for the purpose of obtaining a cost proposal for the
rehabilitation of Redbird Street from Green Avenue to Jefferson Drive; and
WHEREAS, PaveCon, Ltd. submitted a BuyBoard-compliant proposal in the amount of
$678,349.66 for the Redbird Street Rehabilitation Project; and
WHEREAS, staff from the Utilities and Engineering Departments reviewed the proposal and
determined that the pricing submitted by PaveCon, Ltd. was reasonable and competitive with similar
street rehabilitation projects; and
WHEREAS, Chapter 271, Subchapter D, of the Texas Local Government Code authorizes
municipalities to participate in cooperative purchasing programs through a resolution adopted by the
governing body, including programs such as the BuyBoard Cooperative Purchasing Program, as an
alternative to traditional competitive bidding; and
PR 24826
03/04/2026 RLD
WHEREAS, pursuant to Resolution No. 25-365, the City Council authorized a construction
contract with PaveCon, Ltd., in the amount of$678,349.66 for the Redbird Street Rehabilitation Project
from Green Avenue to Jefferson Drive; and
WHEREAS, during the course of project planning and coordination with the Utilities
Department, it was determined that the existing sanitary sewer line within the project corridor may
require replacement due to unknown field conditions; and
WHEREAS, it is anticipated that approximately 650 linear feet of existing sewer line and
approximately 10 sewer service taps located between Wignall Avenue and Jefferson Drive may require
replacement depending on the condition of the existing infrastructure; and
WHEREAS, PaveCon, Ltd. has requested Amendment No. 1 providing for a 100-calendar-day
extension of the contract time to accommodate potential utility replacement work and associated delays;
and
WHEREAS, the proposed amendment does not increase the contract price and is necessary to
allow sufficient time to address potential sewer line replacement if field conditions require such work;
and
WHEREAS, City staff recommends approval of Purchase Requisition No. 24826 and
Amendment No. 1 to the construction contract as being in the best interest of the City of Port Arthur.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PORT ARTHUR, TEXAS:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, the City Council hereby approves Amendment No. 1 to the construction contract with
PaveCon, Ltd., of Houston, Texas, for the Redbird Street Rehabilitation Project from Green Avenue to
Jefferson Drive, providing for a (100) calendar day extension of the contract time due to unknown field
conditions related to the existing sewer line and the potential replacement of approximately (650) linear
feet of sewer line and (10) sewer service taps between Wignall Avenue and Jefferson Drive, as more
particularly described in Exhibit "A"; and
THAT, funding for the project is available in Street Capital Account No. 307-21-053-8517-00-
10-000, Project No. ST5106.CON.
THAT, a copy of the Resolution shall be spread upon the Minutes of the City Council.
PR 24826
03/04/2026 RLD
READ, ADOPTED AND APPROVED this the day of , A.D., 2026, at a
of the City Council of the City of Port Arthur, Texas, by the following vote:
Ayes:_ Mayor:
Councilmembers:
Noes:
Charlotte M. Moses
Mayor
PR 24826
03/04/2026 RLD
Page 4 of 4
ATTEST:
Sherri Bellard, TRMC
City Secretary
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION
etk r
alf?%1
Roxann Pais Cotroneo, Esq. Ron ;urt �CM
City Attorney City M J ger
APPROVED 0 AV ABILITY OF FUNDS:
Ly a (Lyn) oswell, MA, ICMA-
Fi ante Dire or
Suhail Kanwar, PE 3 — 14-24?—
Director of Public Services/City Engineer
Clifton Williams, CPPB
Purchasing Manager
EXHIBIT A
Time Extension Proposal PAVE......4„........„
Redbird St Rehabilitation Houston Division
City of Port Arthur Public Works 9900 Windfern Rd
Redbird St(Green Ave.to Jefferson Dr), Port Arthur TX Houston Tx
BuyBoard # 700-23
Due to the unknown condition of the existing sewer tine,Pavecon is requesting a contract extension of 100 days in the case that the
sewer line will need to be replaced. It is assumed approximetly 650 LF of existing sewer line and 10 sewer taps will need to
be replaced between Wignall Ave and Jefferson Dr.
Estimated Sewer Line Replcament-100 Calender Days
s
4...1,, -4 44ir :4: 1 f'd: ir r , ot,t'..,`i" 4, ,, , ' ,
'''' ' 01: 1- ' 'rff!' t 7:.'';',,,t74 :44;, '„11--' - .
s .
'
.. *e R WU VI n,s411141 P
}' i^ air
,--
is sa
r;
dt3i 'ttlefy h i
ACCEPTED: PAVECON, LTD.
Tristan Frerich
City of Port Arthur Senior Project Manager
Pavecon LTD. March 3, 2026
Corporate Otfice P.O.Box 535457,Grand Prairie,TX 75053• 3022 Roy Orr Blvd.,Grand Prairie,TX 75050